Concept explainers
Dwayne Cole, owner of a Florida firm that manufactures display cabinets, develops an 8-month aggregate plan. Demand and capacity (in units) are
The cost of producing each unit is $1,000 on regular time, $1,300 on overtime, and $1,800 on a subcontract. Inventory carrying cost is $200 per unit per month. There is no beginning or ending inventory in stock, and no backorders are permitted from period to period.
Let the production (workforce) vary by using regular time first, then overtime, and then subcontracting.
a) Set up a production plan that minimizes cost by producing exactly what the demand is each month. This plan allows no backorders or inventory. What is this plan’s cost?
b) Through better planning, regular time production can be set at exactly the same amount, 275 units, per month. If demand cannot be met there is no cost assigned to shortages and they will not be filled. Does this alter the solution?
c) If overtime costs per unit rise from $1,300 to $1,400, will your answer to (a) change? What if overtime costs then fall to $1,200?
a)
To determine: The total cost of the plan.
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 19P
The total cost of the plan is $2,608,300.
Explanation of Solution
Given information:
Regular time cost per unit is given as $1,000, overtime cost is $1,300, and subcontract cost is $1,800 per unit. The capacity and demand are given as follows:
Month | Demand | Regular time capacity | Overtime capacity | Subcontract capacity |
Initial | 0 | 0 | 0 | 0 |
January | 255 | 235 | 20 | 12 |
February | 294 | 255 | 24 | 16 |
March | 321 | 290 | 26 | 15 |
April | 301 | 300 | 24 | 17 |
May | 330 | 300 | 30 | 17 |
June | 320 | 290 | 28 | 19 |
July | 345 | 300 | 30 | 19 |
August | 340 | 290 | 30 | 20 |
Calculate the total cost:
Table 1
Working note:
Demand, regular time capacity, overtime capacity, and subcontract capacity are given.
Determine regular time, overtime, and subcontract units for the month of January:
It is given that the demand for the month of January is 255 units. 235 units would be produced in the regular time (as the regular time capacity is 235). Remaining 20 units would be produced in the overtime (as the overtime capacity is 20). Hence, regular time unit is 235 units and overtime unit is 20 units.
Determine regular time, overtime, and subcontract units for the month of February:
It is given that the demand for the month of February is 294 units. 255 units would be produced in the regular time (as the regular time capacity is 255). From the remaining 39 units, 24 units would be produced in the overtime (as the overtime capacity is 24) and 15 units would be produced using subcontract (as the subcontract capacity is 16). Hence, regular time unit is 255 units, overtime unit is 24 units, and subcontract unit is 15 units.
Determine regular time, overtime, and subcontract units for the month of March:
It is given that the demand for the month of March is 321 units. 290 units would be produced in the regular time (as the regular time capacity is 290). From the remaining 31 units, 26 units would be produced in the overtime (as the overtime capacity is 26) and 5 units would be produced using subcontract (as the subcontract capacity is 15). Hence, regular time unit is 290 units, overtime unit is 26 units, and subcontract unit is 5 units.
Note: The procedure continues for all months.
Increase or decrease for the month of January:
There would be no increase or decrease for the month of January as there is no period compare.
Increase or decrease for the month of February:
Production in the month of January is 235 units and production in the month of February is 255 units. There is an increase of 20 units. Hence, there would be 20 units increase in February.
Increase or decrease for the month of March:
Production in the month of February is 255 units and production in the month of March is 290 units. There is an increase of 35 units. Hence, there would be 35 units increase in March.
Increase or decrease for the month of April:
Production in the month of March is 290 units and production in the month of April is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in April.
Increase or decrease for the month of May:
Production in the month of April is 300 units and production in the month of May is 300 units. As there is no change in the production units, there would not be any increase or decrease.
Increase or decrease for the month of June:
Production in the month of May is 300 units and production in the month of June is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in June.
Increase or decrease for the month of July:
Production in the month of June is 290 units and production in the month of July is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in July.
Increase or decrease for the month of August:
Production in the month of July is 300 units and production in the month of August is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in August.
Summary of the table:
Type | Units | Cost |
Regular time | 2,260 | $2,260,000 |
Overtime | 189 | $245,700 |
Subcontract | 57 | $102,600 |
Holding | 0 | 0 |
Shortage | 0 | 0 |
Increase | 75 | 0 |
Decrease | 20 | 0 |
$2,608,300 |
Table 2
Working note:
Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 1.
Calculate the regular time cost:
Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,260,000.
Calculate the overtime cost:
Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $245,700.
Calculate the subcontract cost:
Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $102,600.
Calculate the increase and decrease cost:
As there is no increase or decrease cost per unit, it would remain 0.
Calculate the total cost:
Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.
Hence, the total cost of the plan is $2,608,300.
b)
To determine: The total cost of the plan.
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 19P
The total cost of the plan is $2,585,100.
Explanation of Solution
Given information:
Regular time cost per unit is given as $1,000, overtime cost is $1,300, and subcontract cost is $1,800 per unit. The capacity and demand are given as follows:
Month | Demand | Regular time capacity | Overtime capacity | Subcontract capacity |
Initial | 0 | 0 | 0 | 0 |
January | 255 | 275 | 20 | 12 |
February | 294 | 275 | 24 | 16 |
March | 321 | 275 | 26 | 15 |
April | 301 | 275 | 24 | 17 |
May | 330 | 275 | 30 | 17 |
June | 320 | 275 | 28 | 19 |
July | 345 | 275 | 30 | 19 |
August | 340 | 275 | 30 | 20 |
Calculate the total cost:
Table 3
Working note:
Demand, regular time capacity, overtime capacity, and subcontract capacity are given.
Determine regular time, overtime, and subcontract units for the month of January:
It is given that the demand for the month of January is 255 units. Whole 255 units would be produced in the regular time (as the regular time capacity is 275). Hence, regular time unit is 255 units.
Determine regular time, overtime, and subcontract units for the month of February:
It is given that the demand for the month of February is 294 units. 275 units would be produced in the regular time (as the regular time capacity is 275). Remaining 19 units would be produced in the overtime (as the overtime capacity is 24). Hence, regular time unit is 275 units and overtime unit is 19 units.
Determine regular time, overtime, and subcontract units for the month of March:
It is given that the demand for the month of March is 321 units. 275 units would be produced in the regular time (as the regular time capacity is 290). From the remaining 46 units, 26 units would be produced in the overtime (as the overtime capacity is 26) and 15 units would be produced using subcontract (as the subcontract capacity is 15). Hence, regular time unit is 275 units, overtime unit is 26 units, and subcontract unit is 15 units. Remaining 5 units is a shortage.
Note: The procedure continues for all months.
Increase or decrease for the month of January:
There would be no increase or decrease for the month of January as there is no period compare.
Increase or decrease for the month of February:
Production in the month of January is 255 units and production in the month of February is 275 units. There is an increase of 20 units. Hence, there would be 20 units increase in February.
Increase or decrease from the month of March to August:
As the production for regular time remains the same, there would be no increase or decrease from the month of March to August.
Summary of the table:
Type | Units | Cost |
Regular time | 2,180 | $2,180,000 |
Overtime | 187 | $243,100 |
Subcontract | 90 | $162,000 |
Holding | 0 | 0 |
Shortage | 49 | 0 |
Increase | 20 | 0 |
Decrease | 0 | |
$2,585,100 |
Table 4
Working note:
Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 3.
Calculate the regular time cost:
Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,180,000.
Calculate the overtime cost:
Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $243,100.
Calculate the subcontract cost:
Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $162,000.
Calculate the increase and decrease cost:
As there is no increase or decrease cost per unit, it would remain 0.
Calculate the total cost:
Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.
Hence, the total cost of the plan is $2,585,100.
c)
To determine: The total cost of the plan, if the overtime increased to $1,400.
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 19P
The total cost of the plan is $2,627,200.
Explanation of Solution
Given information:
Regular time cost per unit is given as $1,000, overtime cost is $1,400, and subcontract cost is $1,800 per unit. The capacity and demand are given as follows:
Month | Demand | Regular time capacity | Overtime capacity | Subcontract capacity |
Initial | 0 | 0 | 0 | 0 |
January | 255 | 235 | 20 | 12 |
February | 294 | 255 | 24 | 16 |
March | 321 | 290 | 26 | 15 |
April | 301 | 300 | 24 | 17 |
May | 330 | 300 | 30 | 17 |
June | 320 | 290 | 28 | 19 |
July | 345 | 300 | 30 | 19 |
August | 340 | 290 | 30 | 20 |
Calculate the total cost:
Table 5
Working note:
Demand, regular time capacity, overtime capacity, and subcontract capacity are given.
Determine regular time, overtime, and subcontract units for the month of January:
It is given that the demand for the month of January is 255 units. 235 units would be produced in the regular time (as the regular time capacity is 235). Remaining 20 units would be produced in the overtime (as the overtime capacity is 20). Hence, regular time unit is 235 units and overtime unit is 20 units.
Determine regular time, overtime, and subcontract units for the month of February:
It is given that the demand for the month of February is 294 units. 255 units would be produced in the regular time (as the regular time capacity is 255). From the remaining 39 units, 24 units would be produced in the overtime (as the overtime capacity is 24) and 15 units would be produced using subcontract (as the subcontract capacity is 16). Hence, regular time unit is 255 units, overtime unit is 24 units, and subcontract unit is 15 units.
Determine regular time, overtime, and subcontract units for the month of March:
It is given that the demand for the month of March is 321 units. 290 units would be produced in the regular time (as the regular time capacity is 290). From the remaining 31 units, 26 units would be produced in the overtime (as the overtime capacity is 26) and 5 units would be produced using subcontract (as the subcontract capacity is 15). Hence, regular time unit is 290 units, overtime unit is 26 units, and subcontract unit is 5 units.
Note: The procedure continues for all months.
Increase or decrease for the month of January:
There would be no increase or decrease for the month of January as there is no period compare.
Increase or decrease for the month of February:
Production in the month of January is 235 units and production in the month of February is 255 units. There is an increase of 20 units. Hence, there would be 20 units increase in February.
Increase or decrease for the month of March:
Production in the month of February is 255 units and production in the month of March is 290 units. There is an increase of 35 units. Hence, there would be 35 units increase in March.
Increase or decrease for the month of April:
Production in the month of March is 290 units and production in the month of April is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in April.
Increase or decrease for the month of May:
Production in the month of April is 300 units and production in the month of May is 300 units. As there is no change in the production units, there would not be any increase or decrease.
Increase or decrease for the month of June:
Production in the month of May is 300 units and production in the month of June is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in June.
Increase or decrease for the month of July:
Production in the month of June is 290 units and production in the month of July is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in July.
Increase or decrease for the month of August:
Production in the month of July is 300 units and production in the month of August is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in August.
Calculate the total cost if the overtime cost per unit increased to $1,400:
Type | Units | Cost |
Regular time | 2,260 | $2,260,000 |
Overtime | 189 | $264,600 |
Subcontract | 57 | $102,600 |
Holding | 0 | 0 |
Shortage | 0 | 0 |
Increase | 75 | 0 |
Decrease | 20 | 0 |
$2,627,200 |
Table 6
Working note:
Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 5.
Calculate the regular time cost:
Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,260,000.
Calculate the overtime cost:
Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $264,600.
Calculate the subcontract cost:
Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $102,600.
Calculate the increase and decrease cost:
As there is no increase or decrease cost per unit, it would remain 0.
Calculate the total cost:
Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.
Hence, the total cost of the plan is $2,627,200.
Calculate the total cost if the overtime cost per unit increased to $1,200:
Type | Units | Cost |
Regular time | 2,260 | $2,260,000 |
Overtime | 189 | $226,800 |
Subcontract | 57 | $102,600 |
Holding | 0 | 0 |
Shortage | 0 | 0 |
Increase | 75 | 0 |
Decrease | 20 | 0 |
$2,589,400 |
Table 7
Working note:
Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 6.
Calculate the regular time cost:
Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,260,000.
Calculate the overtime cost:
Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $264,600.
Calculate the subcontract cost:
Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $102,600.
Calculate the increase and decrease cost:
As there is no increase or decrease cost per unit, it would remain 0.
Calculate the total cost:
Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.
Hence, the total cost of the plan is $2,589,400.
Want to see more full solutions like this?
Chapter 13 Solutions
Principles Of Operations Management
- This area of emotional intelligence describes your ability to not only understand your strengths and weaknesses but to recognize your emotions and their effect on you and your team’s performance self management self awareness relationship management social awarenessarrow_forwardEmotional intelligence is defined as the ability to understand and manage your emotions, as well as recognize and influence the emotions of those around you. True Falsearrow_forwardAt the Ford automobile Highland plant, assume the one-millionth vehicle was produced in 1916 at a cost of $8084 (in 2013 US$), by how much did the Ford company reduce his cost with each doubling of cumulative output from 1916 to 1927?arrow_forward
- At the Ford automobile Highland plant,in 1913, how long did the average worker stay with the plant and what was the average tenure of a worker?arrow_forwardCommunity Federal Bank in Dothan, Alabama, recently increased its fees to customers who use employees as tellers. Management is interested in whether its new tee policy has increased the number of customers now using its automatic teller machines to that point that more machines are required. The following table provides the number of automatic teller transactions by week. Use trend projection with regression to forecast usage for weeks 13-16.arrow_forwardDavison Electronics manufactures three LED television monitors, identified as Model A, Model B, and Model C. Davison Electronics four manufacturing plants. Each model has its lowest possible production cost when produced at Plant 1. However, Plant 1 does not have the capacity to handle the total production of all three models. As a result, at least some of the production must be routed to the other manufacturing plants. The following table shows the minimum production requirements for next month, the plant capacities in units per month, and the production cost per unit at each plant: Model Production Cost per Unit Minimum Production Requirements Plant 1 Plant 2 Plant 3 Plant 4 A $25 $28 $37 $34 48,000 B $26 $35 $36 $41 75,000 C $20 $31 $26 $23 60,000 Production Capacity 65,000 50,000 32,000 43,000 Davison’s objective is to determine the cost-minimizing production planarrow_forward
- Anecdotally, entrepreneurs frequently encounter two critical dilemmas in managing human resources: the timing of hiring and the decision regarding hiring a generalist versus a specialist for their growing venture. Deciding when to expand a team is crucial, as premature hiring (i.e., hiring too soon) can strain resources, while delayed hiring (i.e., hiring too late) might hinder growth opportunities. Moreover, the choice between hiring a generalist or a specialist depends on the specific needs and stage of the venture, with each option presenting distinct advantages and challenges. To address these issues, a management scholar seeks to identify the factors shaping the hiring cycle throughout the entrepreneurial journey and to understand the criteria for choosing between generalists and specialists at various stages of a venture. The scholar has assembled a sample of 20 experienced South African entrepreneurs who have encountered both failure and success in the financial technology…arrow_forward3. [25 pts.] Four projects are available for investment. The projects require the cash flows and yield the net present values (NPV) (in millions) shown in the following table. Project id. 1 2 Cash outflow at time 0 (million Lira) 8 8 NPV (million Lira) 12 11 3 4 6 5 8 6 If 20 million Lira is available for investment at time 0, find the investment plan that maximizes NPV. All investments are required to be 0 or 1 (fractional investment values are not permitted). a. Formulate the mathematical model. (Write the decision variables, objective function and the constraints.) [10 pts.] b. Find the optimal solution by using Branch and Bound method (Draw the branch and bound tree clearly, write also lower bounds(LB)) (Left branches x=0, right branches x =1) [15 pts.].arrow_forwardexamine the production concept and operations management, what are the key steps required to achieve success? Be specific in your response.arrow_forward
- Produce a 3000 report with references on one international organization of your choice and Address the following: Provide a brief introduction of the organisation and sector it operates in, including its mission and vision statements, its core values, a summary of its financial performance and a general overview of the business’s operational activities. From the relevant literature explain the Total Quality Management (TQM) processes the chosen organization follows and identify one quality challenge/issue that the organization faced or is currently facing. Explain how the organization managed/or still managing the particular quality challenge/issue. Critically analyze whether the organization failed or succeeded in achieving and maintaining quality performance. Provide a few critical recommendations for business managers in order to highlight the importance of Total Quality Management (TQM) within an organization.arrow_forward問題2 Production system design involves determining the arrangement of workstations and the... O allocation of resources to workstations design of the process O production schedule all of the abovearrow_forwardElaborate on the need for and the benefits of an effective supply chain management (SCM) system in the context of a globalized and networked economy. In your answer, explain how organizations like Dell and Hewlett-Packard leverage supply chain networks to maintain competitiveness, and analyse the impact of globalization, technological advancements, and business environment changes on supply chain structures. Additionally, evaluate the key components of SCM, including distribution network configuration, inventory management, and cash-flow management, and discuss how these components contribute to creating an effective and integrated supply chain. (15) 3.2. Critically evaluate the requirements for effective inventory management within an organization. In your answer, discuss the importance of inventory accounting systems, the role of cost information (holding, ordering, and shortage costs), and the significance of classification systems like ABC analysis. Additionally, analyse how…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningMarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing