Textbook Question
Chapter 18, Problem 19R
According to the Code, what trade size EMT is required for each of the following combinations of conductors? Assume that these are new installations. Show all calculations. Refer to Chapter 9, NEC, Table 4, Table 5, and Table 8.
- a. Three 14 AWG THHN, four 12 AWG THHN __________________
- b. Two 12 AWG THHN, three 8 AWG THHN __________________
- c. Three 3/0 AWG THHN, two 8 AWG THHN __________________
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
12. Which of the following statements about ground faults is true?A. They can happen if a conductive tool is dropped in an energized equipment's electrical enclosure.B. They usually occur between any grounded circuit conductor and the equipment grounding conductor.C. They can't result from human error.D. They're often normal and typically intentional.
Equipment Grounding
10. Which of the following statements about ground faults is true?A. They usually occur between any grounded circuit conductor and the equipment grounding conductor. B. They're often normal and typically intentional.C. They can't result from human error.D. They can happen if a conductive tool is dropped in an energized equipment's electrical enclosure.
11. Which of the following statements about the use of structural steel as an equipment grounding conductor (EGC) in an AC system is correct?
A. Structural steel can be used as an EGC when it's bonded at both ends.B. Structural steel isn't allowed for use as an EGC.C. Structural steel must have an EGC bonding jumper every three feet of structure. D. Structural steel can be used as an EGC bonding jumper between panelboards.
12. Which of the following statements about equipment grounding conductors is true?
A. They increase voltages above ground potential on conductors and equipment enclosures during normal operation.
B. Unacceptable equipment grounding conductors include conduit, tubing, and cable armor.
C. They must be capable of withstanding the higher level of ground-fault current to perform their safety function.
D. When they're far from their associated circuit conductors, impedance values are kept as low as possible during ground-fault conditions.
13. Imagine that…
Chapter 18 Solutions
ELECTRICAL WIRING:RESIDENTAL-6 PLANS
Ch. 18 - a. What circuit supplies the workshop lighting?...Ch. 18 - Prob. 2RCh. 18 - a. How is EMT fastened to masonry? _______________...Ch. 18 - What type of luminaires are installed on the...Ch. 18 - Prob. 5RCh. 18 - To what circuit are the smoke detectors connected?...Ch. 18 - Is it a Code requirement to connect smoke...Ch. 18 - Prob. 8RCh. 18 - Prob. 9RCh. 18 - Prob. 10R
Ch. 18 - Adjustment factors for conductor ampacities must...Ch. 18 - Prob. 12RCh. 18 - Prob. 13RCh. 18 - Calculate the total current draw of Circuit A17 if...Ch. 18 - Prob. 15RCh. 18 - A conduit body may contain splices if marked with...Ch. 18 - What size box would you use where Circuit A17...Ch. 18 - List the proper trade size of electrical metallic...Ch. 18 - According to the Code, what trade size EMT is...Ch. 18 - a. When more than three current-carrying...Ch. 18 - Prob. 21RCh. 18 - For laundry equipment in basements, what sort of...Ch. 18 - Prob. 23RCh. 18 - A Type NM cable carries a branch circuit to the...Ch. 18 - Prob. 25RCh. 18 - The following is a layout of the lighting circuits...Ch. 18 - Prob. 27RCh. 18 - Prob. 28R
Additional Engineering Textbook Solutions
Find more solutions based on key concepts
Locate the centroid of the area. Prob. 9-17
INTERNATIONAL EDITION---Engineering Mechanics: Statics, 14th edition (SI unit)
Assume a telephone signal travels through a cable at two-thirds the speed of light. How long does it take the s...
Electric Circuits. (11th Edition)
Why is the study of database technology important?
Database Concepts (8th Edition)
Write a summary list of the problem-solving steps identified in the chapter, using your own words.
BASIC BIOMECHANICS
What are the design issues for character string types?
Concepts Of Programming Languages
How is the hydrodynamic entry length defined for flow in a pipe? Is the entry length longer in laminar or turbu...
Fluid Mechanics: Fundamentals and Applications
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.Similar questions
- 11. Specific rules apply for the installation of _______, but no identification requirements for them exists.A. grounding electrode conductorsB. grounding electrodes.C. main bonding jumpers.D. equipment grounding conductors.arrow_forwardA? Conductor is defined in NEC 240.2 as a conductor, other than a service conductor, having overcurrent protection ahead of its point of supply that exceeds the value permitted for similar conductors that are not taps. A. Faulted b. Tap c. Magnetic d. Copper-likearrow_forwardWhich of the following statements about equipment grounding conductors (EGCS) is true? A. The National Electrical Code permits the EGC to also perform as a grounding electrode conductor. B. More than one EGC must be used if multiple circuits are installed in a single raceway, cable, or cable tray. C. No current should be present in the EGC during normal operation. D. EGCs are required to be decreased in size to address voltage drop.arrow_forward
- Which of the following statements about equipment grounding conductors (EGCs) is true?A. The National Electrical Code permits the EGC to also perform as a grounding electrode conductor.B. More than one EGC must be used if multiple circuits are installed in a single raceway, cable, or cable tray.C. No current should be present in the EGC during normal operation.D. EGCs are required to be decreased in size to address voltage drop.arrow_forwardof p o How many conductors enter the ceiling fan/light wall box? Switch ond out let boxes s tirst 10. What type and size of box may be used for the ceiling fan/light wall box?. 11. What type of covers are used with 4 in. square outlet boxes? 12. a. Does the circuit for the Master Bedroom have a grounded circuit conductor? b. Does it have an equipment grounding conductor? c. Explain the difference between a "grounded" conductor and an "equipment grounding" conductor. 13. Approximately how many feet (meters) of 2-wire cable and 3-wire cable are needed to ft complete the circuit supplying the Master Bedroom? Two-wire cable: ft (- m). m). Three-wire cable: 14. If the cable is laid in notches in the corner studs, what protection for the cable must be provided? 15. How high are the receptacles mounted above the finished floor in this bedroom? 16. Approximately how far from the bedroom door is the first receptacle mounted? (See the plans.) 17. What is the distance from the finished floor to…arrow_forwardThe term "____" is defined in NEC® Article 100 as "connected to establish electrical continuity and conductivity." Select one: A. BENDED (BENDING) B. BONDED (BONDING) C. SHUNTED (SHUNTING) D. GROUNDED (GROUNDING)arrow_forward
- 5. How many system bonding jumpers normally are there for a separately derived system that's grounded? A. ThreeB. TwoC. One D. Zero 6. How many grounded neutral conductors are in a 208Y/120 volt, 3-phase, 4-wire system? A. ThreeB. TwoC. One D. Four 7. Which of the following are sometimes installed as an emergency system, legally required standby system, or optional standby power system for a building or structure? A. GeneratorsB. Surge protection devices C. Surge arrestersD. Transformers 8. If the system bonding jumper in a DC system is a screw, what color must the screw be? A. WhiteB. RedC. Orange D. Green 9. If overcurrent protection is provided in the transformer of a separately derived system, which of the following statements is correct? A. An equipment grounding conductor must be run with the conductors between the transformer and the building's disconnect. B. There's no need for service equipment or a panelboard in the separate building.C. A ground electrode must…arrow_forward- Loads, Service, and Overcurrent Protection 6.a. The general lighting load is based on a _______ per square foot basis.A. kilowattB. number of circuitsC. volt-ampereD. general illumination6.b. What's the primary disadvantage of using copper conductors?A. AvailabilityB. WeightC. CostD. Durabilityarrow_forwardequipment grounding 1. The only exception to the need for all information technology equipment to be satisfactorily grounded is where the equipment is A. DC powered.B. backup generator powered. C. double-insulated.D. isolated equipment. 2. Which section of the National Electrical Code lists sizing requirements for wire-type equipment grounding conductors? A. 250.66 B. 250.118 C. 250.4 D. 250.122arrow_forward
- 20.a. What's the primary disadvantage of using copper conductors?A. DurabilityB. CostC. AvailabilityD. Weight20.b. The NEC requires that each service-disconnecting means be suitable forA. hazardous locations.B. disconnecting the meter.C. wet conditions.D. the prevailing conditions 20.c. As a general rule, each building or structure is limited to a single service. What's an automatic exceptionto this rule?A. A second service deemed suitable for useB. A second service having the proper markingsC. Emergency systems or fire pumpsD. Higher building occupancyarrow_forwardL1. Boxes are classified by type, construction, andA. installation location.B. luminaire support capability.C. number of knockouts.D. power rating L2. Which of the following devices must be placed at each end of an armored cable to prevent damage tothe conductors?A. An insulating sliderB. An insertion couplingC. An antishort bushingD. A metal loop fitting L3. Which of the following is the maximum cross-sectional conductor fill area for underfloor raceways?A. 50%B. 60%C. 40%D. 30%arrow_forward3. Which of the following statements about the use of structural steel as an equipment grounding conductor(EGC) in an AC system is correct?A. Structural steel isn't allowed for use as an EGC.B. Structural steel can be used as an EGC bonding jumper between panelboards.C. Structural steel must have an EGC bonding jumper every three feet of structure.D. Structural steel can be used as an EGC when it's bonded at both ends.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- EBK ELECTRICAL WIRING RESIDENTIALElectrical EngineeringISBN:9781337516549Author:SimmonsPublisher:CENGAGE LEARNING - CONSIGNMENT
EBK ELECTRICAL WIRING RESIDENTIAL
Electrical Engineering
ISBN:9781337516549
Author:Simmons
Publisher:CENGAGE LEARNING - CONSIGNMENT
Latches and Flip-Flops 1 - The SR Latch; Author: Computer Science;https://www.youtube.com/watch?v=-aQH0ybMd3U;License: Standard Youtube License