Calculate the cost per cubic yard to place concrete using each of the alternatives described. The work in both cases consists of placing 140 cubic yards of concrete in footings.

a. Using a crane and bucket at a price of $225 per hour, including an operator, with a crew consisting of 6 laborers, a cement finisher, and a foreman. The concrete will be placed in 7 hours using this setup, and transportation of the crane costs $390.

b. Using a concrete pump at a price of $295 per hour, including an operator and a crew consisting of 5 laborers, a cement finisher, and a foreman. With this setup, concrete is placed in 6 hours and transportation of the pump costs $290.

Blurred answer
Students have asked these similar questions
Hello and respectCan you tell me the source of these questions from which book or pamphlet thank you
A steel, possessing an eutectoid composition, undergoes a gradual cooling process from 800°C to 600°C. Outline the transformation, equilibrium microstructure, and provide approximate component proportions. Describe the resultant non-equilibrium microstructure in two scenarios: a) the steel is rapidly cooled from 800°C to 600°C within 1 s, and then held at such temperature; b) the steel is rapidly cooled from 800°C to 600°C within 1 s, maintained at this temperature for 5 s, and subsequently quenched to room temperature. Use the provided diagrams. Temperature (°C) 1600 1538°C 1493°C 1400 L 1394°C Y+L 1200- 1147°C 2.14 Y. Austenite 4.30 1000 912°C Y+ FeC 800 a 600 400 0 (Fe) 0.76 0.022 a, Ferrite 2 a + Fe3C 3 Composition (wt% C) 727°C Cementite (Fe3C) 4 5 6 6.7
Please show the complete solution. The answers in this problem must be: 1. 16.25 kN 2. 51.725 kN 3. 45 000 mm² 4. 52.086 kN 5. 165.776 MPa 6. 62. 572 kN 7. 199. 173 MPa 8. 68.579 kN

Chapter 11 Solutions

FUND.OF CONSTRUCTION...-MINDTAP(2 TERM)

Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Text book image
Architectural Drafting and Design (MindTap Course...
Civil Engineering
ISBN:9781285165738
Author:Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:Cengage Learning
Text book image
Construction Materials, Methods and Techniques (M...
Civil Engineering
ISBN:9781305086272
Author:William P. Spence, Eva Kultermann
Publisher:Cengage Learning
Text book image
Solid Waste Engineering
Civil Engineering
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Cengage Learning,
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Text book image
Fundamentals of Geotechnical Engineering (MindTap...
Civil Engineering
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Pricing Concrete Jobs - 24' X 24' Concrete Floor (Prep, Pour, Finish); Author: Mike Day Concrete;https://www.youtube.com/watch?v=V-fgI1Hiu9w;License: Standard Youtube License