Rick Wing, salesperson for Wave Soldering Systems, Inc. (WSSI), has provided you with a proposal for improving the temperature control on your present machine. The machine uses a hot-air knife to cleanly remove excess solder from printed circuit boards; this is a great concept, but the hot-air temperature control lacks reliability. According to Wing, engineers at WSSI have improved the reliability of the critical temperature controls. The new system still has the four sensitive integrated circuits controlling the temperature, but the new machine has a backup for each. The four integrated circuits have reliabilities of .90, .92, .94, and .96. The four backup circuits all have a reliability of .90.

a) What is the reliability of the new temperature controller?

b) If you pay a premium, Wing says he can improve all four of the backup units to .93. What is the reliability of this option?

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The reliability of the new temperature controller.

Explanation of Solution

Draw a schematic diagram as shown in figure of the reliabilities of the four integrated circuits along with their respective back ups for the wave soldering machine given that R1=0.90 back up R1'=0.90 , R2=0.92 back up R2'=0.90 , R3=0.94 back up R3'=0.90 and R4=0.96 back up R4'=0.90

Principles Of Operations Management, Chapter 17, Problem 13P , additional homework tip  1

The combined reliabilities RC with backups for each integrated circuit can be expressed as follows

RC=(R1+R1'×(1R1))×(R2+R2'×(1R2))×(R3+R3'×(1R3))×(R4+R4'×(1R4))=(0.9+0.9×(10.9))×(0.92+0.90×(10.92))×(0.94+0.90×(10.94))×(0.96+0.90(10.96))=0.99×0.992×0.994×0.996RC=0.9723

The reliability of the temperature controller is 0.9723.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The reliability of this option.

Explanation of Solution

The reliability of each of the backup integrated circuits has been improved from 0.9 to 0.93. To calculate the reliability of the temperature controller, again draw a schematic diagram as shown in figure of the reliabilities of the four integrated circuits along with their respective back ups for the wave soldering machine given that R1=0.90 back up R1'=0.93 , R2=0.92 back up R2'=0.93 , R3=0.94 back up R3'=0.93 and R4=0.96 back up R4'=0.93

Principles Of Operations Management, Chapter 17, Problem 13P , additional homework tip  2

The combined reliabilities RC with backups for each integrated circuit can be expressed as follows

RC=(R1+R1'×(1R1))×(R2+R2'×(1R2))×(R3+R3'×(1R3))×(R4+R4'×(1R4))=(0.9+0.93×(10.9))×(0.92+0.93×(10.92))×(0.94+0.93×(10.94))×(0.96+0.93(10.96))=0.993×0.9944×0.9958×0.9972RC=0.9805

The reliability of the temperature controller improves to 0.9805 from an earlier figure of 0.9723.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Research proposal: The Investigation of Career Development and Job satisfaction atEskom Rotek Industries 1. Introduction (250 words) 2. Research Context: Background (Research Context: Background (250 words) 3. The Research Problem (The Research Problem) 4. Aim of the study (Maximum 50 words) 5. Research Objectives (3 in total) 6. Research Questions (3 in total) 7. Justification or rationale of the study (150 words) 8. Literature Review (2-3 pages / 1000-1500 words) 9. Research Design and Methodology (1 - 2 page in total, from 9.1 to 9.6) 9.1 Research Philosophy  9.2 Research Methodology  9.3 Target Population and Sampling strategy  9.4 Data Collection 9.5 Data Analysis (100 words) 9.6 Pilot Study 10. Ethical considerations  11. Reference
With your experience and research, discuss;(a) what type of “Leadership Style” is used in communications services (Digicel Group Limited)?(b) whether the style used is successful or not and why. Justify your position with relevant citation and references  ( Rubic is attached to guide the essay ) NOTE: NO AI RESPONSES PLEASE
by the end of 2013, the IPL port was operational and the naphtha was flowing to the Himachal Fertilizer Corporation (HFC) plant in Central India after being granted the port contract in Summer 2012. The plant was located in an industrial area that had several pipelines in the general geographic area including a crude oil pipeline leading to a refinery, and a pipeline carrying pesticides to be processed and redistributed to local farms in the area. In July 2014, Ajay Patel, the logistics general manager received notification that there were some minor leaks along the pipeline that were being fixed. Workers in the area had experienced sudden headaches and lightheadedness and the company immediately moved to investigate the leak and address faulty seams that had eroded and weakened. The flow of naphtha was temporarily stopped for 72 hours so two portions of the pipeline could be removed, and the eroded portions replaced. Patel put enormous pressure on the repair team to get the repair…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY