Concept explainers
Keller Construction is considering two new investments. Project E calls for the purchase of earthmoving equipment. Project H represents an investment in a hydraulic lift. Keller wishes to use a
a. Determine the net present value of the projects based on a zero percent discount rate.
b. Determine the net present value of the projects based on a 9 percent discount rate.
c. The
d. If the two projects are not mutually exclusive, what would your acceptance or rejection decision be if the cost of capital (discount rate) is 8 percent? (Use the net present value profile for your decision; no actual numbers are necessary.)
e. If the two projects are mutually exclusive (the selection of one precludes the selection of the other), what would be your decision if the cost of capital is (1) 6 percent, (2) 13 percent, (3) 18 percent? Once again, use the net present value profile for your answer.
a.
To calculate: The NPV of the projects by using zero discount rate for Keller Construction Company.
Introduction:
Net present value (NPV):
It is the difference between the PV (present value) of cash inflows and the PV of cash outflows. It is used in capital budgeting and planning of investment to assess the benefits and losses of any project or investment.
Answer to Problem 23P
The NPV of the project E is $8,000 and project H is $5,000 based on zero discount rate for Keller Construction Company.
Explanation of Solution
The calculation of NPV of project E:
The calculation of NPV of project H:
Working Notes:
The calculation of inflows for project E:
The calculation of inflows for project H:
b.
To calculate: The NPV of the projects by using 9% discount rate for Keller Construction Company.
Introduction:
Net present value (NPV):
It is the difference between the PV (present value) of cash inflows and the PV of cash outflows. It is used in capital budgeting and planning of investment to assess the benefits and losses of any project or investment.
Present value (PV):
The current value of an investment or an asset is termed as its present value. It is calculated by discounting the future value of the investment or asset.
Answer to Problem 23P
The calculation of PV of inflows for Project E at 9%:
The calculation of PV of inflows for Project H at 9%:
Thus, the NPV of project E is $2,127 and project H is $1,976.
Explanation of Solution
The calculation of NPV of project E:
The calculation of NPV of project H:
The formulae used for the calculation of PV of inflows for Project E:
The formulae used for the calculation of PV of inflows for Project E:
c.
To plot: The graph for the NPV of the project according to the Fig. 12-3 for the Keller Construction Company.
Introduction:
Internal rate of return (IRR):
A method of capital budgeting that is used to measure the profitability of potential projects or investments. It is a discount that makes the NPV equals to zero for a specific project.
Answer to Problem 23P
The graph for the NPV of the project according to the Fig. 12-3 for the Keller Construction Company:
Explanation of Solution
Calculation of IRR:
Working Note:
The formulae used in the calculation of IRR:
d.
To determine: The decision regarding the acceptance or the rejection of the projects, if the projects are mutually exclusive and discount rate of the cost of capital is 8% for the Keller Construction Company.
Introduction:
Net present value (NPV):
It is the difference between the PV (present value) of cash inflows and the PV of cash outflows. It is used in capital budgeting and planning of investment to assess the benefits and losses of any project or investment.
Present value (PV):
The current value of an investment or an asset is termed as its present value. It is calculated by discounting the future value of the investment or asset.
Answer to Problem 23P
The calculation of PV of project E and project H at 8%:
The NPV of project E is $2,681 and project H is $2,277. Thus, the NPV of project E is higher than the project H. Therefore, project E must be accepted as it is more profitable than the project H.
Explanation of Solution
The calculation of NPV of project E:
The calculation of NPV of project H:
The formulae used in the calculation of PV of project E and H at 8% are shown below:
e.
To determine: The decision regarding the acceptance or rejection of the projects, if the projects are mutually exclusive and discount rates of cost of capital are 6%, 13%, and 18% for the Keller Construction Company.
Introduction:
Net present value (NPV):
It is the difference between the PV (present value) of cash inflows and the PV of cash outflows. It is used in capital budgeting and planning of investment to assess the benefits and losses of any project or investment.
Present value (PV):
The current value of an investment or an asset is termed as its present value. It is calculated by discounting the future value of the investment or asset.
Answer to Problem 23P
The calculation of PV of project E and project H at 6%:
The NPV of project E is $3,855 and project H is $2,903. Thus, the NPV of project E is higher than the project H, So, project E must be accepted at 6% discount rate as it is superior to the project H.
The calculation of PV of project E and project H at 13%:
The NPV of project E is $108 and project H is $847. Thus, the NPV of project H is higher than the project E, So, project H must be accepted at 13% discount rate as it is superior to the project E.
The calculation of PV of project E and project H at 18%:
The NPV of project E is ($2,035) and project H is ($415). Thus, both projects must be rejected at 18% discount rate as NPV of both projects are negative.
Explanation of Solution
The calculation of NPV of project E at 6%:
The calculation of NPV of project H at 6%:
The calculation of NPV of project E at 13%:
The calculation of NPV of project H at 13%:
The calculation of NPV of project E at 18%:
The calculation of NPV of project H at 18%:
The formulae used in the calculation of PV of project E and H at 6% are shown below:
The formulae used in the calculation of PV of project E and H at 13% are shown below:
The formulae used in the calculation of PV of project E and H at 18% are shown below:
Want to see more full solutions like this?
Chapter 12 Solutions
EBK FOUNDATIONS OF FINANCIAL MANAGEMENT
- A firm needs to raise $950,000 but will incur flotation costs of 5%. How much will it pay in flotation costs? Multiple choice question. $55,500 $50,000 $47,500 $55,000arrow_forwardWhile determining the appropriate discount rate, if a firm uses a weighted average cost of capital that is unique to a particular project, it is using the Blank______. Multiple choice question. pure play approach economic value added method subjective approach security market line approacharrow_forwardWhen a company's interest payment Blank______, the company's tax bill Blank______. Multiple choice question. stays the same; increases decreases; decreases increases; decreases increases; increasesarrow_forward
- For the calculation of equity weights, the Blank______ value is used. Multiple choice question. historical average book marketarrow_forwardA firm needs to raise $950,000 but will incur flotation costs of 5%. How much will it pay in flotation costs? Multiple choice question. $50,000 $55,000 $55,500 $47,500arrow_forwardQuestion Mode Multiple Choice Question The issuance costs of new securities are referred to as Blank______ costs. Multiple choice question. exorbitant flotation sunk reparationarrow_forward
- What will happen to a company's tax bill if interest expense is deducted? Multiple choice question. The company's tax bill will increase. The company's tax bill will decrease. The company's tax bill will not be affected. The company's tax bill for the next year will be affected.arrow_forwardThe total market value of a firm is calculated as Blank______. Multiple choice question. the number of shares times the average price the number of shares times the future price the number of shares times the share price the number of shares times the issue pricearrow_forwardAccording the to the Blank______ approach for project evaluation, all proposed projects are placed into several risk categories. Multiple choice question. pure play divisional WACC subjectivearrow_forward
- To invest in a project, a company needs $50 million. Given its flotation costs of 7%, how much does the company need to raise? Multiple choice question. $53.76 million $46.50 million $50.00 million $53.50 millionarrow_forwardWhile determining the appropriate discount rate, if a firm uses a weighted average cost of capital that is unique to a particular project, it is using the Blank______. Multiple choice question. economic value added method pure play approach subjective approach security market line approacharrow_forwardWhat are flotation costs? Multiple choice question. They are the costs incurred to issue new securities in the market. They are the costs incurred to insure the payment due to bondholders. They are the costs incurred to meet day to day expenses. They are the costs incurred to keep a project in the business.arrow_forward
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubIntermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage Learning