The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: A Time B- Code Description (hrs) Immediate Predecessor(s) A Find location; determine resource requirements 20 None B Requisition of lumber and sand 65 A C Dig and grade 100 A D Saw lumber into appropriate sizes 30 B E Position lumber in correct locations 25 D, C F Nail lumber together E G Put sand in and under the equipment 25 F H H Put dirt around the equipment 10 F Put grass all over the garden, landscape, paint 35 G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 0 20 40 60 80 100 120 140 160 180 200 220 Clear all
The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: A Time B- Code Description (hrs) Immediate Predecessor(s) A Find location; determine resource requirements 20 None B Requisition of lumber and sand 65 A C Dig and grade 100 A D Saw lumber into appropriate sizes 30 B E Position lumber in correct locations 25 D, C F Nail lumber together E G Put sand in and under the equipment 25 F H H Put dirt around the equipment 10 F Put grass all over the garden, landscape, paint 35 G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 0 20 40 60 80 100 120 140 160 180 200 220 Clear all
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter5: Network Models
Section5.3: Assignment Models
Problem 11P
Related questions
Question

Transcribed Image Text:The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart
of the city for the recreation of its citizens. The precedence table for all the activities required to
construct this area successfully is as follows:
A
Time
B-
Code
Description
(hrs)
Immediate Predecessor(s)
A
Find location; determine resource
requirements
20
None
B
Requisition of lumber and sand
65
A
C
Dig and grade
100
A
D
Saw lumber into appropriate sizes
30
B
E
Position lumber in correct locations
25
D, C
F
Nail lumber together
E
G
Put sand in and under the equipment
25
F
H
H
Put dirt around the equipment
10
F
Put grass all over the garden, landscape,
paint
35
G, H
Refer to the legend for the activity that corresponds to each code.
Using the line drawing tool, draw a Gantt chart for activities E through I of the project.
0 20
40
60
80 100 120 140 160 180 200 220
Clear all
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing