Question
Book Icon
Chapter 11.S, Problem 5P

a)

Summary Introduction

To determine: The probability that all three suppliers are disrupted using option 1.

Introduction: Supply chain management is one of the important elements of a business which impacts business product development. With expanding businesses in global conditions, supply chain activities can impact the cost effectiveness of these businesses.

a)

Expert Solution
Check Mark

Answer to Problem 5P

The probability that three suppliers are disrupted using option 1 is 0.025062.

Explanation of Solution

Given information:

Option 1

Probabilityofsuper-event,S=2.5%=0.025Probabilityofunique-event,U=4%=0.04Purchasing & Transportation cost=$1,000,000Disruption loss=$500,000

Option 2

Probabilityofsuper-event,S=0.4%=0.004Probabilityofunique-event,U=20%=0.20Purchasing & Transportation cost=$1,010,000Disruption loss=$500,000

Formula:

P(n)=S+(1-S)Un

Probability calculation when both suppliers are disrupted by option 1:

P(n)=S+(1-S)UnP(3)=0.025+(1-0.025)0.043=0.025+(0.975×0.000064)=0.025062 Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 11.S, Problem 5P , additional homework tip  1

To find the probability of selection, one supplier substitutes the number of chosen suppliers, and the probability of super-event and unique-event in the above formula. Here, the number of suppliers chosen is ‘3’, S=0.025 and U=0.04, and is substituted in the above formula which gives probability as 0.025062.

Hence, the probability that two suppliers are disrupted using option 1 is 0.025062.

b)

Summary Introduction

To determine: The probability that all three suppliers are disrupted using option 2.

b)

Expert Solution
Check Mark

Answer to Problem 5P

The probability that three suppliers are disrupted using option 1 is 0.011968.

Explanation of Solution

Given information:

Option 1

Probabilityofsuper-event,S=2.5%=0.025Probabilityofunique-event,U=4%=0.04Purchasing & Transportation cost=$1,000,000Disruption loss=$500,000

Option 2

Probabilityofsuper-event,S=0.4%=0.004Probabilityofunique-event,U=20%=0.20Purchasing & Transportation cost=$1,010,000Disruption loss=$500,000

Formula:

P(n)=S+(1-S)Un

Probability calculation when both suppliers are disrupted by option 2:

P(n)=S+(1-S)UnP(3)=0.004+(1-0.004)0.203=0.004+(0.996×0.008)=0.011968 Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+), Chapter 11.S, Problem 5P , additional homework tip  2

To find the probability of selection, one supplier substitutes the number of chosen suppliers, anf the probability of super-event and unique-event in the above formula. Here, the number of suppliers chosen is ‘3’, S=0.004 and U=0.20, and is substituted in the above formula which gives probability as 0.011968.

Hence, the probability that two suppliers are disrupted using option 1 is 0.011968.

c)

Summary Introduction

To determine: The total annual expected cost for option 1.

c)

Expert Solution
Check Mark

Answer to Problem 5P

The total expected cost for option 1 is $1,012,531.

Explanation of Solution

Given information:

Option 1

Probabilityofsuper-event,S=2.5%=0.025Probabilityofunique-event,U=4%=0.04Purchasing & Transportation cost=$1,000,000Disruption loss=$500,000

Option 2

Probabilityofsuper-event,S=0.4%=0.004Probabilityofunique-event,U=20%=0.20Purchasing & Transportation cost=$1,010,000Disruption loss=$500,000

Formula:

Total expected cost=Annualpurchasingcost+Expecteddisruptioncost

Calculation of total expected cost:

Total expected cost=Annualpurchasingcost+Expecteddisruptioncost=$1,000,000+($500,000×0.025062)=$1,012,531 (1)

The total expected cost is calculated by taking the summation of the annual purchasing cost and expected disruption cost. The product of $500,000 and 0.025062 is added with $1,000,000, which gives $1,012,531 as the total expected cost for option 1.

Hence, the total expected cost using option 1 is $1,012,531.

d)

Summary Introduction

To determine: The total annual expected cost for option 2.

d)

Expert Solution
Check Mark

Answer to Problem 5P

The total expected cost for option 2 is $1,015,984.

Explanation of Solution

Given information:

Option 1

Probabilityofsuper-event,S=2.5%=0.025Probabilityofunique-event,U=4%=0.04Purchasing & Transportation cost=$1,000,000Disruption loss=$500,000

Option 2

Probabilityofsuper-event,S=0.4%=0.004Probabilityofunique-event,U=20%=0.20Purchasing & Transportation cost=$1,010,000Disruption loss=$500,000

Formula:

Total expected cost=Annualpurchasingcost+Expecteddisruptioncost

Calculation of total expected cost:

Total expected cost=Annualpurchasingcost+Expecteddisruptioncost=$1,010,000+($500,000×0.11968)=$1,015,984 (2)

The total expected cost is calculated by taking the summation of the annual purchasing cost and expected disruption cost. The product of $500,000 and 0.11968 is added with $1,010,000 which gives $1,015,984 as the total expected cost for option 2.

Hence, the total expected cost using option 2 is $1,015,984.

e)

Summary Introduction

To determine: The best options.

e)

Expert Solution
Check Mark

Answer to Problem 5P

Option 1 is best.

Explanation of Solution

Given information:

Option 1

Probabilityofsuper-event,S=2.5%=0.025Probabilityofunique-event,U=4%=0.04Purchasing & Transportation cost=$1,000,000Disruption loss=$500,000

Option 2

Probabilityofsuper-event,S=0.4%=0.004Probabilityofunique-event,U=20%=0.20Purchasing & Transportation cost=$1,010,000Disruption loss=$500,000

On comparing equations (1) and (2), it can be inferred that option 1 has the least expected cost. Therefore, it is advisable for Company BJ to choose option 1.

Hence, Option 1 is best.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Please show all units, work, and steps needed to solve this problem I need answer typing clear urjent no chatgpt used pls i will give 5 Upvotes.
IM.82 A distributor of industrial equipment purchases specialized compressors for use in air conditioners. The regular price is $50, however, the manufacturer of this compressor offers quantity discounts per the following discount schedule: Option Plan Quantity Discount A 1 - 299 0% B 300 - 1,199 0.50% C 1,200+ 1.50% The distributor pays $56 each time it places an order with the manufacturer. Holding costs are negligible (none) but they do earn 10% annual interest on all cash balances (meaning there will be a financial opportunity cost when they put cash into inventory). Annual demand is expected to be 10,750 units. When there is no quantity discount (Option Plan A, the first row of the schedule listed above), what is the adjusted order quantity? (Display your answer to the nearest whole number.) 491 Based on your answer to the previous question, and based on the annual demand as stated above, what will be the annual ordering costs? (Display your answer to the…
Excel Please. The workload of many areas of banking operations varies considerably based on time of day.  A variable capacity can be achieved effectively by employing part-time personnel.  Because part-timers are not entitled to all the fringe benefits, they are often more economical than full-time employees.  Other considerations, however, may limit the extent to which part-time people can be hired in a given department.  The problem is to find an optimal workforce schedule that would meet personnel requirements at any given time and also be economical.   Some of the factors affecting personnel assignments are listed here:   The bank is open from 9:00am to 7:00pm. Full-time employees work for 8 hours (1 hour for lunch included) per day. They do not necessarily have to start their shift when the bank opens. Part-time employees work for at least 4 hours per day, but less than 8 hours per day and do not get a lunch break. By corporate policy, total part-time personnel hours is limited…

Chapter 11 Solutions

Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)

Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Contemporary Marketing
Marketing
ISBN:9780357033777
Author:Louis E. Boone, David L. Kurtz
Publisher:Cengage Learning