You are expected to have the gift bags in Problem 14.1 ready at 5 P.M. However, you need to personalize the items (monogrammed pens, note pads, literature from the printer, etc.). The lead time is 1 hour to assemble 200 Js once the other items are prepared. The other items will take a while as well. Given the volunteers you have, the other time estimates are item K (2 hours), item L (1 hour), and item M (4 hours). Develop a time-phased assembly plan to prepare the gift bags.

14.1 You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 200 attendees. Assume that there is no inventory on hand of any of the items. Explode the bill of material. (Subscripts indicate the number of units required.)

Chapter 14, Problem 2P, You are expected to have the gift bags in Problem 14.1 ready at 5 P.M. However, you need to

Blurred answer
Students have asked these similar questions
Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule and lead times for the bracket. The unit is to be prepared in week 10. The lead times for the components a re bracket (I week), base (1 week), spring ( I week), clamp (I week), housing (2 weeks), handle (I week), casting (3 weeks), bearing (I week), and shaft (1 week).a) Prepare the time-phased product structure for the bracket.b) In what week do you need to start the castings?
You have developed the following simple product structure of items needed for your gift bag for a rush party for perspective pledges in your organization. You forecast 200 atendees. You are expected to have the gift bags ready at 5 pm. However, you need to personalize the items. The lead time is 1 hour to assemble 20” Js once the other items are prepared. The other items will take a while as well. Given the volunteers you have, the other time estimates are item K ( 1 hour), item L (1 hour), and item M (3 hours). Develop a time-phased assembly plan to prepare the gift bags
Consider the following product structure (bill of material).                   One hundred and fifty (150) units of Product A are needed in week 10. Assuming no on-hand inventory of A exists, explode the bill of material, and use the following information to construct a net requirements plan for all the items. You must use the template provided by the instructor and provide all the information needed on the template. There are no scheduled receipts for all the items.       Item On-hand Inventory Lead time (weeks) A 0 2 B 20 2 C 10 1 D 0 3 E 5 1 F 10 3           Item: LT=   1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirements                         Scheduled Receipts                         Projected on Hand                         Net Requirements…

Chapter 14 Solutions

Operations Management

Ch. 14 - Prob. 11DQCh. 14 - Identify five specific requirements of an...Ch. 14 - What are the typical benefits of ERP?Ch. 14 - What are the distinctions between MRP, DRP, and...Ch. 14 - As an approach to inventory management, how does...Ch. 14 - What are the disadvantages of ERP?Ch. 14 - Use the Web or other sources to: a. Find stories...Ch. 14 - Prob. 18DQCh. 14 - Use the Web or other sources to identify what an...Ch. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Using the information in Problem 14.3, construct a...Ch. 14 - Using the information in Problem 14.3, construct a...Ch. 14 - Refer again to Problems 14.3 and 14.4. In addition...Ch. 14 - Refer again to Problems 14.3 and 14.5. In addition...Ch. 14 - As the production planner for Scott Sampson...Ch. 14 - Prob. 9PCh. 14 - a. Given the product structure and master...Ch. 14 - Prob. 11PCh. 14 - Based on the data in Figure 14.13, complete a net...Ch. 14 - Prob. 13PCh. 14 - A part structure, lead time (weeks), and on-hand...Ch. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Data Table for Problems 14.17 through 14.20 14.17...Ch. 14 - Develop an EOQ solution and calculate total...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - Prob. 21PCh. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Karl Knapps, Inc., has received the following...Ch. 14 - Coleman Rich, Ltd., has received the following...Ch. 14 - Prob. 25PCh. 14 - Prob. 26PCh. 14 - Using the data for the coffee table in Problem...Ch. 14 - When 18,500 Orlando Magic Fans Come to Dinner...Ch. 14 - When 18,500 Orlando Magic Fans Come to Dinner...Ch. 14 - When 18,500 Orlando Magic Fans Come to Dinner...Ch. 14 - MRP at Wheeled Coach Video Case Wheeled Coach, the...Ch. 14 - MRP at Wheeled Coach Video Case Wheeled Coach, the...Ch. 14 - MRP at Wheeled Coach Video Case Wheeled Coach, the...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY