Individual Income Taxes
43rd Edition
ISBN: 9780357109731
Author: Hoffman
Publisher: CENGAGE LEARNING - CONSIGNMENT
expand_more
expand_more
format_list_bulleted
Question
Chapter 18, Problem 57P
a.
To determine
Provide information of the effects of the transactions and incidents on the taxable income of W Company for the year 2019 and 2020.
b.
To determine
Provide information of the effects of the transactions and incidents on the taxable income of W Company for the year 2019 and 2020. Assume that W Company had $100,000 of accumulated costs under the contract at the end of the year 2019.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,to construct a four-story office building. At that time, Curtiss estimated that it would take between two and threeyears to complete the project. The total contract price for construction of the building is $4,000,000. Curtissconcludes that the contract does not qualify for revenue recognition over time. The building was completed onDecember 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs tocomplete the contract, and accumulated billings to Axelrod under the contract were as follows:At 12-31-2018 At 12-31-2019 At 12-31-2020Percentage of completion 10% 60% 100%Costs incurred to date $ 350,000 $2,500,000 $4,250,000Estimated costs to complete 3,150,000 1,700,000 –0–Billings to Axelrod, to date 720,000 2,170,000 3,600,000Required:1. For each of the three years, prepare a schedule to compute total gross profit or loss to be…
On July 1, 2017, Dinar obtained a contract to construct a building. The building was estimated to be built at a total cost of P15,000,000 and is scheduled for completion on October 2019. The contract contains a penalty clause to the effect that the other party was to deduct P35,000 from the contract price for each week of delay. On the other hand, if the contractor was able to finish the building earlier than agreed, it will be rewarded an amount equal to P50,000 for every month of early completion. Furthermore, cost escalation clause was included in the contract. In 2018, the estimated costs of particular construction material amounting to P520,000 were bought for P780,000. The increase in the contract price related to this cost escalation was approved by the client. Completion was delayed for 4 weeks. The records show:
2017
2018
2019
Costs incurred
P1,750,000
6,440,000
1,085,000
Estimated cost to complete
7,000,000
1,810,000
--
Progress billings…
On January 1, 2020, Gordon Co. enters into a contract to sell a customer a wiring base and shelving unit that sits on the base in exchange for $3,000. The contract requires delivery of the base first but states that payment for the base will not be made until the shelving unit is delivered. Gordon identifies two performance obligations and allocates $1,200 of the transaction price to the wiring base and the remainder to the shelving unit. The cost of the wiring base is $700; the shelves have a cost of $320.
Instructions
a. Prepare the journal entry on January 1, 2020, for Gordon.
b. Prepare the journal entry on February 5, 2020, for Gordon when the wiring base is delivered to the customer.
c. Prepare the journal entry on February 25, 2020, for Gordon when the shelving unit is delivered to the customer and Gordon receives full payment.
Chapter 18 Solutions
Individual Income Taxes
Ch. 18 - Prob. 1DQCh. 18 - Prob. 2DQCh. 18 - Prob. 3DQCh. 18 - Prob. 4DQCh. 18 - Prob. 5DQCh. 18 - Prob. 6DQCh. 18 - Prob. 7DQCh. 18 - LO.2 In 2019, the taxpayer became ineligible to...Ch. 18 - LO.2 Osprey Corporation, an accrual basis...Ch. 18 - Prob. 10DQ
Ch. 18 - Prob. 11DQCh. 18 - Prob. 12DQCh. 18 - LO.2 Emerald Motors is an automobile dealer. The...Ch. 18 - Prob. 14DQCh. 18 - Prob. 15DQCh. 18 - Prob. 16DQCh. 18 - Prob. 17DQCh. 18 - LO.4, 7 In December 2019, Carl Corporation sold...Ch. 18 - LO.2, 5 What are the similarities between the crop...Ch. 18 - Prob. 20DQCh. 18 - Prob. 21DQCh. 18 - Prob. 22DQCh. 18 - LO.6 Largo Company is an engineering consulting...Ch. 18 - Prob. 24DQCh. 18 - Prob. 25DQCh. 18 - Prob. 26DQCh. 18 - Prob. 27CECh. 18 - LO.2 Gaffney Corporation is a wholesale...Ch. 18 - Prob. 29CECh. 18 - LO.2 In 2019, Chaya Corporation, an accrual basis,...Ch. 18 - Prob. 31CECh. 18 - Prob. 32CECh. 18 - Prob. 33CECh. 18 - Prob. 34CECh. 18 - Prob. 35CECh. 18 - Prob. 36CECh. 18 - Prob. 37CECh. 18 - Prob. 38CECh. 18 - Prob. 39PCh. 18 - Prob. 40PCh. 18 - Prob. 41PCh. 18 - In 2018, Juan entered into a contract to write a...Ch. 18 - Prob. 43PCh. 18 - Compute Marys income or deductions for 2019 using...Ch. 18 - What accounting method (cash or accrual) would you...Ch. 18 - Blue Company, an architectural firm, has a...Ch. 18 - How do the all events and economic performance...Ch. 18 - Ross Company is a C corporation providing property...Ch. 18 - Prob. 49PCh. 18 - Prob. 50PCh. 18 - Floyd, a cash basis taxpayer, has received an...Ch. 18 - Prob. 52PCh. 18 - Prob. 53PCh. 18 - On June 30, 2019, Kelly sold property for 240,000...Ch. 18 - Prob. 55PCh. 18 - Prob. 56PCh. 18 - Prob. 57PCh. 18 - Prob. 58PCh. 18 - Prob. 59PCh. 18 - Ostrich Company makes gasoline storage tanks....Ch. 18 - Prob. 61PCh. 18 - Grouse Company is a furniture retailer whose...Ch. 18 - Lavender Manufacturing Company began business in...Ch. 18 - Silver Creek Ranch LLC is a small, family-owned...Ch. 18 - In 2019, Gail changed from the lower of cost or...Ch. 18 - At the end of 2020, Magenta Manufacturing Company...Ch. 18 - Prob. 67PCh. 18 - Prob. 68PCh. 18 - Prob. 69PCh. 18 - Prob. 1RPCh. 18 - Prob. 2RPCh. 18 - Prob. 3RPCh. 18 - Paula has sales that qualify to be reported on the...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- On March 31, 2018, Big Boats Company entered into a contract with Vacations Unlimited to produce a state-of-the-art cruise ship to be completed within three years. Big Boats estimated the total cost of building the ship at $300,000,000. The contract price was $400,000,000. The ship was completed on February 15, 2021. What tax accounting method must Big Boats use for the contract? Why? Using the financial data provided relating to the contract’s performance, com- plete the following schedule. What are the consequences of the total cost of $360,000,000 exceeding the estimated total cost of $300,000,000?arrow_forwardAyala homes is a construction company who uses the percentage of completion method in accounting for its income. The company began constructing a building in the year 2019 for a contract price of P5,000,000. For the year ended 2019, the company billed its clients a total of 30% of the contract price. The books of the company show the following balances: Costs incurred to date 900,000 Construction income to date 300,000 HOW MUCH IS THE COMPANY'S CONTRACT ASSET(LIABILITY) FOR THE YEAR 2019? Show your solution in a good accounting form. Thank you!arrow_forwardOn April 1, 2025, Sandhill Inc. entered into a cost plus fixed fee contract to construct an electric generator for Sweet Acacia Corporation. At the contract date, Sandhill estimated that it would take 2 years to complete the project at a cost of $2,060,000. The fixed fee stipulated in the contract is $468,000. Sandhill appropriately accounts for this contract under the percentage-of-completion method. During 2025, Sandhill incurred costs of $762,200 related to the project. The estimated cost at December 31, 2025, to complete the contract is $1,297,800. Sweet Acacia was billed $584,000 under the contract. Prepare a schedule to compute the amount of gross profit to be recognized by Sandhill under the contract for the year ended December 31, 2025. (If an amount reduces the account balance then enter with negative sign., e.g. -45 or parentheses e.g. (45).) SANDHILL INC. Computation of Gross Profit to be Recognized on Uncompleted Contract Year Ended December 31, 2025 Total Contract Price…arrow_forward
- On July 1, 2020, Oriole Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Oriole estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. At12/31/20 At12/31/21 At12/31/22 Contract costs incurred to date $288,800 $1,227,600 $2,078,500 Estimated costs to complete the contract 1,231,200 752,400 –0– Billings to Gumbel 290,000 1,090,000 1,820,000 (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank.…arrow_forwardCemex Co. began work on a P280 million contract in 2019 to construct an office building. During 2019, Cemex uses the percentage of completion method. At the end of the year, the balance in certain accounts were: Construction in Progress, P98 million; Accounts Receivable, P9.6 million; and Progress Billings, P48 million. The estimated future cost of completion is P127.4 million. How much is the construction income for the year 2019? A. P98,000,000 B. P48,000,000 C. P29,400,000 D. -0-arrow_forwardSage Hill Inc. began work on a $10,700,000 non-cancellable contract in 2020 to construct an office building. During 2020, Sage Hill Inc. incurred costs of $1,352,000, billed its customers for $1,200,000 (non-refundable), and collected $910,000. At December 31, 2020, the estimated future costs to complete the project totalled $3,848,000.arrow_forward
- On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. At 12/31/20 At 12/31/21 At 12/31/22 Contract costs incurred to date $ 300,000 $1,200,000 $2,100,000 Estimated costs to complete the contract 1,200,000 800,000 –0– Billings to Gumbel 300,000 1,100,000 1,850,000 Instructions a. Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) b. Using the…arrow_forwardHeadland Construction Company began work on a $404,000 construction contract in 2020. During 2020, Headland incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660.Prepare Headland’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.arrow_forwardMetlock Inc. began work on a $11,300,000 non-cancellable contract in 2020 to construct an office building. During 2020, Metlock Inc. incurred costs of $1,092,000, billed its customers for $1,200,000 (non-refundable), and collected $990,000. At December 31, 2020, the estimated future costs to complete the project totalled $3,108,000.Prepare Metlock’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.) Account Titles and Explanation Debit Credit enter an account title to record cost of construction No Entry / Contract Asset/Liability / Materials, Cash, Payables / Revenue from Long-Term Contracts / Accounts Receivable / Construction Expenses enter a debit amount enter a credit amount enter an account…arrow_forward
- YEYE Company began operations on January 2, 2021. During the year, the company entered into a contract with YAYA Company to construct a manufacturing facility. At that time YAYA estimated that it would take five years to complete the facility at a cost of P4,812,500. The total contract price for the construction of the facility is P5,468,750. During the year, the company incurred P962,500 in construction costs related to the construction project. At year end, the total estimated cost to complete the contract is P4,375,000. YAYA was billed and paid 30% of the contract price subject to a 10% retention. Using the percentage of completion method, how much is Contract Liability to be presented in the Statement of Financial Position for the year just ended?arrow_forwardHuskiesBest Construction Company began work on a $420,000 construction contract in 2020. During 2020, HuskiesBest incurred costs of $278,000, billed its customer for $215,000, and collected $175,000. At December 31, 2020, the estimated additional costs to complete the project total $162,000. Prepare HuskiesBest 's journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.arrow_forwardDelta Spirit, Inc. entered into a contract to sell equipment to Wilco, LLC on October 1, 2021. Along with the equipment, Delta Spirit will provide one-year maintenance services on an as-needed basis, beginning once the equipment is installed. Delta Spirit offers similar services to other customers that purchased equipment sold by other vendors for $20,000. Delta Spirit will also provide installation services at no additional cost, a service that Delta Spirit typically charges $10,000. The equipment normally sells for $170,000 on its own. For the package deal, Wilco agrees to pay a total of $180,000. The equipment was delivered and installed on November 1, 2021. Wilco paid the entire invoice in cash on the delivery and installation date. How much revenue should Delta Spirit allocate to the various performance obligations in the above contract (round to the nearest dollar, if needed)?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Individual Income TaxesAccountingISBN:9780357109731Author:HoffmanPublisher:CENGAGE LEARNING - CONSIGNMENT
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Individual Income Taxes
Accounting
ISBN:9780357109731
Author:Hoffman
Publisher:CENGAGE LEARNING - CONSIGNMENT
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning
Accounting Changes and Error Analysis: Intermediate Accounting Chapter 22; Author: Finally Learn;https://www.youtube.com/watch?v=c2uQdN53MV4;License: Standard Youtube License