Question
Chapter 15, Problem 1.1VC
Summary Introduction
Case summary:
The case deals about the conversion of concert to a basketball. The details about the center were given. The available crew size is given as 16. The following information is given in the case:
To draw: The Gantt chart to help Person C to organize his crew to perform the concert-to-basketball conversion.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Question: Create me an AON diagram for Production of High-Quality Organic Rice. You may assume the activities and days.
10:15
←
Assignment for chapter One.pdf
Operation Research
Assignment for Chapter One
Instructor: Wehliye
Operation Research
K 7
ку
5. Operation research analysis does not:
a) Predict future operation
b) Collect the relative data
4G 83%
个
Part One: Multiple Choice
1. A feasible solution to an lp problem
a) Must satisfy all of the problems constraints simultaneously
b) Need not satisfy all of the constraints, only some of them
c) Must be a corner point of the feasible region
d) Must optimize the value of the objective function
2. Which of the following statements is true with respect to the optimal solution
of an LP problem?
|||
L
a) Every LP problem has an optimal solution b) Optimal solution of an LP
problem always occur at an extreme point c) At optimal solution, all
resources are completely used d) If an optimal solution exists, there will
always be at least one at a corner
3. While plotting constraints on a graph paper, terminal points on both the axes
are connected by straight line…
QUESTION 6
The framing department has six jobs waiting to be processed as shown in Table 3 below. It is
now time zero and all jobs are ready to begin. Each has only one operation remaining.
Table 3
Jobs
(In order of arrival)
Processing Time
Due Date
A
5
12
B
7
18
C
8.
14
D
3
10
E
9
22
F
12
17
Using minimum flow time as the evaluation criterion, recommend the best rule to sequence
the jobs from the list below:
i. FCFS
ii. SOT
iii.
EDD
iv.
STR
Chapter 15 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 15 - Prob. 1EDCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Prob. 5DQCh. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Prob. 10DQCh. 15 - Prob. 11DQCh. 15 - Prob. 12DQCh. 15 - Prob. 13DQCh. 15 - Prob. 1PCh. 15 - Prob. 2PCh. 15 - Prob. 3PCh. 15 - Prob. 4PCh. 15 - Prob. 5PCh. 15 - Prob. 6PCh. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - Prob. 9PCh. 15 - Prob. 10PCh. 15 - Prob. 11PCh. 15 - Prob. 12PCh. 15 - Prob. 13PCh. 15 - Prob. 14PCh. 15 - Prob. 15PCh. 15 - Prob. 16PCh. 15 - Prob. 17PCh. 15 - Prob. 18PCh. 15 - Prob. 19PCh. 15 - Prob. 20PCh. 15 - Prob. 21PCh. 15 - Prob. 22PCh. 15 - Prob. 23PCh. 15 - Prob. 24PCh. 15 - Prob. 25PCh. 15 - Prob. 26PCh. 15 - Prob. 27PCh. 15 - Prob. 28PCh. 15 - Daniels Barber Shop at Newark Airport is open 7...Ch. 15 - Given the following demand for waiters and...Ch. 15 - Prob. 1CSCh. 15 - Prob. 2CSCh. 15 - Prob. 3CSCh. 15 - Prob. 4CSCh. 15 - Prob. 1.1VCCh. 15 - Prob. 1.2VCCh. 15 - Prob. 1.3VCCh. 15 - Prob. 2.1VCCh. 15 - Prob. 2.2VCCh. 15 - Why is seniority important in scheduling servers?Ch. 15 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Question 16 An activity on a PERT network has an optimistic time of 2 hours, a most likely time of 4 hours, and a pessimistic time of 14 hours. Find its STANDARD DEVIATION. O 2.5 hours O 1 hour O 0.5 hour 2 hours O 1.5 hoursarrow_forwardQuestion 3 of 19 The following table contains information concerning four jobs that are awaiting processing at a work center. Job Time Due date (days) (days) 14 10 7 6 Job A B C D Determine the average flow time using the EDD rule. Select the correct response: 20 20.5 19.75 21 20 16 15 17 ProviQUSarrow_forwardQuestion 2: A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 28 units. Assume the shop works a 56-minute hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules: (SEE PHOTO) a. What is Cycle time? (Round your answer to 1 decimal place.) In order of most following tasks. Tiebreaker: greatest positional weight. (Use your rounded cycle time. Enter your tasks in the order they were assigned at each station as a letter between a and h in lowercase with no other text or symbols. Round your numerical answers to 1 decimal place.) What is Efficiency? (Use your rounded cycle time in the denominator of your efficiency calculation. Round your answer to 1 decimal place.) b. In order of greatest positional weight. Tiebreaker: most following tasks. (Use your rounded cycle time. Enter your tasks in the order they were assigned at each station as a letter between a and…arrow_forward
- time (hours) pH 7.00 7.30 6.99 7.00 Assignment 1 2 7.12 7.25 7.12 7.20 3 720 7.16 720 7.16 4 6.98 7.00 6.94 7.00 5 6.99 6.99 6.99 6.98 6 7.00 6.93 7.02 6.93 7 6.92 7.00 6.92 7.02 Construct the X-Bar charts and R- charts 6.88 6.82 6.94 6.99 7.10 7.00 7.00 7.00 for reporting your results 10 721 7.02 721 7.04 11 7.01 6.86 7.01 6.90 12 6.86 6.98 6.90 6.98 13 6.90 7.00 6.87 7.00 14 7.01 7.04 7.01 7.05 15 7.00 6.95 7.00 6.99 16 7.09 7.20 7.03 7.20 17 6.89 7.14 6.87 7.15 18 6.98 6.80 6.98 6.89 19 7.00 6.90 7.00 6.90 20 7.20 7.00 723 7.00 21 7.04 7.03 7.08 7.00 22 6.90 6.92 6.98 6.92 23 7.00 7.00 7.00 7.00 24 7.00 6.97 7.01 6.98arrow_forwardQUESTION 1 Background The IT group at Fang Technology received approval to add a new entry-level systems analyst position. You will help set up the hiring timetable and create a task list to handle the interviewing logistics. After checking with several people in the IT department, you identified seven specific tasks, estimated their duration, and determined the order in which they should be performed. Now you need to create a work breakdown structure and a PERT chart that shows the task pattern and a critical path. Practice Tasks and Answers The IT group at Fang Technology has received approval to add a new entry-level systems analyst position. You will help set up the hiring timetable and tasks. After speaking to several people in the department, you identified seven tasks and the order in which they should be performed. Using your notes, you write up the following statement: First, review the applications (2 days). Then start three tasks: notify the IT team (2 days), reserve a…arrow_forwardQUESTION 2 Six processes are to be laid out in six areas in a company. The distance between adjacent work centres is 40 feet. The number of trips between work centres is given in the following table: FROM A B с D E F A TRIPS BETWEEN PROCESSES TO с 25 96 B 18 D 73 23 41 a) Assign the processes to the initial work areas and draw the total flow. E 12 31 22 19 F 54 45 20 57 48arrow_forward
- Mangement question Alpha Enterprises is a company manufacturing water geysers. The company has a functional structure with four main functions-Production, Marketing, Finance and Human Resource. As the demand for the product grew, the company decided to hire more employees. Identify the concept which will help the Human Resource Manager in deciding the actual number of persons required in each department.arrow_forwardQuestion 13 Jassim is a 'Team Leader' with a three month project to develop a new mobile phone app. Maryam is a member of Jassim's team and hence reports to Jassim. Maryam also reports to Faisal, the Product Development Manager. This is an example of a structure. A) functional B) product team customer D divisional E) matrix O 113 minutes remaining hparrow_forwardQuestion 2 Time Chart (WBS) I Description Feasibility Study Estimate production volumes Market Study Write SOP and BOM Activity Preceded by Time (wks) A 8 В 6. A 4 A 1 E Identify equipment and material C,D 3 F Prepare raw material requirements B 2 Prepare production volume target 6. Prepare project budget E,F Prepare resources budget Project Implementation E,F,G 6. J H,I Using the AOA format i. List out all the possible path activities? i. Identify the Critical Path and determine the total duration of the project? If this project must be finished in 22 weeks, write a short recommendation III. explaining which activities may have to be done more quickly?arrow_forward
- Question attachedarrow_forwardQuestion 1- Week 31 Ola Ltd, which uses a job costing system, had two jobs in process at the start of the year: Job L1 ($68,000) and Job L2 ($30 000). The following information is available: i) The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $1,000,000 and 25,000 hours, respectively. ii) The company worked on three jobs during the first quarter (i.e. from 1 January to 31 March). Direct materials used, direct labour incurred and machine hours consumed were as shown in the following table: Job numbers Direct material Direct labour Machine hours L1 $15,000 $30,000 900 L2 33,000 1,600 L3 45,000 65,000 2,000 ii) Manufacturing overhead incurred during the first quarter was $215,000. iv) Ola Ltd completed Job L1 and Job L2 during the first quarter. Job L2 was sold on credit, producing a profit of $30,000 for the company. Required: a) Calculate the company's predetermined overhead rate. b)…arrow_forward1. Explain human resources management in drink powder factory. 2. Explain labor specialization in drink powder factory with diagram. 3. Explain job expansion in drink powder factory with diagram.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.