
Concept explainers
Interpretation: The total project completion time is to be calculated along with the lowest cost solution if the project is to be completed
Concept Introduction:
Project

Explanation of Solution
The activity with their immediate predecessor and estimated time, crash time, crash cost and normal cost is tabulated below.
Activity | Immediate Predecessor | Estimated Normal Time | Crash Time | Normal Cost | Crash Cost |
A | - | ||||
B | A | ||||
C | A | ||||
D | - | ||||
E | B, D, C | ||||
F | D | ||||
G | D | ||||
H | E | ||||
I | F, G, H |
Table (1)
The network diagram for the activity shown in table (1) is shown below.
Figure (1)
Therefore, the network diagram of the given project is shown in Figure (1).
The expression for the cost slope is given by,
The cost slope for each activity is tabulated below.
Activity | Immediate Predecessor | Estimated Normal Time | Crash Time | Normal Cost | Crash Cost | Cost Slope |
A | - | |||||
B | A | |||||
C | A | |||||
D | - | |||||
E | B, D, C | |||||
F | D | |||||
G | D | |||||
H | E | |||||
I | F, G, H |
Table (2)
Consider figure (1), the different paths and their completion times is tabulated below.
Path | Completion time (weeks) |
Table (3)
From Table (3), the maximum completion time is taken by path
Therefore, the critical path is
Now the project is to be completed
Consider the critical path activities.
The lowest crash cost per week is of activity B and activity H.
Crash Activity B by
And,
Thus, the additional cost of crashing the activity by
The new network diagram is shown in figure below.
Figure (2)
Consider figure (2), the different paths and their completion times is tabulated below.
Path | Completion time (weeks) |
Table (4)
From Table (4), the maximum completion time is taken by path
Therefore, the critical path is
But the desired project duration is
Try different option.
Crash Activity B by
And,
And,
Thus, the additional cost of crashing the activity by
The new network diagram is shown in figure below.
Figure (3)
Consider figure (3), the different paths and their completion times is tabulated below.
Path | Completion time (weeks) |
Table (4)
From Table (4), the maximum completion time is taken by path
Therefore, the critical path are
Therefore, the crashing cost of the project is
Want to see more full solutions like this?
Chapter 18 Solutions
OM (with OM Online, 1 term (6 months) Printed Access Card)
- Which of the following statements about organization's strategy is FALSE? OA. They are formulated after the organization's mission is determined. OB. They reflect an organization's purpose. OC. An organization's strategy exploits opportunities and threats. OD. They help determine how an organization expects to achieve its miss OE. Each functional area of the organization will have a strategy. The ability of an organization to match changes in a marketplace where design volumes fluctuate substantially is: OA. competing on productivity. OB. mass production. OC. time-based competition. OD. competing on differentiation. O E. competing on response. Porter's Five Forces Model is used to evaluate competition based on which 5 asp A. immediate rivals, potential entrants, customers, suppliers, and substitute B. potential entrants, customers, suppliers, legal regulations, and costarrow_forwardplease answerarrow_forwardplease answerarrow_forward
- please asnwerarrow_forwardWhat are the obstacles to incorporating stress management techniques? How can we overcome these obstacles?arrow_forwardIn the 2016, "ATB: digital disruption in the parking meter industry" perform a finanacial analysis and make a chart similar to this one 2013 2014 Current Ratio 1.88 1.41 Quick Ratio 0.49 0.29 Debt to Equity 0.95 1.92 Return on Assets 5.47% 2.76% Net Profit Margin 2.71% 1.89%arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning

