
Concept explainers
The preference of one alternative out of the three based on economic criteria by using the present worth, equivalent annual cost, benefit-cost ratio and rate of return methods.

Answer to Problem 14P
Alternative 3- Intersection widening
Explanation of Solution
Given:
Analysis period = 20 years
Annual interest rate = 15 percent
Calculation:
Determine the present worth of alternative 1 (Traffic signals):
Determine the present worth of alternative 2 (Intersection widening):
Determine the present worth of alternative 3 (Grade separation):
The project with the highest present worth is alternative 2.
Determine the equivalent annual cost of alternative 1 (Traffic signals):
Determine the equivalent annual cost of alternative 2 (Intersection widening):
Determine the equivalent annual cost of alternative 3 (Grade separation):
The project with the highest equivalent annual costis alternative 2.
Determine the benefit-cost ratioof alternative 1 (Traffic signals):
Determine the benefit-cost ratio of alternative 2 (Intersection widening):
Since BCR >1, we would select Alternative 2.
Determine the benefit-cost ratio of alternative 3 (Grade separation):
Since BCR is less than 1, we would not select Alternative 3
Determine the benefit-cost ratio of alternative 2 with respect to 1:
We reachthe same conclusion as previously, which is to select Alternative 2
Determine the rate of return (ROR)of alternative 1versus 2:
It is very difficult to solve this explicitly for i. By trial and error, we can easily find the i that makes the right side of the equation equal to the left side.
Try
For
Then, we can try
Since ROR is greater than 15 percent, we select Alternative 2
Determine the rate of return (ROR) of alternative 3 versus 1:
By trial and error, we can easily find the i that makes the right side of the equation equal to the left side.
Try
For
By interpolation 11.428 % is the rate of return to make the left side to equal to the right side.
Since the ROR is lower than 15 percent, we discard Alternative 3.
Conclusion:
The second alternative i.e. Intersection widening is selected by using the three economic methods.
Want to see more full solutions like this?
Chapter 13 Solutions
Traffic And Highway Engineering
- Determine the stiffness matrices of elements 2, 3 and 4 in the global co-ordinate system. Assume A=0.0015m2 and E=200GPa, indicate the degrees of freedom in all stiffness matricies.arrow_forwardA short plain concrete column with cross-section dimensions of 12 in x 12 in is to be constructed. If the compressive strength of the concrete (f’c) is 5000 psi, what is the maximum load that can be safely applied to the column? - 600 k - 950 k - 720 k - 347 karrow_forwardThe borrow pit has 2000 cyds of suitable fill. The fill required for the project is 1900 cyds. The swell factor is 10% and the shrinkage factor is 15%. How much more borrow do we need? Or is there extra? - 13 yards extra - 13 yards short - 200 yards extra - 161 yards shortarrow_forward
- The job site has a primary vertical control point with a reference benchmark of 100 ft. An instrument is set up with an HI of 5.42 ft above the BM. A grade stake is set at an elevation of 96 ft. What is the height reading on the rod at the grade stake? - 9.42 ft - 4.00 ft - 1.42 ft - 5.42 ftarrow_forwardAssume you have a simple beam 16 ft long supported on each end by R1 and R2. There is a concentrated load of 900 lb that is 4 ft from R2. Reaction R1 is pinned 12 ft from the load. Reaction R1 is 225 lb and R2 is 675 lb. What is the maximum bending moment in pounds per foot? - 3,600 - 1,800 - 2,700- 900arrow_forwardA wall form is four-feet high, ten-feet long and ten-feet wide. It is full of fluid concrete. What is the pressure at the bottom of the form? - 86,400 psi - 60,000 psf - 600 psf - 60,000 psiarrow_forward
- he sides of a building are 300 feet long and 200 feet wide. What is the diagonal distance between the opposite corners? - 300 feet - 306 feet - 360.60 feet - 306.6 feetarrow_forwardThe excavation for a square basement requires a 1:2 H:V slope cut back. The external dimensions of the footings are 30 x 30 feet. The excavation is 8 feet deep and you need to add 2 feet on each side to install the footing forms. What is the volume of cubic yards of excavation? - 486.7cy - 13140cy - 858.8cy - 429.4cyarrow_forwardThe Modulus of Elasticity is 30,000,000 for mild carbon steel. In the plastic state, the unit stress is 25000 psi. What is the strain? - 1.45 - 145.0 - 0.00083 - 1450.0arrow_forward
- The building is twenty-five feet by twenty five feet. The side line of the building and two corners along the line have been staked. What is the diagonal distance and the 90 degree distance to the other corners? - 35.36 feet and 35.36 feet - 25.00 feet and 35.36 feet - 35.36 feet and 25 feet - 25.00 feet and 25.00 feetarrow_forwardNEED HELP THANK YOU IN ADVACEarrow_forwardNEED HELP THANK YOU IN ADVANCEarrow_forward
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage LearningSolid Waste EngineeringCivil EngineeringISBN:9781305635203Author:Worrell, William A.Publisher:Cengage Learning,

