Concept explainers
The trip distribution using the average growth factor method.
Answer to Problem 14P
The trip distribution has been developed using the average growth factor method.
Explanation of Solution
Given:
For Zone
Present total observed trip ends is
Zonal growth rate is
For Zone
Present total observed trip ends is
Zonal growth rate is
For Zone
Present total observed trip ends is
Zonal growth rate is
For Zone
Present total observed trip ends is
Zonal growth rate is
Formula used:
Estimated growth total is given by,
The number of trips estimated from zone
Here,
The new growth factor is given as,
Calculation:
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The data of
Zones | |||
Table (1)
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The calculated trips from zone
Zones | |
Table (2)
The
The
Substitute
The
The
Substitute
The
The
Substitute
The
The
Substitute
The remaining movement between zones, new present total and new growth factor for zone s
Zones | New Present total | New Growth factor |
Table (3)
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The data of
Zones | |||
Table (4)
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The calculated trips from zone
Zones | |
Table (5)
The
The
Substitute
The
The
Substitute
The
The
Substitute
The
The
Substitute
The remaining movement between zones, new present total and new growth factor for zone
Zones | New Present total | New Growth factor |
| ||
Table (6)
Conclusion:
The trip distribution has been done using the average growth factor method.
Want to see more full solutions like this?
Chapter 12 Solutions
Traffic and Highway Engineering
- Develop a LOB schedule for 20 houses. The target output rate for this project is 3 houses per week. A typical working week includes five 8-hour days. The construction of a single house consists of the following five sequential activities:arrow_forwardGiven the list of construction activities for your newly-acquired residential project. Determine the critical path for this project. Activity Depends on Duration (weeks) D A 5 B A 3 G E 3 4 E В. С 2 G. H, I 2 A 4 F C. D 5 E. F A none The critical path for this project is Note: Use this format in your final answer/s, such as if your answer is S, T, U, V, W, then type your final answer as S-T-U-V-Warrow_forwardWhat is the probability of completion of the project in 17.5 months? * Actv. Duration (month) a m 5-10 4 5-15 4 10-20 4 4 7 10-25 10-30 4 5 6. 15-25 3.5 5.5 7.5 15-30 3 20-35 9 12 25-35 5 8. 30-35arrow_forward
- A particular project is scheduled to complete in Week 50 at a budgeted cost of $150,000. As of Week 30, an earned value chart is prepared to present the project progress as below: Status Date 160- 140 PV 120 100 80 AC 60 40- 20 10 15 20 25 30 35 40 45 50 Weeks 1. Calculate schedule, cost and time variances, as well as schedule and cost performance indices for Week 30. Then use this information to comment on the project progress at Week 30 (status date). 2. Based on the performance at Week 30, estimate the final project cost (EAC). Will the final project cost be higher or lower than the budgeted cost, and by how much? Also estimate the revised project completion date. Will the project complete sooner or later than the planned completion date, and by how many weeks? 000.Sarrow_forwardDraw the node diagram and perform the CPM computations for the schedule shown. Tabulate ES, EF, LS, LF, TT, and LF. Identify the critical path and the total duration of the project. Activity Duration IPA Lag ES EF LS LF TF FF A B A 4 A 3 D A E B F 7 В G 6 H 8 D 4 3 7 E, G F 2 K 4 F, G, H L 1 H 3 M K, L 2.arrow_forwardQUESTION 6. The activities involved in the construction of a new shopping mall are given in Table Q6. One resource type will be used during the contract. Determine minimum level of the resource required to complete the project. Table Q6 Activity Duration Predecessors Resource (units/week) (Weeks) A B 2 2 2 1 2 3 1 5 3 1 E 2 6. 2 F G 3 H 6. 4 4 4 5, 6 6, 7 2, 8 2, 8, 9 10, 11, 12, 13 4 2 K 2 L. 2.arrow_forward
- The activity details of a project are given below: Activity Depends P Q R S T U V A 68 B The estimated minimum time (in days) for the completion of the project will be 51 C 85 on D 40 P Q,T R P Q,T U Duration (in days) 6 15 12 16 10 14 16arrow_forward10. Assume that the duration of some activities is not known with certainty. The estimates of these activities are shown below. Activity A C D G H Optimistic Q 8 3 10 13 8 Most Likely 10 5 12 15 10 POM a. What is the project's expected completion time and its variance? b. What is the probability that the project will be completed in 61 days or more? c. What is the probability that the project will be completed in no more than 54 days? c. If the company wants a 94% probability of completing the project on time, state the latest time each activity should have started and completed. Pessimistic 5+ 12 7 14 17 12arrow_forward1- A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the three indexes.($000)arrow_forward
- B. Find the weighted unit cost per square meter for the project data shown and determine the cost of a 2700-m2 project. Project No. Total cost (LE) Size, m? 147,300 153,700 128,100 118,400 135,700 2580 2900 2100 1 2 3 4 1850 5 2300 C. Determine the relationship between unit cost and size for the project data shown in Problem 2 to estimate the cost of a2200-m2 project.arrow_forwardQA: for the information shown in table below, find the probability of finishing the project in 20 weeks? Activities 1-2 1-3 3-4 2-5 3-6 4-5 5-6 6-7 Optimistic time 2 4 6 1 1 Most likely time 3 2 4 5 8 2 2 5 Pessimistic time 4 3 6 12 16 3 3 13arrow_forwardB. Given Table Construction Economic Trends 5 years ago 4 years ago 3 years ago 2 years ago 1 year ago Current Year 438 415 368 369 333 378 Location Cost Indices City A City B City C City D 1.033 1.125 1.278 1.345 Suppose that the construction cost of a project completed at city C is LE3,357,890, it is required to prepare a conceptual estimate for a similar project proposed in city A. (arrow_forward
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning