
Concept explainers
a)
To determine: Sequence of jobs based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the
a)

Answer to Problem 19P
The sequence is A-B-C-D-E.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using FCFS:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
A | 20 | 20 | 180 | 130 | 149 | |
B | 30 | 50 | 200 | 150 | 179 | |
C | 10 | 60 | 175 | 180 | 189 | 14 |
D | 16 | 76 | 230 | 190 | 205 | |
E | 18 | 94 | 210 | 206 | 223 | 13 |
Total | 94 | 300 | 27 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130.
End day of Job A:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 149.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 179.
End day of Job C:
Start day of Job C is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 189.
End day of Job D:
Start day of Job D is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 205.
End day of Job E:
Start day of Job E is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 223.
Lateness of Job A, Job B, and Job D:
End day of Job A, Job B, and Job D is less than its respective due date. Hence, there would be no lateness.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 14.
Lateness of Job E:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job E is 13.
b)
To determine: Sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the earliest due date would be served first. Then, the process would be going on from the earliest due date to the latest due date.
b)

Answer to Problem 19P
The sequence is C-A-B-E-D.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using EDD:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
C | 10 | 10 | 175 | 130 | 139 | |
A | 20 | 30 | 180 | 140 | 159 | |
B | 30 | 60 | 200 | 160 | 189 | |
E | 18 | 78 | 210 | 190 | 207 | |
D | 16 | 94 | 230 | 208 | 223 | |
Total | 94 | 272 |
Working note:
Duration and due date for the jobs have been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on due date. Due date should be assembled in the ascending order.
End day of Job C:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 139.
End day of Job A:
Start day of Job A is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 159.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 189.
End day of Job E:
Start day of Job E is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 207.
End day of Job D:
Start day of Job D is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 223.
Lateness of Job A, Job B, Job C, Job D, and Job E:
End day of all the jobs is less than its respective due date. Hence, there would be no lateness.
c)
To determine: Sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule which helps to arrange the sequence in the order. Here, the job with the shortest duration would be served first. Then, the process would be going on from shortest to largest duration.
c)

Answer to Problem 19P
The sequence is C-D-E-A-B.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using SPT:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
C | 10 | 10 | 175 | 130 | 139 | |
D | 16 | 26 | 230 | 140 | 155 | |
E | 18 | 44 | 210 | 156 | 173 | |
A | 20 | 64 | 180 | 174 | 193 | 13 |
B | 30 | 94 | 200 | 194 | 223 | 23 |
Total | 94 | 238 | 36 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on the duration (processing time). The duration should be assembled in the ascending order.
End day of Job C:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 139.
End day of Job D:
Start day of Job D is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 155.
End day of Job E:
Start day of Job E is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 173.
End day of Job A:
Start day of Job A is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 193.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 223.
Lateness of Job C, Job D, and Job E:
End day of Job C, Job D, and Job E are less than its respective due date. Hence, there would be no lateness.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 13.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 23.
d)
To determine: Sequence of jobs based on decision rule Longest Processing Time (LPT).
Introduction: Largest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the largest duration would be served first. Then, the process would be going on from largest to shortest duration.
d)

Answer to Problem 19P
The sequence is B-A-E-D-C.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using LPT:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
B | 30 | 30 | 200 | 130 | 159 | |
A | 20 | 50 | 180 | 160 | 179 | |
E | 18 | 68 | 210 | 180 | 197 | |
D | 16 | 84 | 230 | 198 | 213 | |
C | 10 | 94 | 175 | 214 | 223 | 48 |
Total | 94 | 326 | 48 |
Working note:
Duration and due date for the jobs have been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on the duration (processing time). The duration should be assembled in the descending order
End day of Job B:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 159.
End day of Job A:
Start day of Job A is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 179.
End day of Job E:
Start day of Job E is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 197.
End day of Job D:
Start day of Job D is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 213.
End day of Job C:
Start day of Job C is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 223.
Lateness of Job B, Job A, Job E, and Job D:
End day of Job B, Job A, Job E, and Job D are less than its respective due date. Hence, there would be no lateness.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 48.
Summary:
Scheduling rule | Average lateness | Average flow time | Average number of jobs in system |
FCFS | 5.4 | 60.0 | 3.2 |
EDD | 0.0 | 54.4 | 2.9 |
SPT | 7.2 | 47.6 | 2.5 |
LPT | 9.6 | 65.2 | 3.5 |
First Come First Served (FCFS):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 5.4.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 60.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.2.
Earliest Due Date (EDD):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 0.0.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 54.4.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.9.
Shortest Processing Time (SPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 7.2.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 47.6.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.5.
Longest Processing Time (LPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 9.6.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 65.2.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.55.
Hence, Earliest Due Date is the best method for the average lateness. Shortest processing time has the minimum average flow time and average number of jobs in systems.
Want to see more full solutions like this?
Chapter 15 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- Following their early success and growth, Listo hired a number of new managers and employees. In response to the expansion of staff, Listo reorganized by adding layers of supervisors and managers between executive management and line staff; however, growth occurred so rapidly that proper training was not provided to the new employees. Management was less concerned with the employees’ opinions and was more focused on production and profit. Instead of enlisting employees’ opinions, more directive orders were given. The change and increased complexity associated with adding new layers to the hierarchy resulted in the organization’s goals and objectives becoming unclear. Employees began to complain about the new bureaucratic processes and the slow pace of decision-making. While the organization has been growing in size, productivity has slowed and quality has decreased. The turnover rate is higher than it has ever been, and the number of sick days that people take has doubled over the past…arrow_forwardFollowing their early success and growth, Listo hired a number of new managers and employees. In response to the expansion of staff, Listo reorganized by adding layers of supervisors and managers between executive management and line staff; however, growth occurred so rapidly that proper training was not provided to the new employees. Management was less concerned with the employees’ opinions and was more focused on production and profit. Instead of enlisting employees’ opinions, more directive orders were given. The change and increased complexity associated with adding new layers to the hierarchy resulted in the organization’s goals and objectives becoming unclear. Employees began to complain about the new bureaucratic processes and the slow pace of decision-making. While the organization has been growing in size, productivity has slowed and quality has decreased. The turnover rate is higher than it has ever been, and the number of sick days that people take has doubled over the past…arrow_forwardDiscuss in detail any five types of authority. give citations and referencearrow_forward
- Can you guys help me with this? Thank you! Business Environment: Provide insights into the guidelines for conducting business in the chosen country and working there as an expatriate. This information is vital for understanding the practicalities of engagement in that particular environment. The country in here is India Put the answer as bullet points, provide sources that have relevant information for the answer on economic factorsarrow_forwardCan you guys help me with this? Thank you! Intriguing Facts: Incorporate engaging facts about the country that enhance its value and uniqueness within the global supply chain landscape. These can include cultural anecdotes, technological innovations, or historical achievements. The country in here is India Put the answer as bullet points, provide sources that have relevant information for the answer on economic factorsarrow_forwardCan you guys help me with this? Thank you! Economic Factors: Evaluate the country's economic performance by analyzing key indicators such as GDP (Gross Domestic Product), GDP per capita, exports, and imports. These metrics provide insight into the country's economic prowess and its position in global trade. The country in here is India Put the answer as bullet points, provide sources that have relevant information for the answer on economic factorsarrow_forward
- provide scholarly reseach and define legal and complince risk and reputational risk in banking. Additionally 1. What more can be done about it 2. the department where the risk is exposed to 3. what strategy can be used 4. responsible personarrow_forwardRead the case in the link below and Develop a risk management programme appropriate for this case using the attached template. https://finopsinfo.com/investors/citis-900m-blunder-casts-light-on-poor-loan-ops/arrow_forwardDo the inherent differences between private and public sector objectives—profit versus publicgood—render private sector category management practices unsuitable for public sectorpurchasing, where open tendering is the norm?You have now undergone the Category Management classes and your superiors have requestedfor your input on how to integrate some of the learnings into the public sector policy. Discuss and elaborate what are the activities and governance you would introduce in yourrecommendations without violating the principle of transparency and accountability withinyour organisation. This is based on Singapore context. Pls provide a draft with explanation, examples and useful links for learning purposes. Citations will be good too. This is a module in SUSS called category management and supplier evaluationarrow_forward
- provide scholarly answers for what risk was associated with the Citibank bank loosing 50 million in August 2020arrow_forwardConclusion: The report recommendations and broad conclusion to the essay. TOTAL 5 100arrow_forwardAs part of your new role, as a strategy consultant and member of the steering committee, discuss what logistics and transportation strategies you will execute to achieve operational efficiencies and facilitate economic growth in SA. The committee would like to have a implementable strategic transport and logistics plan to realise the roadmap vision based on the subsection numbering given below! QUESTION ONE Introduction: Must include an overview and history of South Africa's Road, rail and freight transport network. Marks 5arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning


