Compute lead time
Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 40 parts. A part requires 6 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 5 minutes.
Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 5 parts and the move time is eliminated.
Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. Round percentages to one decimal place.
Want to see the full answer?
Check out a sample textbook solutionChapter 13 Solutions
Managerial Accounting
- Bienestar Inc., has the following departmental structure for producing a well-known multivitamin: A consultant designed the following cellular manufacturing structure for the same product: The times above the processes represent the time required to process one unit of product. Required: 1. Calculate the time required to produce a batch of 15 bottles using a batch-processing departmental structure. 2. Calculate the time to process 15 units using cellular manufacturing. 3. How much manufacturing time will the cellular manufacturing structure save for a batch of 15 units?arrow_forwardHealthway uses a process-costing system to compute the unit costs of the minerals that it produces. It has three departments: Mixing, Tableting, and Bottling. In Mixing, at the beginning of the process all materials are added and the ingredients for the minerals are measured, sifted, and blended together. The mix is transferred out in gallon containers. The Tableting Department takes the powdered mix and places it in capsules. One gallon of powdered mix converts to 1,600 capsules. After the capsules are filled and polished, they are transferred to Bottling where they are placed in bottles, which are then affixed with a safety seal and a lid and labeled. Each bottle receives 50 capsules. During July, the following results are available for the first two departments (direct materials are added at the beginning in both departments): Overhead in both departments is applied as a percentage of direct labor costs. In the Mixing Department, overhead is 200 percent of direct labor. In the Tableting Department, the overhead rate is 150 percent of direct labor. Required: 1. Prepare a production report for the Mixing Department using the weighted average method. Follow the five steps outlined in the chapter. Round unit cost to three decimal places. 2. Prepare a production report for the Tableting Department. Materials are added at the beginning of the process. Follow the five steps outlined in the chapter. Round unit cost to four decimal places.arrow_forwardJackson Fabricators Inc. machines metal partS TOI he dutomove mOusuryUnu e two processes: milling and finishing. Parts are produced in batch slzes of 60 parts, A part requires 3 minutes in milling and 9 minutes in finishing. The move time between the two operations for a complete batch is 10 minutes. Under the lean philosophy, the part is produced in a cell that Includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 5 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methads. If required, round percentages to one decimal place.arrow_forward
- CardioTrainer Equipment Company manufactures stationary bicycles and treadmills. The products are produced in the Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $22 per machine hour (mh) Assembly $12 per direct labor hour (dlh) Setup $40 per setup Inspecting $18 per inspection Production scheduling $8 per production order Purchasing $5 per purchase order The activity-base usage quantities and units produced for each product were as follows: Stationary Bicycle Treadmill Machine hours 1,680 1,070 Direct labor hours 243 131 Setups 45 20 Inspections 158 94 Production orders 60 32 Purchase orders 240 98 Units produced 500 350 Use the activity rate and usage information to compute the total activity…arrow_forwardWilliams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows:Step Time (in minutes)Process Step 1 5Process Step 2 8Process Step 3 4Process Step 4 3The time required to move each batch between steps is 4 minutes. In addition, the time to move raw materials to Process Step 1 is also 4 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 6 minutes. The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the:a. present and b. proposed production approaches. (Round percentages to one decimal…arrow_forwardGray Fullbuster produces two different products (Square Ice Cube Trays and Round Ice Cube Trays) using two different activities: Machining, which uses machine hours as an activity driver, and Inspection, which uses number of batches as an activity driver. The activity rate for Machining is $170 per machine hour, and the activity rate for Inspection is $510 per batch. The activity drivers are used as follows: Machine hours Number of batches Square Ice Cube Trays 1,700 51 Round Ice Cube Trays 3,400 18 Total 5,100 69 What is the amount of Inspection cost assigned to Square Ice Cube Trays? Multiple Choice $26,010 $9,180 $289,000 $35,190arrow_forward
- Lynwood, Inc. produces two different products (Product A and Product X) using two different activities: Machining, which uses machine hours as an activity driver, and Inspection, which uses number of batches as an activity driver. The activity rate for Machining is $130 per machine hour, and the activity rate for Inspection is $520 per batch. The activity drivers are used as follows: Product A Product X Total Machine hours 1,200 3,200 4,400 Number of batches 46 16 62 What is the amount of Machining cost assigned to Product X? Multiple Choice $416,000 $27,500 $520,000 $130,000arrow_forwardCycle Time, Velocity, Product Costing Mulhall, Inc., has a JIT system in place. Each manufacturing cell is dedicated to the production of a single product or major subassembly. One cell, dedicated to the production of mopeds, has four operations: machining, finishing, assembly, and qualifying (testing). The machining process is automated, using computers. In this process, the model’s frame and engine are constructed. In finishing, the frame is sandblasted, buffed, and painted. In assembly, the frame and engine are assembled. Finally, each model is tested to ensure operational capability. For the coming year, the moped cell has the following budgeted costs and cell time (both at theoretical capacity): Budgeted conversion costs $5,541,120 Budgeted materials $18,668,000 Cell time 35,520 Theoretical output 17,760 models During the year, the following actual results were obtained: Actual conversion costs $5,541,120 Actual materials $4,009,000 Actual cell time…arrow_forwardWilliams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Step Time (in minutes) Process Step 1 5 Process Step 2 8 Process Step 3 4 Process Step 4 3 The time required to move each batch between steps is 4 minutes. In addition, the time to move raw materials to Process Step 1 is also 4 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 6 minutes. The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the: present and proposed production…arrow_forward
- Isaacson Dental Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 50 units. The process time for each step is as follows: Process Step 1 Process Step 2 Process Step 3 Process Step 4 6 minutes 12 minutes 9 minutes 3 minutes The time required to move each batch between steps is 6 minutes. In addition, the time to move raw materials to Process Step 1 is also 6 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 6 minutes. The new lean layout will allow the company to reduce the batch sizes from 50 units to 2 units. The time required to move each batch between steps and the inventory locations will be reduced to 1 minute. The processing time in each step will stay the same. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the (a) present and (b) proposed production approaches. If required, round…arrow_forwardWilliams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials to Process Step 1 is also 5 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 5 minutes. The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the present and proposed production approaches. If required,…arrow_forwardCardioTrainer Equipment Company manufactures stationary bicycles and treadmills. The products are produced in the Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows:ActivityActivity RateFabrication$22 per machine hour (mh)Assembly$12 per direct labor hour (dlh)Setup$40 per setupInspecting$18 per inspectionProduction scheduling$8 per production orderPurchasing$5 per purchase orderThe activity-base usage quantities and units produced for each product were as follows:Stationary BicycleTreadmillMachine hours1,6801,070 Direct labor hours243131 Setups4520 Inspections15894 Production orders6032 Purchase orders24098 Units produced500350Use the activity rate and usage information to compute the total activity costs and the activity costs per unit for each product. If required, round your answers to two decimal places.arrow_forward
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning