Case summary: Person D wanted a custom-built recording studio in his home. He asked local contractors for bid submission. The lowest bid was of person A. They both discussed the type and quality of the material to be used. Person D asked for better quality of the material within the bid price. They also discussed the starting date for the construction work. Two weeks later, D changed his mind to carry out the plan and A filed a suit in response.
To find: The possibility of the acceptance of the offer.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Peggy had an oral contract with Bill to locate desirable real estate that she could use for rental property. Peggy stated she wanted to find condos that could be purchased for under $300,000 that could be rented for at least $2,000 per month per unit. Bill located a new condo unit that could be purchased for $260,000 and was renting for $2,200 per unit. Bill noted that the units were new and a great deal, and he bought a unit for himself. About a month later, Bill found a second property that was listed for $250,000 and rented for $2,300 per unit. Bill told Peggy about this second property and not the first property, and Peggy purchased the second property. Afterward, Peggy learned that Bill had bought the $260,000 condo without telling her about it. Peggy believes that Bill has acted improperly. Bill claims that he did what Peggy asked -- he found a property for under $300,000 that rented for $2,000 per unit. Bill argues that he did not tell Peggy about the first condo because the…
Buyer Beatrice has entered into an exclusive
buyer single agency agreement with Broker
Nate. The agreement states that the broker will
first look to the seller for payment of earned
commission via the cooperating broker
arrangement as published in the listing for the
property on the local MLS. On one hand,
Beatrice is glad that she probably won't have to
pay the broker's fee, but on the other hand,
she's worried that if Nate is being paid by the
seller, his loyalty might be with the seller.
Is Beatrice's concern warranted?
Although Nate is operating as a single agent for
Beatrice, her concerns might still be warranted
since compensation representation and
loyalty.
Beatrice does not need to worry until it is
actually determined from whom Nate's
compensation will come.
Beatrice does not need to worry because
compensation does not
equal loyalty or an agency relationship.
Beatrice's concerns are valid. If she wants Nate
to only consider her interests, she should not
allow him to receive…
ZeeHome took a new project, building a school, in a new geographical area. The company (ZeeHome) was designated as a consultant on the project with the main task of supervising the work of the contractor. To operate as a consultant, the senior engineers of ZeeHome needed to perform site inspection on a regular basis.
ZeeHome management insisted on taking on the consultancy project without making sure that they have the capacity to fulfil their obligations. In fact, during that period, ZeeHome was overloaded and had eight other important projects under process and all ZeeHome senior engineers were already assigned tasks to their full capacity. Consequently, ZeeHome could not dispatch a team of senior engineers to proceed with the inspection visits on a regular basis. Moreover, the few inspection visits that have taken were made by fresh graduated engineers who were still under training.
The school building was completed on time and the school started its educational activities. More…
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, subject and related others by exploring similar questions and additional content below.Similar questions
- Ezekial Property Management enters into a contract with a homeowner to manage a rental property. The contract states that Ezekial will find and sign a tenant to a lease, and then after the lease is signed, Ezekial will manage the property. How many performance obligations are there in the contract? O One O Two Three O Cannot determine + SUBMITarrow_forwardOn January 1, 2021, Crane, Inc. signs a 10-year noncancelable lease agreement to lease a storage building from Holt Warehouse Company. Collectibility of lease payments is reasonably predictable and no important uncertainties surround the amount of costs yet to be incurred by the lessor. The following information pertains to this lease agreement.(a) The agreement requires equal rental payments at the beginning each year.(b) The fair value of the building on January 1, 2021 is $6550000; however, the book value to Holt is $5500000.(c) The building has an estimated economic life of 10 years, with no residual value. Crane depreciates similar buildings using the straight-line method.(d) At the termination of the lease, the title to the building will be transferred to the lessee.(e) Crane’s incremental borrowing rate is 11% per year. Holt Warehouse Co. set the annual rental to insure a 10% rate of return. The implicit rate of the lessor is known by Crane, Inc.(f) The yearly rental payment…arrow_forwardFrom the information provided state which form of contract (simple or formal) is required for the following cases: a) A court judgement to perform a community service order b) An agreement to build a pool worth $45,000 c) A promise to make a gift of $50,000 d) An agreement to build a house in 18 months’ time e) A hire purchase agreement for household furniturearrow_forward
- Osbom Operator is trying to decide whether he can consider Brooks to be an independent contractor. Osborn pays Brooks a salary but also frequent, large commissions, and the two have for 15 years had a continuing work relationship. In fact, Brooks has been working for Osborn so long that Osborn has allotted him many freedoms, including the ability to determine where, when, and how he wants to work. Even though Brooks performs the same work that is done by the employees in Osborn's business, all of whom work at the business location, Brooks almost never comes to Osborn's business workplace; instead, Brooks works at home in his pajamas without the supervision of Osborn. As long as Brooks completes the work on time, Osborn has no qualms. However, Osborn does require Brooks to do all of his work using the laptop provided to him by the company. Given this information, which characteristic concerning independent contractors and employees is most likely to give Osborn the most trouble in terms…arrow_forwardBUSINESS LAW BUSS2422 Akram posted the offer letter on 2 October 2020 to Salam to sell his Honda City for RM50 000 to be accepted by 10 October 2020. On 4 October 2020 Akram posted another letter to revoke his proposal. The revocation letter reached Salam on 9 October 2020. On 8 October 2020, Salam posted his acceptance letter accepting the proposal. Based on the facts above: (a) Advise Salam as to his legal rights against Akram in relation to the agreement. (b) Explain if your answer would be different if Salam posted the letter of acceptance after the letter of revocation reached him. Support your answer with relevant statutory provisions of the Contracts Act 1950 and decided cases. Format: Times New Roman 12 1% spacing Front cover - Standard Format Number of pages - Minimum 3 pages, maximum 5 pagesarrow_forwardThe Acme Electric Company worked day and night to develop a new current regulator designed to cut the electric power consumption in aluminum plants by 35%. They knew that, although the competition was fierce, their regulator could be produced more cheaply, was more reliable, and worked more efficiently than the competitors’ products. The owner, eager to capture the market, personally but somewhat hastily put together a 120-page proposal to the three major aluminum manufacturers, recommending that their regulators be installed at all company plants. She devoted the first 87 pages of the proposal to the mathematical theory and engineering design behind his new regulator, and the next 32 to descriptions of the new assembly line she planned to set up to produce regulators quickly. Buried in an appendix were the test results that compared her regulator’s performance with present models, and a poorly drawn graph showed how much the dollar savings would be. Acme Electric didn’t get the…arrow_forward
- Mike's Landscaping Inc. enters into an oral contract with the Padres to keep the infield in top condition for the next five years. Six months into the contract the Padres fire Mike. What will happen in a breach of contract suit filed by Mike? Mike will lose because the contract was not in writing Mike will win because he was never late and his work was first rate. O The Padres will lose Mike will win and be awarded the profit he would have made had the contract been performed.arrow_forwardContractor XYX and the Province of Tawi-Tawi, as Project Owner, had a construction dispute. Pedro was Claiming for the return of Retention Money equivalent to P5,000,000.00 inclusive of Arbitration Fees, Attorney’s Fees and Moral Damages. The project owner made a Counterclaim in the total amount of P7,000,000.00 representing damages for defective works, damages for delay (Liquidated Damages) as well as Moral Damages, Exemplary Damages, Arbitration Fees and Attorney’s Fees. XYZ filed the Case before the CIAC on August 17, 2021. After 115 Days, or today December 10, 2021, the Construction Arbitral Tribunal ruled that the Contractor is entitled to a Total of P3,000,000.00. The Award is with interest until the Award is paid. a. In the imposition of interest, what do you think was the rate of interest AND what will the reckoning date of interest: From the Date of filing of the case or From the Date of Tribunal Award? Briefly state your reason. If the Government did…arrow_forwardProvide reaction on discussion below if you agree or disgaree: Whether the limitation of liability in ADT's service contract with Melodee Lane Lingerie Co. is valid would depend on the specific terms and enforceability of that contract. Contractual limitations of liability are generally upheld if they meet certain legal criteria. However, the enforceability of such limitations can vary based on jurisdiction and the nature of the contract. Here are some factors to consider. Clear and Unambiguous Terms: For a limitation of liability clause to be valid, it should be clear and unambiguous in its language. It should not be buried in fine print or hidden within the contract. Bargaining Power: Courts may scrutinize such clauses more closely if there is a significant disparity in bargaining power between the parties. If one party had little or no opportunity to negotiate the terms, it may be viewed less favorably. Public Policy: Courts may refuse to enforce limitations on…arrow_forward
- Prepare a case analysis with 2000-3000 words for the following: A contract forms when one person makes an offer, and another person accepts it by communicating their assent or performing the offer's terms. If the terms are certain, and the parties can be presumed from their behavior to have intended that the terms are binding, generally the agreement is enforceable. While agreement is the basis for all contracts, not all agreements are enforceable. A preliminary question is whether the contract is reasonably certain in its essential terms, such as price, subject matter and the identity of the parties. Requirements 1- An introduction and a conclusion. 2- A critical discussion on the concept of what is an offer, inclusive of the various requirements of an effective and valid offer, with…arrow_forwardTyree and Stella enter into a contract requiring Tyree to pay Stella $500 per month on the first of every month as rent for her storage space. Which of the following examples constitutes a material breach? a. Tyree pays Stella on the second of the month. b. Tyree pays Stella $200 on the first of the month and then $300 the next morning. c. Tyree pays Stella $490. d. Tyree pays Stella $200 at the end of the month.arrow_forward1.A performance bond submitted by a general contractor to an owner guarantees that the owner will perform according to the conditions of the contract. True False 2.A general contractor requires a subcontractor to submit a payment bond to the general contractor on the project. Which of the following is the obligee in this situation? Owner Architect Subcontractor General Contractorarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- BUSN 11 Introduction to Business Student EditionBusinessISBN:9781337407137Author:KellyPublisher:Cengage LearningEssentials of Business Communication (MindTap Cou...BusinessISBN:9781337386494Author:Mary Ellen Guffey, Dana LoewyPublisher:Cengage LearningAccounting Information Systems (14th Edition)BusinessISBN:9780134474021Author:Marshall B. Romney, Paul J. SteinbartPublisher:PEARSON
- International Business: Competing in the Global M...BusinessISBN:9781259929441Author:Charles W. L. Hill Dr, G. Tomas M. HultPublisher:McGraw-Hill Education
BUSN 11 Introduction to Business Student Edition
Business
ISBN:9781337407137
Author:Kelly
Publisher:Cengage Learning
Essentials of Business Communication (MindTap Cou...
Business
ISBN:9781337386494
Author:Mary Ellen Guffey, Dana Loewy
Publisher:Cengage Learning
Accounting Information Systems (14th Edition)
Business
ISBN:9780134474021
Author:Marshall B. Romney, Paul J. Steinbart
Publisher:PEARSON
International Business: Competing in the Global M...
Business
ISBN:9781259929441
Author:Charles W. L. Hill Dr, G. Tomas M. Hult
Publisher:McGraw-Hill Education