EBK OM
EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
Question
Book Icon
Chapter 12, Problem 9PA

a

Summary Introduction

Interpretation:

Total annual parts and logistics cost for each supplier.

Concept Introduction:

The lot sizing rule consists of lot-for-lot, Fixed order quantity and Fixed period quantity. Out of all lot sizing rule, lot-for-lot rule results in least inventory because the order is planned and released according to net requirement of that particular week. A fixed order quantity is an inventory system in which a firm orders a fixed lot size i.e. the order quantity remains the same when ordered every time.

a

Expert Solution
Check Mark

Explanation of Solution

    Data Supplier A Supplier L
    Procurement cost/ unit, P$11.80$10.85
    Tariff cost/ unit,
    Tc
    $0.00$0.46
    Unit transportation cost,
    Tm
    $0.90$1.25
    Order cost/ order,
    Cο
    $155$195
    Holding cost per unit,
    Ch
    $1.45$1.10
    Lead time, L45100

The different cost components that are involved in this case are:

   Total procurement cost

   Total tariff cost

   Total transportation cost

   Annual ordering cost

   Annual inventory carrying cost

   Average annual pipeline Inventory cost

Compute these costs for all the three suppliers and select based on the least total cost of the supply chain.

The following formulae will be used:

Total procurement cost = D.P

Total tariff cost = D.Te

Total transportation cost = D.Tm

Annual ordering cost = (DQ).Cο

Annual carrying cost = (Q2).Ch

Annual pipeline inventory cost = (Dd).L.Ch

Where, D= annual demand, P= procurement cost per unit, Tc = tariff cost per unit, Tm = unit transportation cost, Cο = ordering cost per order, Ch = unit carrying cost per annum, Q = order size, d = number of days in a year, and L = lead time.

Note the computations done in the following Excel format.

    Total supply chain cost analysis
    Data Supplier A Supplier L
    Procurement cost/ unit, P$11.80$10.85
    Tariff cost/ unit,
    Tc
    $0.00$0.46
    Unit transportation cost,
    Tm
    $0.90$1.25
    Order cost/ order,
    Cο
    $155$195
    Holding cost per unit,
    Ch
    $1.45$1.10
    Lead time, L45100
    Order quantity50000100000
    Average number of orders/ year (D/Q)2010
    Annual demand, D1000000
    No. of days in a year, d340
    Average daily demand (D/d)2941
    Cost calculations
    Total procurement cost$11,800,000.00$10,850,000.00
    Total management oversight cost$0.00$460,000.00
    Total annual transportation cost$900,000.00$1,250,000.00
    Annual order cost$3,100$1,950
    Annual holding cost$36,250.00$55,000.00
    Average annual pipeline Inventory cost$191,911.76$323,529.41
    Total supply chain cost$12,931,261.76$12,940,479.41

The following is the formulated excel sheet calculations as shown below:

  EBK OM, Chapter 12, Problem 9PA

b

Summary Introduction

Interpretation:

Recommendation on order quantity

Concept Introduction:

The lot sizing rule consists of lot-for-lot, Fixed order quantity and Fixed period quantity. Out of all lot sizing rule, lot-for-lot rule results in least inventory because the order is planned and released according to net requirement of that particular week. A fixed order quantity is an inventory system in which a firm orders a fixed lot size i.e. the order quantity remains the same when ordered every time.

b

Expert Solution
Check Mark

Explanation of Solution

Based on the minimum total cost, the correct choice should be the Supplier A with Q = 50,000.

c

Summary Introduction

Interpretation:

Criteria for choosing supplier and quantity

Concept Introduction:

The lot sizing rule consists of lot-for-lot, Fixed order quantity and Fixed period quantity. Out of all lot sizing rule, lot-for-lot rule results in least inventory because the order is planned and released according to net requirement of that particular week. A fixed order quantity is an inventory system in which a firm orders a fixed lot size i.e. the order quantity remains the same when ordered every time.

c

Expert Solution
Check Mark

Explanation of Solution

Following are some of the criteria other than then total cost. The relevant metrics for measurement are also mentioned in the following table.

    CriteriaMetric
    QualitySigma level
    ReliabilityAverage service level
    CapacityPercentage utilization
    Delivery adherenceVariability in lead time

d

Summary Introduction

Interpretation:

Recommendation for supplier who is not awarded the brake pad order..

Concept Introduction:

The lot sizing rule consists of lot-for-lot, Fixed order quantity and Fixed period quantity. Out of all lot sizing rule, lot-for-lot rule results in least inventory because the order is planned and released according to net requirement of that particular week. A fixed order quantity is an inventory system in which a firm orders a fixed lot size i.e. the order quantity remains the same when ordered every time.

d

Expert Solution
Check Mark

Explanation of Solution

Supplier L should be given a target of reducing the procurement cost per unit by, say, 3%. Even with a 3% reduction of procurement cost per unit, it can compete with supplier A based on the total cost. This is shown below.

    Total supply chain cost analysis
    Data Supplier A Supplier L
    Procurement cost/ unit, P$11.80$10.85
    Tariff cost/ unit,
    Tc
    $0.00$0.46
    Unit transportation cost,
    Tm
    $0.90$1.25
    Order cost/ order,
    Cο
    $155$195
    Holding cost per unit,
    Ch
    $1.45$1.10
    Lead time, L45100
    Order quantity50000100000
    Average number of orders/ year (D/Q)2010
    Annual demand, D1000000
    No. of days in a year, d340
    Average daily demand (D/d)2941
    Cost calculations
    Total procurement cost$11,800,000.00$10,524,500.00
    Total management oversight cost$0.00$460,000.00
    Total annual transportation cost$900,000.00$1,250,000.00
    Annual order cost$3,100$1,950
    Annual holding cost$36,250.00$55,000.00
    Average annual pipeline Inventory cost$191,911.76$323,529.41
    Total supply chain cost$12,931,261.76$12,614,979.41

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Galaxy Co. sells virtual reality (VR) goggles, particularly targeting customers who like to play video games. Galaxy procures each pair of goggles for $150 from its supplier and sells each pair of goggles for $300. Monthly demand for the VR goggles is a normal random variable with a mean of 157 units and a standard deviation of 41 units. At the beginning of each month, Galaxy orders enough goggles from its supplier to bring the inventory level up to 140 goggles. If the monthly demand is less than 140, Galaxy pays $20 per pair of goggles that remains in inventory at the end of the month. If the monthly demand exceeds 140, Galaxy sells only the 140 pairs of goggles in stock. Galaxy assigns a shortage cost of $40 for each unit of demand that is unsatisfied to represent a loss-of-goodwill among its customers. Management would like to use a simulation model to analyze this situation. (Use at least 1,000 trials.) (a) What is the average monthly profit (in dollars)? (Round your answer to the…
Hospital administrators must schedule nurses so that the hospital's patients are provided adequate care. At the same time, careful attention must be paid to keeping costs down. From historical records, administrators can project the minimum number of nurses required to be on hand for various times of day and days of the week. The objective is to find the minimum total number of nurses required to provide adequate care. Nurses start work at the beginning of one of the four-hour shifts given below (except for shift 6) and work for 8 consecutive hours. Hence, possible start times are the start of shifts 1 through 5. Also, assume that the projected required number of nurses factors in time for each nurse to have a meal break. Formulate and solve the nurse scheduling problem as an integer program for one day for the data given below. (Let x = number of nurses who start work at the beginning of shift t, t = 1, 2, 3, 4, 5.) Shift Time Minimum Number of Nurses Needed 1 12:00 A.M. - 4:00 A.M.…
The Kolkmeyer Manufacturing Company uses a group of six identical machines, each of which operates an average of 23 hours between breakdowns. With randomly occurring breakdowns, the Poisson probability distribution is used to describe the machine breakdown arrival process. One person from the maintenance department provides the single-server repair service for the six machines. Management is now considering adding two machines to its manufacturing operation. This addition will bring the number of machines to eight. The president of Kolkmeyer asked for a study of the need to add a second employee to the repair operation. The service rate for each individual assigned to the repair operation is 0.40 machines per hour. (a) Compute the operating characteristics if the company retains the single-employee repair operation. (Round your answers to four decimal places. Report time in hours.) W L = q W = ✓ X h × h (b) Compute the operating characteristics if a second employee is added to the…
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Contemporary Marketing
Marketing
ISBN:9780357033777
Author:Louis E. Boone, David L. Kurtz
Publisher:Cengage Learning
Text book image
MKTG 12:STUDENT ED.-TEXT
Marketing
ISBN:9781337407595
Author:Lamb
Publisher:Cengage