Question
Chapter 12, Problem 2P
To determine
Select the alternative.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
There are four estimates made for the anticipated cycle time to produce a subcomponent. The estimates, in seconds, are 10, 20, 30, and 70. If the first two estimates have equal weights, which total 70%, and the last two are weighted equally with the remaining 30%, what is the expected time?
The management of Brinkley Corporation is interested in using simulation to estimate the profit per unit for a new product. The selling price for the product will be $45 per unit. Probability distributions for the purchase cost, the labor cost, and the transportation cost
are estimated as follows:
Procurement
Cost($)
10
$
11
12
Probability
0.25
0.45
0.30
Labor
Cost ($)
20
22
24
25
Probability
0.10
0.25
0.35
0.30
Transportation
Cost ($)
3
5
(a) Compute profit per unit for the base-case, worst-case, and best-case scenarios.
Base Case using most likely costs
Profit = $
/unit
Worst Case
Profit = $
/unit
Best Case
Profit = $
/unit
Probability
0.75
0.25
(b) Construct a simulation model to estimate the mean profit per unit. (Use at least 1,000 trials.)
(c) Why is the simulation approach to risk analysis preferable to generating a variety of what-if scenarios?
Simulation will provide ---Select---
of the profit per unit values which can then be used to find ---Select--- ◆ of an unacceptably low…
Last year, 18,00018,000 people died from a newly discovered disease. Pollution is one of the contributing factors. However, even if the level of pollution is reduced, it is estimated that about 5,5005,500 people will die annually from the disease. The estimated cost of a pollution-reduction project is $33.75$33.75 billion; before investing, the government wants to verify the project's value.Calculate the average cost of a life saved. Enter your answer in U.S. dollars in the box below and round to the nearest whole number if necessary.
Chapter 12 Solutions
Engineering Economy, Student Value Edition (17th Edition)
Ch. 12 - Prob. 1PCh. 12 - Prob. 2PCh. 12 - A new snow making machine utilizes technology that...Ch. 12 - Prob. 4PCh. 12 - Prob. 5PCh. 12 - Prob. 6PCh. 12 - Prob. 7PCh. 12 - Prob. 8PCh. 12 - Prob. 9PCh. 12 - Prob. 10P
Ch. 12 - Prob. 11PCh. 12 - Prob. 12PCh. 12 - Prob. 13PCh. 12 - Prob. 14PCh. 12 - Prob. 15PCh. 12 - Prob. 16PCh. 12 - Prob. 17PCh. 12 - Prob. 18PCh. 12 - Prob. 19PCh. 12 - Prob. 20PCh. 12 - Prob. 21PCh. 12 - Prob. 22PCh. 12 - If the interest rate is 8% per year, what decision...Ch. 12 - Prob. 24PCh. 12 - Prob. 25PCh. 12 - Prob. 26SE
Knowledge Booster
Similar questions
- Hudson Corporation is considering three options for managing its data warehouse: continuing with its own staff, hiring an outside vendor to do the managing, or using a combination of its own staff and an outside vendor. The cost of the operation depends on future demand. The annual cost of each option (in thousands of dollars) depends on demand as follows: a. If the demand probabilities are 0.2, 0.5, and 0.3, which decision alternative will minimize the expected cost of the data warehouse? What is the expected annual cost associated with that recommendation? b. Construct a risk profile for the optimal decision in part (a). What is the probability of the cost exceeding $700,000?arrow_forwardOnly typed answerarrow_forwardFethe's Funny Hats is considering selling trademarked, orange-haired curly wigs for University of Tennessee football games. The purchase cost for a 2-year franchise to sell the wigs is $20,000. If demand is good (40% probability), then the net cash flows will be $27,000 per year for 2 years. If demand is bad (60% probability), then the net cash flows will be $9,000 per year for 2 years. Fethe's cost of capital is 14%. A. What is the expected NPV of the project? B. Use decision-tree analysis to calculate the expected NPV of this project, including the option to continue for an additional 2 years. B. Use decision-tree analysis to calculate the expected NPV of this project, including the option to continue for an additional 2 years.arrow_forward
- Consolidated Edison Power is evaluating the construction of a new electric generation facility. The two choices are a coal-burning plant (CB) and a gaseous diffusion (GD) plant. The CB plant will cost $160 per megawatt to construct, and the GD plant will cost $180 per megawatt. Owing to uncertainties concerning fuel availability and the impact of future regulations related to air and water quality, the useful life of each plant is unknown, but the following probability estimates have been made .a. Determine the expected life of each plant. b. Based on the ratio of construction cost per megawatt to expected life, which plant would you recommend that Con Ed build?arrow_forwardFrom the decision tree branch shown, determine the expected values of the two outcomes if decision D3 is already selected and the maximum outcome value is sought. (This decision branch is part of a larger tree.) Probability 0.4 03 0.3 0.3 0.6 When the probability is 0.4, the value is $60. When the probability is 0.3, the value is $-27. When the probability is 0.3, the value is $20. When the probability is 0.6, the value is $-11. When the probability is 0.4, the value is $6.2. 0.4 The expected value of the the top node is $ The expected value of the bottom node is $[arrow_forwardThe owner of a ski resort is considering installing a new ski lift that will cost $850,000. Expenses for operating and maintaining the lift are estimated to be $2,000 per day when operating. The U.S.Weather Service estimates that there is a 55% probability of 90 days of skiing weather per year, a 30% probability of 100 days per year, and a 15% probability of 120 days per year. The operators of the resort estimate that during the first 90 days of adequate snow in a season, an average of 550 people will use the lift each day, at a fee of $10 each. If 10 additional days are available, the lift will be used by only 450 people per day during the extra period; and if 20 more days of skiing are available, only 250 people per day will use the lift during those days. The study period is eight years; the ski lift will be depreciated by using the MACRS Alternative Depreciation System (ADS); the ADS recovery period is seven years; MARR = 10% per year (after-tax); and the effective income tax rate…arrow_forward
- Suzy's Temporary Employee (STE) business, located in a big city, can do an online criminal background check in-house for $3.38 per search with a fixed cost of $28,000. A third-party online security firm offered to do a similar security search for $9.50 per person with an annual service contract with STE. If STE's forecast is 2,700 searches next year, should STE continue to do the search in-house or accept the third-party offer? Use the Excel template Break-Even to determine the best decision. Round your answer for the breakeven quantity to the nearest whole number and round your answer for the amount of saving/loss to the nearest dollar. Breakeven quantity: searches Since the demand forecast of 2,700 searches is than the breakeven quantity, STE outsource the work. STE $ by outsourcing.arrow_forwardFive years ago a dam was constructed to impound irrigation water and to provide flood protection for the area below the dam. Last winter a 100-year flood caused extensive damage both to the dam and to the surrounding area. This was not surprising, since the dam was designed for a 50-year flood. The cost to repair the dam now will be $250,000. Damage in the valley below amounts to $750,000. If the spillway is redesigned at a cost of $250,000 and the dam is repaired for another $250,000, the dam may be expected to withstand a 100-year flood without sustaining damage. However, the storage capacity of the dam will not be increased and the probability of damage to the surrounding area below the dam will be unchanged. A second dam can be constructed up the river from the existing dam for $1 million. The capacity of the second dam would be more than adequate to provide the desired flood protection. If the second dam is built, redesign of the existing dam spillway will not be necessary, but…arrow_forwardData in the matrix below indicates COST expected from 3 alternatives under 4 states of nature. Determine which alternative is dominant using With and Without Probability (use a = 0.3 and probability of: 30%; 20%; 40% & 10% for S1, S2, S3, and 54 respectively): Which alternative is best using Expected Value? Alternatives S1 53 S4 A1 10 18 15 A2 12 25 20 A3 15 19 25 S2 20 15 18arrow_forward
- Assume a pool of 115 people in an insurance pool (a group of people insured through community rating). It is estimated that a small number in the pool will have significant pre- existing conditions as indicated in the table. Based on the age of these 115 people, the insurance company estimates the following distribution of health care claims (which includes necessary profit and administrative costs of the insurance company). Number of Insured Antidipated Heath Costs/Year/Person $1,400 $1,500 $1,600 $1,700 $1,800 $1,900 $2,000 $2,100 $2,200 $2.300 $2,400 $2,500 $2,700 $2,000 $2,900 $3,000 $3,100 $3.200 $3.300 $4,000 57,00 $10,000 Everyone joins the poal ad pays the necessary premum in the first year. The clams experience of the customers is faund to be generaly consstent with expeclations of the insurance company. A) What would be the premium In the third year if there is no inflation, based on the company's oxperience from the past year? B) If those customers who have anticipated…arrow_forwardAn electric utility is taking bids for the purchase, installation, and operation of decentralized battery storage systems. The table below has some details for the two bids received. a) Which is the most economical bid if the rate is 11%. None of the batteries are expected to have a salvage value after 30 years of use. (Actual expected service life is listed in the bid) b) Also solve using NPW method to compare these two mutually exclusive plans Equipment cost Installation cost Annual Inspection and Maintenance fee Annual extra income taxes Life Salvage Value Bid A $112,000 $25,000 $2,000 0 40 years 0 Bid B $98,000 $30,000 $2,000 $800 35 years 0arrow_forwardA young couple planning ahead for their retirement has decided that $3 million is the amount they will need in order to retire comfortably 20 years from now. For the past 5 years, they have been able to invest one of their salaries ($50,000 per year, which includes employer contributions) while living off the other salary. They plan to start a family sometime in the next 10 years and when they will have their first child, one of the parents will quit working, causing the savings to decrease to $10,000 per year thereafter. If they have realized an average ROR of 10% per year on their investments, and expect to continue at this ROR, is reaching their goal of $3 million in 20 years sensitive to when they have their first child (i.e., between now and 10 years from now)? If so, how many years from now will they have to wait before they have their first child? Use a future worth analysis.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education