Principles Of Operations Management
Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
bartleby

Concept explainers

Question
Book Icon
Chapter 13, Problem 6P

a)

Summary Introduction

To evaluate: Plan D

Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

a)

Expert Solution
Check Mark

Answer to Problem 6P

Plan D has been evaluated. The total cost of plan D is $128,000.

Explanation of Solution

Given information:

The production for all the months is 1,600 units. Overtime cost is $50 per unit. The maximum allowable inventor in the warehouse is 400 units or less. The demand requirement from period 0 to 8 is as follows:

Period Expected demand
0 0
1 1,400
2 1,600
3 1,800
4 1,800
5 2,200
6 2,200
7 1,800
8 1,800

Evaluate the cost of the plan:

Plan D
Period Demand Production Overtime (units) Ending inventory Stock-outs (units) Extra cost
0 200
1 1,400 1,600 - 400 $8,000
2 1,600 1,600 - 400 $8,000
3 1,800 1,600 - 200 $4,000
4 1,800 1,600 - - $0
5 2,200 1,600 320 - 280 $44,000
6 2,200 1,600 320 - 280 $44,000
7 1,800 1,600 200 - $10,000
8 1,800 1,600 200 - $10,000
Total 14,600 1,040 1,000 $128,000

Note: Production is given as 1,600 units. The ending inventory for December is given as 200 units. If the production is more than or equal to the demand, then there would be inventory. If the demand is more, then there would be stock out. Maximum overtime units allowed is 320 units (20% of production)

Calculate the ending inventory or stock-out for Period 1:

It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 1 is 400.

Ending inventory=(Production+Ending inventory of previous month)Demand=(1,600+200)1,400=1,8001,400=400

Calculate the ending inventory or stock-out for Period 2:

It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 2 is 400.

Ending inventory=(Production+Ending inventory)Demand=(1,600+400)1,600=2,0001,600=400

Calculate the ending inventory or stock-out for Period 3:

It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 3 is 200.

Ending inventory=(Production+Ending inventory)Demand=(1,600+400)1,800=2,0001,800=200

Calculate the ending inventory or stock-out for Period 4:

It is calculated by adding the production and ending inventory of the previous month and subtracting the result from the demand. The ending inventory for Period 4 is 0.

Ending inventory=(Production+Ending inventory)Demand=(1,600+200)1,800=1,8001,800=0

Calculate the ending inventory or stock-out for Period 5:

As the demand is more than the production, there would be a stock-out.

It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 5 is 280 units.

Stock-out=(DemandProduction)Overtime unit=(2,2001,600)320=600320=280 units

Calculate the ending inventory or stock-out for Period 6:

As the demand is more than the production, there would be a stock-out.

It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 6 is 280 units.

Stock-out=(DemandProduction)Overtime unit=(2,2001,600)320=600320=280 units

Calculate the ending inventory or stock-out for Period 7:

It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 7 is 0 units.

Stock-out=(DemandProduction)Overtime unit=(1,8001,600)200=200200=0 units

Note: Overtime units of 320 units would lead to a negative value. Hence, it was taken as 200 units.

Calculate the ending inventory or stock-out for Period 8:

It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the stock-out units for Period 8 is 0 units.

Stock-out=(DemandProduction)Overtime unit=(1,8001,600)200=200200=0 units

Note: Overtime units of 320 units would lead to negative value. Hence, it was taken as 200 units.

Calculate the extra cost for Period 1:

It is calculated by multiplying the extra inventory units and inventory holding cost. The inventory holding cost is given as $20 per unit. Hence, the extra cost for period 1 is $8,000

Extra cost=Ending inventory×Inventory holding cost per unit=400×$20=$8,000

Calculate the extra cost for Period 2:

It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 2 is $8,000

Extra cost=Ending inventory×Inventory holding cost per unit=400×$20=$8,000

Calculate the extra cost for Period 3:

It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 3 is $4,000

Extra cost=Ending inventory×Inventory holding cost per unit=200×$20=$4,000

Calculate the extra cost for Period 4:

As there are no overtime units, ending inventory units, or stock-out units, there would not be any extra costs.

Calculate the extra cost for Period 5:

It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 5 is $44,000

Extra cost=(Overtime unit×Overtime cost per unit)+(Stock-out units×Stock-out cost per unit)=(320×$50)+(280×$100)=$44,000

Calculate the extra cost for Period 6:

It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 6 is $44,000

Extra cost=(Overtime unit×Overtime cost per unit)+(Stock-out units×Stock-out cost per unit)=(320×$50)+(280×$100)=$44,000

Calculate the extra cost for Period 7:

It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 7 is $10,000

Extra cost=(Overtime unit×Overtime cost per unit)=(200×$50)=$10,000

Calculate the extra cost for Period 8:

It is calculated by adding the product of overtime units and inventory holding overtime cost per unit, and the product of stock-out units and stock-out cost per unit. Stock-out cost is given as $100 per unit and overtime cost is given as $50 per unit. Hence, the extra cost for period 8 is $10,000

Extra cost=(Overtime unit×Overtime cost per unit)=(200×$50)=$10,000

Calculate the total cost of Plan D:

It is calculated by adding the extra costs of all the periods.

Total cost=Extra costs of all periods=$8,000+$8,000+$4,000+$0+$44,000+$44,000+$10,000+$10,000=$128,000

Hence, the total cost for Plan D is $128,000.

b)

Summary Introduction

To determine: Plan E

Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

b)

Expert Solution
Check Mark

Answer to Problem 6P

Plan E has been evaluated. The total cost of Plan E is $140,000.

Explanation of Solution

Given information:

Production for all the months is 1,600 units. Overtime cost is $50 per unit. Maximum allowable inventor in the warehouse is 400 units or less. Demand requirement from period 0 to 8 is as follows:

Period Expected demand
0 0
1 1,400
2 1,600
3 1,800
4 1,800
5 2,200
6 2,200
7 1,800
8 1,800

Evaluate the cost of the plan:

Plan E
Period Demand Production Subcontract (units) Ending inventory Extra cost
0 200
1 1,400 1,600 - 400 $8,000
2 1,600 1,600 - 400 $8,000
3 1,800 1,600 - 200 $4,000
4 1,800 1,600 - - $0
5 2,200 1,600 600 - $45,000
6 2,200 1,600 600 - $45,000
7 1,800 1,600 200 - $15,000
8 1,800 1,600 200 - $15,000
Total 14,600 1,600 1,000 $140,000

Note: Production is given as 1,600 units. The ending inventory for December is given as 200 units. If the production is more than or equal to the demand, then there would be inventory. If the demand is more, then there would be subcontract.

Calculate the ending inventory or subcontract for Period 1:

It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 1 is 400.

Ending inventory=(Production+Ending inventory of previous month)Demand=(1,600+200)1,400=1,8001,400=400

Calculate the ending inventory or subcontract for Period 2:

It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 2 is 400.

Ending inventory=(Production+Ending inventory)Demand=(1,600+400)1,600=2,0001,600=400

Calculate the ending inventory or subcontract for Period 3:

It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 3 is 200.

Ending inventory=(Production+Ending inventory)Demand=(1,600+400)1,800=2,0001,800=200

Calculate the ending inventory or subcontract for Period 4:

It is calculated by adding the production and ending inventory of previous month and subtracting the demand from the result. The ending inventory for Period 4 is 0.

Ending inventory=(Production+Ending inventory)Demand=(1,600+200)1,800=1,8001,800=0

Calculate the ending inventory or subcontract for Period 5:

As the demand is more than the production, there would be a subcontract.

It is calculated by subtracting the production from the demand. Hence, the subcontract units for Period 5 is 600 units.

Stock-out=(DemandProduction)=(2,2001,600)=600 units

Calculate the ending inventory or subcontract for Period 6:

As the demand is more than the production, there would be a subcontract.

It is calculated by subtracting the production from the demand. Hence, the subcontract units for Period 6 is 600 units.

Stock-out=(DemandProduction)=(2,2001,600)=600 units

Calculate the ending inventory or subcontract for Period 7:

It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the subcontract units for Period 7 is 200 units.

Stock-out=(DemandProduction)=(1,8001,600)=200 units

Calculate the ending inventory or subcontract for Period 8:

It is calculated by subtracting the production from the demand. The result should then be subtracted from the overtime units. Hence, the subcontract units for Period 8 is 0 units.

Stock-out=(DemandProduction)=(1,8001,600)=200 units

Calculate the extra cost for Period 1:

It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 1 is $8,000

Extra cost=Ending inventory×Inventory holding cost per unit=400×$20=$8,000

Calculate the extra cost for Period 2:

It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 2 is $8,000

Extra cost=Ending inventory×Inventory holding cost per unit=400×$20=$8,000

Calculate the extra cost for Period 3:

It is calculated by multiplying the extra inventory units and inventory holding cost. Inventory holding cost is given as $20 per unit. Hence, the extra cost for period 3 is $4,000

Extra cost=Ending inventory×Inventory holding cost per unit=200×$20=$4,000

Calculate the extra cost for Period 4:

As there are no overtime units, ending inventory units, and subcontract units, there would not be extra costs.

Calculate the extra cost for Period 5:

It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 5 is $45,000

Extra cost=(Subcontract units×Subcontract cost per unit)=(600×$75)=$45,000

Calculate the extra cost for Period 6:

It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 6 is $45,000

Extra cost=(Subcontract units×Subcontract cost per unit)=(600×$75)=$45,000

Calculate the extra cost for Period 7:

It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 7 is $15,000

Extra cost=(Subcontract units×Subcontract cost per unit)=(200×$75)=$15,000

Calculate the extra cost for Period 8:

It is calculated by multiplying the subcontract units and subcontract cost per unit. Subcontract cost is given as $75 per unit. Hence, the extra cost for period 8 is $15,000

Extra cost=(Subcontract units×Subcontract cost per unit)=(200×$75)=$15,000

Calculate the total cost of Plan E:

It is calculated by adding the extra costs of all the periods.

Total cost=Extra costs of all periods=$8,000+$8,000+$4,000+$0+$45,000+$45,000+$15,000+$15,000=$140,000

Hence, the total cost for Plan E is $140,000.

Conclusion

The total cost for Plan D is preferable when compared with Plan E. However, Plan C, with the total cost of $86,000 is preferable over other plans.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
What is a bottleneck? Would you try to reduce a bottleneck? Why or why not? Please provide a reference
Your firm has been the auditor of Caribild Products, a listed company, for a number of years. The  engagement partner has asked you to describe the matters you would consider when planning the audit for  the year ended 31January 2022. During  recent visit to the company you obtained the following information: (a) The management accounts for the 10 months to 30 November 2021 show a revenue of $260 million and profit before tax of $8 million. Assume sales and profits accrue evenly throughout the year. In the year ended 31 January 2021 Caribild Products had sales of $220 million and profit before tax of $16 million. (b) The company installed a new computerised inventory control system which has operated from 1 June  2021. As the inventory control system records inventory movements and current inventory quantities, the company is proposing: (i) To use the inventory quantities on the computer to value the inventory at the year-end (ii) Not to carry out an inventory count at the year-end (c)…
Develop and implement a complex and scientific project for an organisation of your choice. please include report include the following: Introduction Background research to the project The 5 basic phases in the project management process Project Initiation Project Planning Project Execution Project Monitoring and Controlling Project Closing Conclusion
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning