Capital Projects Fund Entries and Statements
The City of Waterman established a capital projects fund for the construction of an access ramp from the parking garage to the city’s office building to be used by individuals with disabilities. The estimated cost of the ramp is $200,000. On January 1, 20X2, a 10 percent, $150,000 bond issue was sold at 104.0 with the premium transferred to the debt service fund. At that date, the county board provided a $50,000 grant. After a period of negotiation, the city council awarded a construction contract for $182,000 on April 5, 20X2. The ramp was completed on August 8, 20X2; its actual cost was $189,000. The city council approved payment of the total actual cost of $189,000.
In addition to the $189,000, the ramp was carpeted with all-weather material at a cost of $5,500. On November 3, 20X2, the city council gave the final approval to pay for the ramp and the carpeting. After all bills were paid, the remaining fund balance was transferred to the debt service fund.
Required
- Prepare entries for the capital projects fund for 20X2.
- Prepare a statement of revenues, expenditures, and changes in fund balance for the capital projects fund for 20X2.
(a)
Introduction: Interim reporting is made in between the fiscal year. It is made before the completion of fiscal year in mostly public corporation for taking various decisions for the remaining period. Mostly quarterly and half yearly report is prepared.
The journal entries for capital project fund for 20X2.
Explanation of Solution
The journal entries for capital project fund for 20X2 is as follows:
Date | Particulars | Debit ($) | Credit ($) |
January 1, 20X2 | Cash | 50000 | |
To revenue account-Grant | 50000 | ||
(Recording entry for receipt of grant from country board) | |||
January 1, 20X2 | Cash | 156000 | |
To Other financing sources-Bond account | 150000 | ||
To Other financing sources-Bond premium | 6000 | ||
(Recording entry for issuing bonds at premium) | |||
January 1, 20X2 | Other financing sources-Transfer to debt service fund | 6000 | |
To cash | 6000 | ||
(Recording entry for transfer of bond premium to debt service fund) | |||
April 5, 20X2 | Encumbrances-construction contract | 182000 | |
To Budgetary fund balance-Assigned for encumbrances | 182000 | ||
(Recording entry for construction contract awarded) | |||
August 8, 20X2 | Budgetary fund balance-Assigned for encumbrances | 182000 | |
To Encumbrances-construction contract | 182000 | ||
(Recording entry to reverse the effect of construction contract as ramp was completed) | |||
August 8, 20X2 | Expenditure-Capital expense | 189000 | |
To Contract payable | 189000 | ||
(Recording entry for approval of payment of all construction expense) | |||
August 8, 20X2 | Expenditures | 5500 | |
To vouchers payable | 5500 | ||
(Recording entry for expense incurred for carpeting all-weather material to building) | |||
November 3, 20X2 | Contract payable | 189000 | |
Vouchers payable | 5500 | ||
To Cash | 194500 | ||
(Recording entry for payment of expenses related to construction of ramp) | |||
November 3, 20X2 | Revenue account-Grant | 50000 | |
Other financing sources-Bond account | 150000 | ||
Other financing sources-Bond premium | 6000 | ||
To fund balance-unassigned | 206000 | ||
(Recording entry for closing nominal accounts) | |||
November 3, 20X2 | Fund balance-unassigned | 200500 | |
To Expenditures | 194500 | ||
To Other financing sources-Transfer to debt service fund | 6000 | ||
(Recording entry for closing nominal accounts) | |||
November 3, 20X2 | Other financing sources-Transfer to debt service fund | 5500 | |
To cash | 5500 | ||
(Recording entry for transfer of remaining amount to debt service fund) | |||
November 3, 20X2 | Fund balance-unassigned | ||
To Other financing sources-Transfer to debt service fund | |||
(Recording entry to close balance of debt service fund) |
(b)
Introduction: Interim reporting is made in between the fiscal year. It is made before the completion of fiscal year in mostly public corporation for taking various decisions for the remaining period. Mostly quarterly and half yearly report is prepared.
The statement of revenues, expenditures and changes in fund balance for capital projects fund.
Explanation of Solution
The statement of revenues, expenditures and changes in fund balance for capital projects fund is as follows:
Particulars | Amount ($) |
Revenue- Country grant | 50000 |
Expenditure-Capital expense (189000+5500) | -194500 |
Expense over revenue (A) | -144500 |
Other finance sources
| |
Bonds issued | 156000 |
Less: Premium | -6000 |
Less: Remaining balance transferred | -5500 |
Total of Other finance sources (B) | 144500 |
Net change in balance (A-B) | 0 |
Want to see more full solutions like this?
Chapter 18 Solutions
Advanced Financial Accounting
Additional Business Textbook Solutions
Principles of Accounting Volume 2
Financial Accounting (11th Edition)
Principles Of Taxation For Business And Investment Planning 2020 Edition
Intermediate Accounting
PRINCIPLES OF TAXATION F/BUS.+INVEST.
- The City of Sunnyville’s General Fund has the following net resources at year end: $55,000 for LT Advance to an internal service fund $375,000 approved by the City Council with specific conditions for its use $2,500 of supplies inventory $60,000 state grant for snow removal $150,000 City Council resolution approved for funds to renovate city hall $400,000 to be used to fund government operations in the future Outstanding encumbrances of $80,000 for the purchase of furniture & fixtures What would be the total “Restricted” Fund balance? Select one: a. $275,000 b. $210,000 c. $150,000 d. $60,000arrow_forwardThe City of Sunnyville’s General Fund has the following net resources at year end: $55,000 for LT Advance to an internal service fund $375,000 approved by the City Council with specific conditions for its use $2,500 of supplies inventory $60,000 state grant for snow removal $150,000 City Council resolution approved for funds to renovate city hall $400,000 to be used to fund government operations in the future Outstanding encumbrances of $80,000 for the purchase of furniture & fixtures What would be the total “Non-spendable” fund balance? Select one: a. $2,500 b. $57,500 c. $75,000 d. $105,000arrow_forwardThe City of Sunnyville’s General Fund has the following net resources at year end: $55,000 for LT Advance to an internal service fund $375,000 approved by the City Council with specific conditions for its use $2,500 of supplies inventory $60,000 state grant for snow removal $150,000 City Council resolution approved for funds to renovate city hall $400,000 to be used to fund government operations in the future Outstanding encumbrances of $80,000 for the purchase of furniture & fixtures What would be the total “Unassigned” fund balance? Select one: a. $280,000 b. $400,000 c. $80,000 d. $377,500arrow_forward
- The citizens of Spencer County approved the issuance of $2,008,000 in 6 percent general obligation bonds to finance the construction of a courthouse annex. A capital projects fund was established for that purpose. The preclosing trial balance of the courthouse annex capital project fund follows: Trial Balance—December 31, 2020 Debits Credits Cash $ 908,000 Contract payable $ 551,000 Due from state government 192,000 Encumbrances 108,000 Expenditures—capital 1,854,000 Intergovernmental grant 395,000 OFS: premium on bonds 57,000 OFS: proceeds sale of bonds 2,008,000 Budgetary fund balance—Reserve for encumbrances 108,000 OFU: Transfer out 57,000 $ 3,119,000 $ 3,119,000 Required:a. Prepare any closing entries necessary at year-end.b. Prepare a Statement of Revenues, Expenditures, and Changes in Fund Balance…arrow_forwardOn December 31, Year 1, the following balances were due from the state government to Clare City's various funds: Capital projects $300,000 Special revenue fund $18,000 Investment trust fund100,000 Enterprise 80,000 Custodial fund 100,000 Debt servide fund 100,000 In Clare's December 31, Year 1, financial statements, what amount should be reported in fiduciary funds? $600,000 $400,000. $300,000. $1,050,000arrow_forwardThe citizens of Spencer County approve the issuance of $2,000,000 in 6 percent genneral obligtions bonds to finance the contruction of a courthouse annex. A capital projects fund was established for that pupose. The precolisning trial balance of the courthouse annex capital project fund follows: Debits: Cash $400,000; due from state government $75,000; Encumbrances $120,000; Expenditures - Capitals $2,160,000; OFU: Transfer Out $25,000 Credit: Contract Payable $250,000; Intergivernmental Grant $385,000; OFS: Premium on bonds $25,00; OFS: proceeds sale of Bonds $2,000,000; Budgetary fund Balamce- Reserve for encumbrance $120,000 Required: a. Prepare any closing entries neccessary at year end. b. Prepare a statement of Revenue, Expenditures, and Changes in Fund Balance for the courthouse annex capital fund project. c. Prepare a Balance Sheet for the courthouse annex capital project fund, assuming all unexpendedresources are restricted to construction of the courthouse annex.arrow_forward
- A city is building a new park. To finance the construction of the park, the city will issue a $1,800,000 bond, and receive a transfer of $200,000 from the general Please record the journal entries for the Capital Project Fund and the Government-Wide financial statements. 1. The city signed a contract with a construction company to construct the park for $2,000.000. 2. The $1.800.000 bonds were issued at par. 3. The construction company billed the city for $2,000,000 upon completion of the project. 4. The park is completed.arrow_forwardIbri township issued the following bonds during the year. The bond issued to purchase equipment for vehicle repair service that is accounted for in an internal service fund RO 30,000, The bonds issued to construct a new city hall RO 10,000 The bonds issued to improve its water utility, which is accounted for in an enterprise fund RO 50,000. The amount of bond issued to be reported in the general fund is a. RO 10,000 b. RO 50,000 c. None of the options d. RO 30,000arrow_forwardIn Fulbright County, the Culture and Recreation Department constructed a library in one of the county’s high-growth areas. The construction was funded by a number of sources. Below is selected information related to the Library Capital Project Fund. All activity related to the library construction occurred within the current fiscal year. The county operates on a calendar-year basis. The county issued $6,000,000 of 4 percent bonds, with interest payable semiannually on January 1 and July 1. The bonds sold for 101 on February 1. Proceeds from the bonds were to be used for construction of the library, with all interest and premiums received to be used to service the debt issue. A $650,000 federal grant was received to help finance construction of the library. The Library Special Revenue Fund transferred $250,000 for use in construction of the library. A construction contract was awarded in the amount of $6,800,000. The library was completed four months ahead of schedule. Total…arrow_forward
- A city transfers cash of $90,000 from its general fund to start construction on a police station. The city issues a bond at its $1.8 million face value. The police station is built for a total cost of $1.89 million. a. Prepare all necessary journal entries for these transactions for both fund and government-wide financial statements. Assume that the city does not record the commitment for this construction. (Select the appropriate fund for each situation when required. If no entry is required for a transaction/event, select "No journal entry required" in the first account field. Enter your answers in dollar, not in millons.)arrow_forwardThe county of Santa Clara is building a new park. The main financing source will be $1,000,000 bond issue. In addition, the general fund will transfer $100,000 transfer to fund the capital project. Please record the journal entries for the Capital Project Fund & the Government-Wide financial statements. 1. The county has signed a contract with Spectacular Construction to construct the park $1,000,000 2.The $1,000,000 bonds were issued at par 3. Spectacular Construction billed the county of Santa Clara $1,000,000 upon completion of the project 4. The park is completedarrow_forwardThe City of Oxbow General Fund has the following net resources at year-end: $260,000 unexpended proceeds of a state grant required by law to be used for health education. $20,000 of prepaid insurance. $609,000 rainy day fund approved by city council for use under specified circumstances. $210,000 budget stabilization fund to be used in the event of revenue shortfall. $285,000 provided for contractual obligations for capital projects. $41,000 unexpended proceeds of a tax required by law to be used for emergency 911 services. $1,636,000 total fund balance. Required:Prepare the fund balance section of the Balance Sheet. City of Oxbow Partial Balance sheet-General Fund Fund Balances Nonspendable $ Restricted $ $ Committed $ $ Assigned Unassigned Total Fund Balancearrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education