
Concept explainers
A jewelry firm buys semiprecious stones to make bracelets and rings. The supplier quotes a price of $8 per stone for quantities of 600 stones or more, $9 per stone for orders of 400 to 599 stones, and $10 per stone for lesser quantities. The jewelry firm operates 200 days per year. Usage rate is 25 stones per day, and ordering costs are $48.
a. If Carrying costs are $2 per year for each stone, find the order quantity that will minimize total annual cost.
b. If annual carrying costs are 30 percent of unit cost, what is the optimal order size?
c. If lead time is six working days, at what point should the company reorder?
a)

To determine: The Optimal order quantity that minimizes the total cost.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 14P
Explanation of Solution
Given information:
Number of Stones | Price per Stone (P) |
1-399 | $10 |
400-599 | $9 |
600+ | $8 |
Formula:
Calculation of Economic Order Quantity:
H=$2
The economic order quantity is calculated by dividing the product of 2 and 5,000 and 48 with 2 and taking square root which gives the resultant value as 490 stones.
Calculation of total cost:
The optimal order quantity is 600 stones which is the minimal total cost.
Hence, the optimal order quantity is 600 stones.
b)

To determine: The Optimal order size.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 14P
Explanation of Solution
Given information:
Number of Stones | Price per Stone (P) |
1-399 | $10 |
400-599 | $9 |
600+ | $8 |
Formula:
Calculation of optimum order size:
- P=$8
The economic order quantity is calculated by dividing the product of 2 and 5,000 and 48 with the product of 0.30 and 8, square root is taken which gives the resultant value as 447 stones which is not feasible.
- P=$9
The economic order quantity is calculated by dividing the product of 2 and 5,000 and 48 with the product of 0.30 and 9, square root is taken which gives the resultant value as 422 stones which is feasible.
Calculation of total cost:
The optimal order quantity is 600 stones which is the minimal total cost.
Hence, the optimal order quantity is 600 stones.
c)

To determine: The reorder point.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 14P
Explanation of Solution
Given information:
Number of Stones | Price per Stone (P) |
1-399 | $10 |
400-599 | $9 |
600+ | $8 |
Calculation of reorder point:
The reorder point is calculated by multiplying 25 stones/day with 6 days which gives 150 stones.
Hence, the reorder point is 150 stones.
Want to see more full solutions like this?
Chapter 13 Solutions
EBK OPERATIONS MANAGEMENT
- Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 60 units. The MPS rule is to schedule production if the projected on-hand Inventory would be negative without it. Customer orders (committed) are as follows: Week Customer Orders 1 2 36 28 4 1 Use a production lot size of 85 units and no beginning inventory. Note: In the ATP row, enter a value of 0 (zero) in any periods where ATP should not be calculated. Leave no cells blank - be certain to enter "0" wherever required. June July 1 2 3 4 5 8 7 8 Forecast 60 60 60 60 60 60 60 60 Customer Orders 38 28 4 1 0 0 0 0 Projected On-Hand Inventory MPS ATParrow_forwardSales of tablet computers at Marika Gonzalez's electronics store in Washington, D.C., over the past 10 weeks are shown in the table below: Week 1 2 3 4 5 6 7 8 9 10 Demand 21 21 27 38 25 30 35 24 25 30 a) The forecast for weeks 2 through 10 using exponential smoothing with a = 0.50 and a week 1 initial forecast of 21.0 are (round your responses to two decimal places): Week 1 2 3 4 5 6 7 8 9 10 Demand 21 21 27 38 25 30 35 24 25 30 Forecast 21.0 21 21 24 31 28 29 32 28 26.50 b) For the forecast developed using exponential smoothing (a = 0.50 and initial forecast 21.0), the MAD = |||||sales (round your response to two decimal places).arrow_forwardSales of tablet computers at Marika Gonzalez's electronics store in Washington, D.C., over the past 10 weeks are shown in the table below: Week Demand 1 2 3 4 5 6 7 8 9 10 21 21 27 38 25 30 35 24 25 30 a) The forecast for weeks 2 through 10 using exponential smoothing with a = 0.50 and a week 1 initial forecast of 21.0 are (round your responses to two decimal places): Week 1 2 3 4 5 Demand 21 21 27 38 Forecast 21.0 ☐ G ☐ ☐ 6 7 25 30 35 ∞ ☐ 8 9 10 24 25 30arrow_forward
- Each machine costs $3 Million. Building the room with all its attendant safety protection and other ancillary costs increases the spending by an additional $2.0 million dollars per MRI suite. Each machine can perform 2000 scans per year. Each reading of an MRI scan by a radiologist, along with other per-scan-related costs, is $500 per scan. The machine will last five years. Don’t worry about discount rates for this problem Graph the total costs over 5 years as a function of sales for 0-3000 patients annually. Hint: you may need to add a second MRI at some point. Suppose that you want to make a profit of $500 per scan at a target volume of 1000 patients per year, and you purchase only one machine. Superimpose the total revenue curve on top of the total cost curve in (1).arrow_forwardI need the answer to requirement C.arrow_forwardImagine you are Susan Kim and are faced with a difficult choice to either follow the orders she was given, or refusing to do so. Using each lens determine what the ethical response would be. Suppot your answer with materials from readings and lectures. For example, using Universalism what would the ethical response be? Do the same for all four lenses.arrow_forward
- Answer all these questions, selecting any company of your choice. Choose a specific type of food company. Select a specific product. Develop all the inputs that are part of the process. Develop the transformation process in a graphic (diagram, etc.). Develop all the outputs or finished products that are part of the process. Describe all the processes involved in one line of production in any manufacturing facility. Also describing how good management is the center of any part of a production company.arrow_forwardUsing exponential smoothing with α =0.2, forecast the demand for The initial forecast for January is 2000 tons. Calculate the capacity utilization for June, July and Discuss the implications of underutilized or over utilized capacity for Green Harvestarrow_forwardIn organizational development when results are improving but relationships are declining, what leadership style is appropriate? directing delegating supporting coachingarrow_forward
- What is the first thing a leader should do when moving through a cultural change? conduct an assessment comparing the practices to other high-performing organizations learn about the current organizational culture continue to monitor key metrics define expectationsarrow_forwardThe third change leadership strategy, Collaborate on Implementation, is designed to address what type of concerns? impact concerns personal concerns refinement concerns collaboration concernsarrow_forwardIf team members are concerned with specifics such as their tasks, contingency plans, resources, and timeline, what concerns do they have? implementation concerns impact concerns refinement concerns personal concernsarrow_forward
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingContemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage Learning


