Chris received new word processing software for her birthday. She also received a check, with which she intends to purchase a new computer. Chris’s college instructor assigned a paper due next week. Chris decided that she will prepare the paper on the new computer. She made a list of the activities she will need to do and their estimated times.
a. Arrange the activities into two logical sequences.
b. (1) Construct an AOA network diagram.
(2) Construct an AON diagram.
c. Determine the critical path and the expected duration time.
d. PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.
What are some possible reasons for the project to take longer than the expected duration?
Trending nowThis is a popular solution!
Chapter 17 Solutions
Operations Management (Comp. Instructor's Edition)
- create a network for planning and construction of the new hospital at Arnold Palmerarrow_forwardOmar has recently been hired as the HIM director at a large medical center. He realizes that he has a number of employees whose job duties would allow them to work from home. Because his boss has asked him for a space reduction proposal, he recognizes the need to implement a work-at-home program for his employees. What steps should Omar take in developing a security program for the employees who will work from home? Develop a checklist of considerations, along with a list of resources that would facilitate his security program.arrow_forwardC. Job: Installing an IT System at Bana Bank Zambia Ltd. (08-04- 2022 to 20-05-2022) ACTIVITY A. Design system on the computer B. Purchase components C. Configure network D. Prepare software E. Install software F. Assemble computers G. Connect computers H. Pilot test and refine system I. Start up system, inaugurate and handover to client. From the data given above: WEEK 1 ? ? ? 2 ? ? ? ? 5 13 2 2 14 7 13 12 1 NUMBER OF WORKDAYS a. Prepare/draw a full Gantt Chart as at end of Week 5. b. Calculate and indicate the missing (?) week numbers. c. Indicate the completed and planned activities on the chart. d. Explain the shortcomings of the Gantt Cart as a planning tool.arrow_forward
- The conditions and pert times for constructing a network diagram are given below.-Creation conditions:(0-1) It is the initial activity.(1-2) and (1-3) Activities begin together.It follows activity (2-4) (1-2), activity (3-4) (1-3), and ends together.( 4-5 ) It is the last activity. a-Create the network diagram.b-Calculate the critical path and show it on the diagram.c- If the expiry time is extended by 15 days, how much will the probability of expiry increase?arrow_forwarda) Produce work schedule showing the activity of estimated durations and the critical path and estimated overal mean duration for work package. Answers must be handwritten step by step to allow others to follow. b) calculate the probability of the work package being completed by week 24. Answers must be handwritten step by step to allow others to follow. c) Differentiate between ealiest and latest activity start and finisg times and explain how these variables determine the degree of spare time or float contained within activities. Answers must be handwritten step by step to allow others to follow.arrow_forwardPlease do not give solution in image format thankuarrow_forward
- Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity Description ImmediatePredecessor Time(weeks) A Survey building site 7 B Develop initial design 9 C Obtain board approval A, B 12 D Select architect C 4 E Establish budget C 7 F Finalize design D, E 16 G Obtain financing E 13 H Hire contractor F, G 6 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) (b) Identify the critical path. (Enter your answers as a comma-separated list.) (c) Develop the activity schedule for the project. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F G…arrow_forwardB. Please draw an activity diagram for the tour reservation. Tour Reservation Procedure 1. Booking Form To make a reservation, we will email you our Credit Card Booking Form (also enclosing our Terms & Conditions and Cancellation Policy). Please return a complete and signed form by fax or email. An incomplete or unsigned form will not be processed. Only Visa or MasterCard credit card will be accepted. We will not accept any other credit card. 2. Bookings Made Once we receive your credit card booking form, we will proceed with all the necessary reservations. If any changes are needed at this stage, for example due to changes in availability, we will ask for your approval by email first. Once everything is confirmed, a required deposit or full payment will be billed as indicated on the booking form. 3. Email Confirmation When the required deposit or full payment is received, we will complete the reservation and will email you confirmation of the services booked including confirmed…arrow_forwardEd is planning to build a treehouse as a present for his son's upcoming 10th birthday. The details for each task are as follows: DE F G AD C,E F 12 Task A B Preceding Task Duration (day) | 12 A B 10 12 5 Cost (RM) 50 140 120 60 70 80 60 (a) Obtain the following: • The number of days it will take for Ed to finish building the treehouse. • Which tasks are cannot be delayed at all without delaying the whole project. • The total cost of building the treehouse. (b) Due to illness, Ed has to begin building the treehouse later than planned. He reckons that he must reduce the build duration by 3 days to complete the treehouse by his son's birthday. He has determined the crash cost and crash time for each task as follows: Task А В С DE F G Crash Time (day) | 12 8 9 8 10 5 6 Crash Cost (RM) | 50 170 180 70 95 80 60 Obtain the following: • All tasks that are crashed and by how much. • The new total cost for building the treehouse.arrow_forward
- Please do not give solution in image format thankuarrow_forwarda. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each case requires the use of a dummy activity. b. Construct an AON diagram for each case.arrow_forwardCreate an AOA diagram based on the information Task A, duration 6, dependent on noneTask B, duration 5, dependent on noneTask C, duration 3, dependent on noneTask D, duration 12, dependent on Task B and Task C Task E, duration 2, dependent on Task ATask F, duration 5, dependent on Task BTask G, duration 1, dependent on Task BTask H, duration 9, dependent on Task E and Task FTask I, duration 7, dependent on Task GTask J, duration 7, dependent on Task HTask K, duration 3, dependent on Task ITask L, duration 5, dependent on Task Darrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.