OPERATIONS MANAGEMENT -CONNECT
14th Edition
ISBN: 9781265205751
Author: Stevenson
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 17, Problem 8P
The new director of special events at a large university has decided to completely revamp graduation ceremonies. Toward that end, a PERT chart of the major activities has been developed. The chart has five paths with expected completion times and variances as shown in the table. Graduation day is 16 weeks from now. Assuming the project begins now, what is the probability that the project will be completed before
a. Graduation time?
b. The end of week 15?
c. The end of week 13?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The new director of special events at a large university has decided to completely revamp graduation ceremonies. Toward that end, a PERT chart of the major activities has been developed. Thechart has five paths with expected completion times and variances as shown in the table. Graduation day is 16 weeks from now. Assuming the project begins now, what is the probability that theproject will be completed beforea. Graduation time?b. The end of week 15?c. The end of week 13?PathExpected Duration(weeks) VarianceA 10 1.21B 8 2.00C 12 1.00D 15 2.89E 14 1.44
Consider the project described in the table
below:
Activity Duration
A
B
C
D
E
F
G
H
9
4
8
8
5
7
4
6
OEST-9 and LCT = 15
OEST=9 and LCT = 13
Immediate
Predecessor
What is the earliest start time (EST) and latest
completion time (LCT) of activity B?
OEST=9 and LCT = 20
OEST-9 and LCT-17
-
A
A
A
B
B,C
C,D
E,F,G
Activities, preceding activities, normal and crashed completion times of each of the activities and
crashed costs of activities per week of a project are given in the following table.
Activity Preceding
Activity
Crashed Completion
time (week)
Normal
Crashed Cost
Completion Time
(week)
7
per week
A
7
6.
5
$500
$700
$600
$800
$400
C
A
4
3
A, C
В, D
D, E
D
9
E
10
9.
F
9
II.
Find the slack time of each of the activities and the critical activities.
Find the minimum possible completion time of the project by considering the crashed
completion times and the minimal total cost of crashing the project.
iv.
Chapter 17 Solutions
OPERATIONS MANAGEMENT -CONNECT
Ch. 17.3 - Will the AI technology render project managers...Ch. 17.3 - Prob. 1.2RQCh. 17 - A project manager may need two skill setsthose of...Ch. 17 - Explain the term project champion and list some...Ch. 17 - List the steps in risk management.Ch. 17 - Give some examples of ethical issues that may...Ch. 17 - What are the key advantages of using project...Ch. 17 - What is a work breakdown structure, and how is it...Ch. 17 - Identify the term being described for each of the...Ch. 17 - List the main advantages of PERT. List the main...
Ch. 17 - Why might a probabilistic estimate of a projects...Ch. 17 - Define each of these terms, and indicate how each...Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - Prob. 9PCh. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A project consisting of the following activities: Activity Predecessor Duration (months) A 2 B Activity A Duration (hours) 1 Predecessor - 3 C 2 D B B 5 1 4 E A, B C 3 1 3 F B 2 D 3 2 G F, C 5 H G Identify the critical path and obtain the project completion time. Calculate free float for each activity. The table describes the activities needed in planning a training session. E 1 4 4 I F F 4 4 3 J I, D 2 G 1 5 H 3 3,6 Determine the critical path and the expected completion time of the training session. K J 1 L E 6arrow_forwardTitle A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the Table. Activity Duration (in weeks) Depends upon N. Q 4 P. R Q S 8. R U R,S V 2 U W U T,V Y 1 W 3. X,Y The total float of the activity V' (in weeks, in 29jo integer) isarrow_forwardA project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $21,000 B A 12 $20,000 9 $30,000 C A 15 $24,000 10 $60,000 D B 3 $10,000 2 $15,000 E C 9 $17,000 6 $34,000 F E 7 $5,000 6 $6,000 G D 8 $14,000 6 $20,000 H A 12 $22,000 10 $30,000 I H 6 $50,000 5 $55,000 J F, G, I 11 $33,000 9 $50,000arrow_forward
- The following represents a project that should be scheduled using CPM a. Complete the table b. Draw the Network Diagram c. What is the critical path? d. What is the expected project completion time?' e. What is the probability of completing this project within 16 days?arrow_forwardThree recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. a. Draw the precedence diagram. b. What is the probability that the project can be completed in 24 days or less? c. Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24. TIME IN DAYS Activity Precedes Optimistic Most Likely Pessimistic A — 5 6 7 B — 8 8 11 C A 6 8 11 D - 9 12 15 E C 5 6 9 F D 5 6 7 G F 2 3 7 H B 4 4 5 I H 5 7 8 End E,G,I d. The partners have decided that shortening the…arrow_forwardSuppose you have a project with a Budget at Completion (BAC) of $250,000 and a projected length of 10 months. After tracking the project for six months, you have collected the information in the table below. a. Complete the table. How do Earned Value SPI (based on $) and Earned Schedule SPI differ? b. Calculate the schedule variances for the project for both Earned Value and Earned Schedule. How do the values differ?arrow_forward
- IMPORTANT NOTE: All Project Management Questions are from the same Project. You only need to solve the project one time. The CEO of Carol O'Lights Manufacturing, produces custom-built relay devices for auto makers. The most recent project undertaken by Ms. O'Lights requires 11 different activities. The activities necessary to build an experimental relay model and related data are given in the following table. What is the Early Start on Activity G?arrow_forwardThe following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration (weeks) This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F Activity A (start) BU C E F (end) 1 2362 10 Precedes B, C F E F c) The total project completion time for Rafay Ishfaq's software firm is 13 weeks. (Enter your response as a whole number.) d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.) Activity Slack Time (weeks)arrow_forwardThe following represents a project that should be scheduled using CPM: ACTIVITY A B C D E F G H IMMEDIATE PREDECESSORS A A B C, D D, E F,G b. What is the critical path? ⒸA-D-G-H OB-E-G-H ⒸA-C-F-H A-D-F-H Probability TIMES (DAYS) b Project completion time a 1 1 2 1 1 3 1 2 m 2 2 2 8 2 4 3 3 6 9 11 9 3 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. 11 11 11 X Answer is not complete. days d. What is the probability of completing this project within 19 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.arrow_forward
- A Research and Development team is creating a project plan for developing a new product. Upper management has requested the project be completed in 60 days. They have developed estimated time durations in days for the project as shown in the following table. Activity Immediate Predecessor Activities A Optimistic Time (to) Most Likely Time (tm) Pessimistic Time (tp) 11 13 16 B A 7 11 15 C A 11 16 21 D A 10 10 19 E B 6 7 9 F C, E 11 13 14 G B 13 15 17 H B, D 19 22 25 I B, D ] F, G, H 11 16 21 11 15 Compute the expected time for activity H. 0000 11 19 22 26arrow_forwardA small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. ACTIVITY IMMEDIATE PREDECESSOR a m b A − 1 4 7 B − 2 5 14 C A 5 11 17 D B 3 9 15 E C 3 3 3 Part 2 a) Find the expected completion time for this project. The expected completion time for this project is (enter your response as a whole number). Part 3 b) What variance value would be used to find probabilities of finishing by a certain time? The…arrow_forwardThree recent college graduates have formed a partnership and have opened an advertising firm.Their first project consists of activities listed in the following table.a. Draw the precedence diagram.b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?c. Suppose it is now the end of the seventh day and that activities A and B have been completedwhile activity D is 50 percent completed. Time estimates for the completion of activity D are5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing theproject by day 24 and the probability of finishing by day 21.TIME IN DAYSActivityImmediatePredecessor Optimistic Most Likely PessimisticA — 5 6 7B — 8 8 11C A 6 8 11D — 9 12 15E C 5 6 9F D 5 6 7G F 2 3 7H B 4 4 5I H 5 7 8End E, G, Id. The partners have decided that shortening the project by two days would be beneficial, as longas it doesn’t cost more than about $20,000. They have estimated the daily crashing costs for…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY