a)1
Determine the total materials cost variance, price and usage variance, the cause of variance and responsible management position.
a)1

Explanation of Solution
Compute the total variance:
Hence, the total variances are $336,200 which is an unfavorable variance.
Compute the total materials price variance:
Hence, the total materials price variances are $172,200 which is an unfavorable variance.
Compute the total materials usage variance:
Hence, the total materials usage variances are $164,000 which is unfavorable variance.
K Company paid more than the budgeted for planks of wood.
The purchasing agent is responsible for the price variance. The variances are occurred because of factors like lumber shortage, and inflation.
K Company used more materials than planned which leads to unfavorable usage variance.
The production supervisor is the responsible party. The variances are occurred because of factors like lack of physically control over inventory and lack of motivation to workers.
2)
Determine the labor cost, price, and usage variance and the cause of variance and responsible management position.
2)

Explanation of Solution
Compute the total labor cost variance:
Hence, the labor variance is $49,200 which is an unfavorable variance.
Compute the labor price variance:
Hence, the labor price variance is $118,900 which is an unfavorable variance.
Compute the labor usage variance:
Hence, the labor usage variance is $69,700 which is a favorable variance.
K Company paid more than the budgeted.
The personnel manager and production supervisors are responsible for the variance. The variances are occurred because of factors like the minimum wages could have been raised by the government.
K Company used less labor than planned which leads to favorable usage variance.
The production supervisor or personal managers are the responsible party. These people motivate the employees and hired more competent people.
3)
Determine the fixed cost spending and variance and the cause of variance and refer whether the actual fixed cost per unit is lower or higher than the budgeted fixed cost per unit.
3)

Explanation of Solution
Compute the fixed cost spending variance:
Table (1)
Hence, the spending variance is $48,400 which is unfavorable variance.
Compute the fixed cost volume variance:
Table (2)
Hence, the volume variance is $32,000 which is favorable variance.
Working note:
Calculate the the predetermined
Hence, the predetermined overhead rate is $16 per table.
The Company K has paid more than the planned with respect to fixed cost. The plant manager is responsible for the rent on manufacturing equipment. The personnel manager is responsible for the salaries paid to the company supervisor.
More units were produced and sold which leads to favorable volume variance. This reduces the fixed cost per unit.
b)
Indicate that the total of material, labor, and overheads variance are equal to the total flexible
b)

Explanation of Solution
Note:
Refer the above part for the calculated values.
Table (3)
c)
Discuss the reaction of Person D reacts to the variance information
c)

Explanation of Solution
Discuss the reaction of Person D reacts to the variance information:
Person D should make an impartible and fair investigation on the responsible parties and causes.
Monitoring the performance is sufficient for the improvement and in the circumstances of intentional disregard and consistent incompetence the disciplinary actions can be taken.
Want to see more full solutions like this?
Chapter 15 Solutions
SURVEY OF ACCOUNTING(LL)>CUSTOM PKG.<
- Royal Designs creates custom furniture. During November, it had applied an overhead of $162,000. Overhead is applied at the rate of 80% of direct labor cost. Direct labor wages average $32 per hour. How many direct labor hours did Royal Designs have for the month of November?arrow_forwardCan you help me solve this general accounting problem using the correct accounting process?arrow_forwardMeridian Corporation applies overhead costs to jobs on the basis of direct labor costs. Job R, which was started and completed during the current period, shows charges of $8,250 for direct materials, $12,500 for direct labor, and $7,500 for overhead on its job cost sheet. Job S, which is still in process at year-end, shows charges of $4,200 for direct materials and $6,800 for direct labor. a. Should any overhead cost be applied to Job S at year-end? b. How much overhead cost should be applied to Job S?arrow_forward
- Hii teacher please provide for General accounting question answer do fastarrow_forwardI am searching for the most suitable approach to this financial accounting problem with valid standards.arrow_forwardThe predetermined overhead rate is $18.50 per direct labor hour. Job 678 required 420 total direct labor hours to complete, of which 280 hours were incurred during the current month. How much overhead should be applied to Job 678 during the current month?arrow_forward
- Griffin Corporation incurs a $22 per pound cost to produce Product X, which it then sells for $35 per pound. The company can further process Product X to produce Product Y. Product Y would sell for $48 per pound and would require an additional cost of $10 per pound to be produced. The differential revenue of producing Product Y is _. (The additional cost of $10 is not included in differential revenue)arrow_forwardI need assistance with this general accounting question using appropriate principles.arrow_forwardMehta Appliances is using the Gross Profit Method to estimate its ending inventory. The company’s current year sales and cost of inventory available for sale are $910,000 and $670,000, respectively. The company’s historical gross profit percentage is 40%. What is the estimated ending inventory.arrow_forward
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegePrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Survey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage Learning