A foreman has determined processing times at a work center for a set of jobs and now wants to sequence them. Given the information shown, do the following:
a. Determine the processing sequence using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each sequence, compute the average job tardiness, the average flow time, and the average number of jobs at the work center. The list is in FCFS order.
b. Using the results of your calculations in part a, show that the ratio of average flow time and the average number of jobs measures are equivalent for all four sequencing rules.
c. Determine the processing sequence that would result using the S/O rule.
a)
1)

To determine: The processing sequence based on First Come First Served (FCFS).
Introduction: First Come First Served is the scheduling rule, which helps to arrange the sequence in the order. Here, the first come would be served first.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine the sequence using FCFS:
According to FCFS, the first come would be served first. Hence, the jobs should be sequenced in the order as per its arrival.
Hence, the sequence of jobs using FCFS is a-b-c-d-e-f.
Determine average flow time, average tardiness, and average number of jobs for FCFS:
Job | Processing time (days) | Flow time (days) | Due date (days) | Tardiness |
a | 4.5 | 4.5 | 10 | 0 |
b | 6 | 10.5 | 17 | 0 |
c | 5.2 | 15.7 | 12 | 3.7 |
d | 1.6 | 17.3 | 27 | 0 |
e | 2.8 | 20.1 | 18 | 2.1 |
f | 3.3 | 23.4 | 19 | 4.4 |
Total | 23.4 | 91.5 | 10.2 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job a:
Flowtime is less than the due date. Hence, there would be tardiness.
Tardiness of Job b:
Flowtime is less than the due date. Hence, there would be tardiness.
Tardiness of Job c:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job c is 3.7.
Note: The procedure continues for all the jobs.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 15.25 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 1.7 days.
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 3.9 jobs.
1)

To determine: The processing sequence based on First Come First Served (FCFS).
Introduction: First Come First Served is the scheduling rule, which helps to arrange the sequence in the order. Here, the first come would be served first.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine the sequence using FCFS:
According to FCFS, the first come would be served first. Hence, the jobs should be sequenced in the order as per its arrival.
Hence, the sequence of jobs using FCFS is a-b-c-d-e-f.
Determine average flow time, average tardiness, and average number of jobs for FCFS:
Job | Processing time (days) | Flow time (days) | Due date (days) | Tardiness |
a | 4.5 | 4.5 | 10 | 0 |
b | 6 | 10.5 | 17 | 0 |
c | 5.2 | 15.7 | 12 | 3.7 |
d | 1.6 | 17.3 | 27 | 0 |
e | 2.8 | 20.1 | 18 | 2.1 |
f | 3.3 | 23.4 | 19 | 4.4 |
Total | 23.4 | 91.5 | 10.2 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job a:
Flowtime is less than the due date. Hence, there would be tardiness.
Tardiness of Job b:
Flowtime is less than the due date. Hence, there would be tardiness.
Tardiness of Job c:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job c is 3.7.
Note: The procedure continues for all the jobs.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 15.25 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 1.7 days.
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 3.9 jobs.
2)

To determine: Sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the shortest duration would be served first. Then, the process would be going on from shortest to largest duration.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine the sequence using SPT:
According to SPT, the job that has the shortest processing would be served first and it goes on as the processing time increase. Duration should be assembled in the ascending order
Hence, the sequence of jobs using SPT is d-e-f-a-c-b.
Determine average flow time, average tardiness, and average number of jobs for SPT:
Job | Processing time (days) | Flow time (days) | Due date (days) | Tardiness |
d | 1.6 | 1.6 | 27 | |
e | 2.8 | 4.4 | 18 | |
f | 3.3 | 7.7 | 19 | |
a | 4.5 | 12.2 | 10 | 2.2 |
c | 5.2 | 17.4 | 12 | 5.4 |
b | 6 | 23.4 | 17 | 6.4 |
Total | 23.4 | 66.7 | 14 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job d, Job e, and Job f:
Flow time of Job d, Job e, and Job f is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job a:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job a is 2.2.
Tardiness of Job c:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job c is 5.4.
Tardiness of Job b:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job b is 6.4.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 11.12 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 2.33 days.
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 2.85 jobs.
3)

To determine: Sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the earliest due date would be served first. Then, the process would be going on from earliest due date to latest due date.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine the sequence using EDD:
According to EDD, the job that has the earliest due date would be served first and it goes on as the due date increases. The job should be arranged based on due date. Due date should be assembled in the ascending order
Hence, the sequence of jobs using EDD is a-c-b-e-f-d.
Determine average flow time, average tardiness, and average number of jobs for EDD:
Job | Processing time (days) | Flow time (days) | Due date (days) | Tardiness |
a | 4.5 | 4.5 | 10 | 0 |
c | 5.2 | 9.7 | 12 | 0 |
b | 6 | 15.7 | 17 | 0 |
e | 2.8 | 18.5 | 18 | 0.5 |
f | 3.3 | 21.8 | 19 | 2.8 |
d | 1.6 | 23.4 | 27 | 0 |
Total | 23.4 | 93.6 | 3.3 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job a, Job c, Job b, and Job d:
Flow time of Job a, Job c, Job b, and Job d is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job e:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job e is 0.5.
Tardiness of Job f:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job f is 2.8.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 15.6 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 0.55 days.
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 4 jobs.
4)

To determine: Sequence of jobs based on decision rule critical ratio.
Introduction: Critical ratio is kind of scheduling rule that helps to identify that, the task or job is on the correct track. It would help to identify if the task is behind or ahead of the schedule.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine the sequence using critical ratio:
Initial critical ratio should be determined at day 0:
Job | Processing time (days) | Due date (days) | Critical ratio |
a | 4.5 | 10 | 2.22 |
b | 6 | 17 | 2.83 |
c | 5.2 | 12 | 2.31 |
d | 1.6 | 27 | 16.88 |
e | 2.8 | 18 | 6.43 |
f | 3.3 | 19 | 5.76 |
Critical ratio for Job a:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Note: Process continues for all the jobs.
Job a has the lowest critical ratio. Thus, it will be completed first. Hence, Job a would be completed first in the sequence of jobs.
Determine the critical ratio after the completion of Job a:
As the processing time of job a is 4.5 days, completion day of completed day would be 4.5.
Job | Processing time (days) | Due date (days) | Critical ratio |
a | |||
b | 6 | 17 | 2.08 |
c | 5.2 | 12 | 1.44 |
d | 1.6 | 27 | 14.06 |
e | 2.8 | 18 | 4.82 |
f | 3.3 | 19 | 4.39 |
Critical ratio for Job b:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Note: Process continues for all the jobs.
Job c has the lowest critical ratio. Hence, Job c would be completed next in the sequence of jobs.
Determine the critical ratio after the completion of Job a and Job c:
As the processing time of job a is 4.5 days and Job c is 5.2, completion day of completed day would be 9.7 (4.5+5.2).
Job | Processing time (days) | Due date (days) | Ratio |
a | |||
b | 6 | 17 | 1.22 |
c | |||
d | 1.6 | 27 | 10.81 |
e | 2.8 | 18 | 2.96 |
f | 3.3 | 19 | 2.82 |
Critical ratio for Job b:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Job b has the lowest critical ratio. Hence, Job b would be completed next in the sequence of jobs after Job a and Job c.
Determine the critical ratio after the completion of Job a, Job c and Job b:
As the processing time of job a is 4.5 days, Job b is 6.0, and Job c is 5.2 days. Completion day of completed day would be 15.7 (4.5+5.2+6).
Job | Processing time (days) | Due date (days) | Ratio |
a | |||
b | |||
c | |||
d | 1.6 | 27 | 7.06 |
e | 2.8 | 18 | 0.82 |
f | 3.3 | 19 | 1 |
Critical ratio for Job d:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Job e has the lowest critical ratio. Hence, Job e would be completed next in the sequence of jobs after Job a, Job c, and Job b.
Determine the critical ratio after the completion of Job a, Job c, Job b, and job e:
As the processing time of job a is 4.5 days, Job b is 6.0, Job c is 5.2 days, and job e is 2.8. Completion day of completed day would be 18.5 (4.5+5.2+6+2.8).
Job | Processing time (days) | Due date (days) | Ratio |
a | |||
b | |||
c | |||
d | 1.6 | 27 | 5.31 |
e | |||
f | 3.3 | 19 | 0.15 |
Critical ratio for Job d:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Job f has the lowest critical ratio. Hence, Job f would be completed next in the sequence of jobs after Job a, Job c, Job b, and Job e.
As Job d is the remaining job, it will be completed next.
Hence, the sequence of jobs using critical ratio is a-c-b-e-f-d.
Determine average flow time, average tardiness, and average number of jobs for critical ratio:
Job | Processing time (days) | Flow time (days) | Due date (days) | Tardiness |
a | 4.5 | 4.5 | 10 | 0 |
c | 5.2 | 9.7 | 12 | 0 |
b | 6 | 15.7 | 17 | 0 |
e | 2.8 | 18.5 | 18 | 0.5 |
f | 3.3 | 21.8 | 19 | 2.8 |
d | 1.6 | 23.4 | 27 | 0 |
Total | 23.4 | 93.6 | 3.3 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job a, Job c, Job b, and Job d:
Flow time of Job a, Job c, Job b, and Job d is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job e:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job e is 0.5.
Tardiness of Job f:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job f is 2.8.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 15.6 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 0.55 days.
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 4 jobs.
b)

To determine: Whether the average flow time and average number of jobs are equivalent for four sequencing rules.
Introduction: Sequencing is the process of arranging the jobs in certain order in which it should be performed.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine whether the average flow time and average number of jobs are equivalent for four sequencing rules:
Rule | Average flow time | Average number of jobs | Ratio |
FCFS | 15.25 | 3.91 | 3.9 |
SPT | 11.12 | 2.85 | 3.9 |
EDD | 15.6 | 4 | 3.9 |
CR | 15.6 | 4 | 3.9 |
Calculate ratio for FCFS:
It is calculated by dividing average flow time and average number of jobs.
Calculate ratio for SPT:
It is calculated by dividing average flow time and average number of jobs.
Calculate ratio for EDD:
It is calculated by dividing average flow time and average number of jobs.
Calculate ratio for CR:
It is calculated by dividing average flow time and average number of jobs.
c)

To determine: The processing sequence of the jobs using Slack per Operation (S/O) rule
Introduction: Slack per operation is a scheduling method that helps to determine the sequence of the operation. Slack is the difference between the due date and the required time to process certain job.
Answer to Problem 15P
Explanation of Solution
Given information:
The following information is given:
Job | Processing time (days) | Due date | Remaining number of operations |
a | 5 | 8 | 2 |
b | 6 | 5 | 4 |
c | 9 | 10 | 4 |
d | 7 | 12 | 3 |
e | 8 | 10 | 2 |
Determine the processing sequence of the jobs using Slack per Operation:
Job | Job time (days) | Due date (days) | Operations remaining | Slack | Slack per operation (S/O) | Rank |
a | 4.5 | 10 | 3 | 5.5 | 1.83 | 1 |
b | 6 | 17 | 4 | 11 | 2.75 | 3 |
c | 5.2 | 12 | 3 | 6.8 | 2.27 | 2 |
d | 1.6 | 27 | 5 | 25.4 | 5.08 | 5 |
e | 2.8 | 18 | 3 | 15.2 | 5.07 | 4 |
f | 3.3 | 19 | 1 | 15.7 | 15.7 | 6 |
Supporting calculation:
Processing time, due date, and remaining number of operation is given. Rank should be assigned according to the slack per operation.
Calculate slack:
It can be calculated by subtracting the processing time from the due date.
Note: The process continues for all the jobs:
Calculate slack per operation:
It can be calculated by dividing the slack value and the remaining number of operations.
Note: The process continues for all the jobs:
Hence, the sequence of jobs using S/O is a-c-b-e-d-f.
Want to see more full solutions like this?
Chapter 16 Solutions
Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
- Can you write me an email about addressing an issue to mentor my supervisor the right way of deligating operations dutiesarrow_forwardCan you right me an email about addressing an issue to mentor the right why of deligating operations dutiesarrow_forwardDefine delegation. Discuss in detail the four reasons why managers do delegation? Also statethe four main types of delegation.arrow_forward
- B) Going forward, is Lean/JIT worth the risks? Should it be embraced (why?), abandoned (if so, why & what are the costs), or modified (how?) Do you think Lean works or not? Please write a complete response (about 1-2 paragraphs each part). Each team member should discuss and contribute so that the group agrees on their joint response. Please help each other and build upon and/or challenge others' points (in a respectful way!)arrow_forwardDiscuss the principle reasons that employee benefits have risen over the past 20 years, along with how best an organization can provide employees with a fair wage yet also provide some level of employee benefit coverage.arrow_forwardPlease assist with the Case Study below as attached. Read the case study below and answer the questions that follow. The Importance of the Planning Phase to Project Success. Traditional wisdom is that planning and analysis are very important and the more there is in a project, the more successful the project will be. Time spent on these activities will reduce risk and increase project success. On the other hand, inadequate analysis and planning will lead to a failed project. If poor planning has led to failed projects, then perhaps billions of dollars have been lost. But how much is too much? “Light weight” project management techniques such as agile are gaining popularity. Part of their ethos is that less initial planning is better and an evolutionary process is more efficient. QUESTION 1 The article above states: “Traditional wisdom is that planning and analysis are very important and the more there is in a project, the more successful the project will be”. Describe FIVE (5) ways…arrow_forward
- On a daily basis, the van is dispatched from Maplewood Hospital to pickup blood and platelet donations made at its local donation centers. The distances in miles between all locations may be found in the table below. Click the icon to view mileage data for Vampire Van. a. The van travels from the Hospital (A) to (B) to (C) to (D) to (E) and then returns to the Hospital (A). What is the total number of miles that the van must travel using this route? Route ABCDEA requires a total distance of 20.4 miles. (Enter your response rounded to one decimal place.) b. Using Maplewood Hospital as the beginning location, create a route using the Nearest Neighbor heuristic. What is the total number of miles that the van must travel using this route? The new route is A A and requires a total distance of miles. (Enter your response rounded to one decimal place.) More Info Maplewood City Center Westbrook Hospital (A) Donation Site (B) Donation Site (C) Municipal Park Donation Site (D) Valley Hills…arrow_forwardView the video Noodles & Company (8.28minutes, Ctrl + Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 7 & 7S – service process design, type of job design, methods analysis, work methods, job design, learning curve effect, etc.) after watching this video. https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=E5i8OKgpqhwywhgFmpp1bmM Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) Leland, the job analyst at Zevo Toys, wanted to perform a time study on the assembling of toys. He observed one of the workers, Magorium, for five hours. During that time, Magorium assembled 250 toys. Leland rated Magorium as performing at 110 percent. The allowance for rest, personal time, etc. at Zevo Toys is 12 percent. a) Compute the normal time for the job. b) Compute the standard time for the job. Note: You could work out the problem by hand or use excel; in chapter 7,…arrow_forward1) Noodles & Company View the video Noodles & Company (8.28minutes, Ctrl + Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 7 & 7S – service process design, type of job design, methods analysis, work methods, job design, learning curve effect, etc.) after watching this video. https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=E5i8OKgpqhwywhgFmpp1bmM Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) Leland, the job analyst at Zevo Toys, wanted to perform a time study on the assembling of toys. He observed one of the workers, Magorium, for five hours. During that time, Magorium assembled 250 toys. Leland rated Magorium as performing at 110 percent. The allowance for rest, personal time, etc. at Zevo Toys is 12 percent. a) Compute the normal time for the job. b) Compute the standard time for the job. Note: You could work out the problem by hand or use…arrow_forward
- An investigation of career development opportunities and job satisfaction atarrow_forwardThe Donald Fertilizer Company produces industrial chemical fertilizers. The projected manufacturing requirements (in gallons) for the next four quarters are 90,000, 90,000, 60,000, and 140,000 respectively. A level workforce is desired, relying only on anticipation inventory as a supply option. Stockouts and backorders are to be avoided, as are overtime and undertime. a. Determine the quarterly production rate required to meet total demand for the year, and minimize the anticipation inventory that would be left over at the end of the year. Beginning inventory is 0. The quarterly production rate is 95000 gallons. (Enter your response as an integer.) b. Specify the anticipation inventory that will be produced. (Enter your responses as an integers.) Quarter Anticipation inventory (gallons) 1 5000 2 10000 3 4 45000 c. Suppose that the requirements (in gallons) for the next four quarters are revised to 140,000, 60,000, 90,000, and 90,000 respectively. If total demand is the same, what level…arrow_forwardPlease help with the attached Capstone proposal Requirements:arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Understanding Management (MindTap Course List)ManagementISBN:9781305502215Author:Richard L. Daft, Dorothy MarcicPublisher:Cengage Learning