EBK OPERATIONS MANAGEMENT
EBK OPERATIONS MANAGEMENT
12th Edition
ISBN: 9780100283961
Author: Stevenson
Publisher: YUZU
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 11, Problem 1P

Compute the total cost for each aggregate plan using these unit costs:

Regular output = $40

Overtime = $50

Subcontract = $60

Average Balance Inventory = $10

a. Chapter 11, Problem 1P, Compute the total cost for each aggregate plan using these unit costs: Regular output = 40 Overtime , example  1

b. Chapter 11, Problem 1P, Compute the total cost for each aggregate plan using these unit costs: Regular output = 40 Overtime , example  2

c. (Refer to part b) After complaints from some workers about working overtime every month during the first half of the year, the manager is now considering adding some temporary workers for the second half of the year, which would increase regular output to a steady 350 units a month, not using any overtime, and using subcontracting to make up needed output. Determine the total cost of that plan.

a)

Expert Solution
Check Mark
Summary Introduction

To compute: The total cost for each aggregate plan

Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

Answer to Problem 1P

The total cost for the aggregate plan is $78,600.

Explanation of Solution

Given information:

Regular output is $40, overtime is $50, subcontract is $60, and average balance inventory is $10.

In addition to this, the following information is given:

Month January February March April May June
Forecast 300 320 320 340 320 320
Regular 300 300 300 300 300 300
Overtime 20 20 20 20 20 20
Subcontract 0 0 0 0 0 0

Determine the aggregate plan to compute total cost:

Month January February March April May June Total
Forecast 300 320 320 340 320 320 1,920
Output
Regular 300 300 300 300 300 300 1,800
Part-time
Overtime 20 20 20 20 20 20 120
Subcontract 0 0 0 0 0 0 0
Difference 20 0 0 -20 0 0 0
Inventory
Beginning 0 20 20 20 0 0 60
Ending 20 20 20 0 0 0 60
Average 10 20 20 10 0 0 60
Backlog 0 0 0 0 0 0 0
Costs
Regular 40 $12,000 $12,000 $12,000 $12,000 $12,000 $12,000 $72,000
Part-time
Overtime 50 $1,000 $1,000 $1,000 $1,000 $1,000 $1,000 $6,000
Subcontract 60 $0 $0 $0 $0 $0 $0 $0
Hire/Layoff
Inventory 10 $100 $200 $200 $100 $0 $0 $600
Backorders $0 $0 $0 $0 $0 $0 $0
$13,100 $13,200 $13,200 $13,100 $13,000 $13,000 $78,600

Supporting calculation:

Forecast, regular time units, overtime, and subcontract units were given.

Calculate the difference of month January:

It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 20 units.

Difference=OutputForecast=(Regular+Overtime+Subcontract)Forecast=(300+20+0)300=20

Calculate the difference of month February:

It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.

Difference=OutputForecast=(Regular+Overtime+Subcontract)Forecast=(300+20+0)320=0

Calculate the difference of month March:

It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.

Difference=OutputForecast=(Regular+Overtime+Subcontract)Forecast=(300+20+0)320=0

Note: The calculation repeats for all the months.

Beginning inventory:

The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.

Ending inventory for the month of January:

Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.

Ending inventory=[Beginning inventory of January+Difference between output and forecast]=0+20=20

Ending inventory for the month of February:

Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.

Ending inventory=[Beginning inventory of February+Difference between output and forecast]=20+0=20

Ending inventory for the month of March:

Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.

Ending inventory=Beginning inventory of March+Difference between output and forecast=20+0=20

Note: The calculation repeats for all the months.

Average inventory for the month of January:

It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 10 units.

Average inventory=Beginning inventory+Ending inventory2=0+202=10

Average inventory for the month of February:

It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 20 units.

Average inventory=Beginning inventory+Ending inventory2=20+202=20

Average inventory for the month of March:

It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 20 units.

Average inventory=Beginning inventory+Ending inventory2=20+202=20

Note: The calculation repeats for all the months.

Calculate the regular time cost for the month of January:

Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.

Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000

Calculate the regular time cost for the month of February:

Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.

Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000

Calculate the regular time cost for the month of March:

Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.

Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000

Note: The calculation repeats for all the months.

Calculate the total regular time cost:

It is calculated by adding the regular time cost of all the months.

Total regular time cost=Regular time of all the months=$12,000+$12,000+$12,000+$12,000+$12,000+$12,000=$72,000

Hence, the total regular time cost is $72,000.

Calculate the overtime cost for the month of January:

Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.

Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000

Calculate the overtime cost for the month of February:

Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.

Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000

Calculate the overtime cost for the month of March:

Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.

Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000

Note: The calculation repeats for all the months.

Calculate the total overtime cost:

It is calculated by adding the overtime cost of all the months.

Total overtime cost=Overtime of all the months=$1,000+$1,000+$1,000+$1,000+$1,000+$1,000=$6,000

Hence, the total overtime cost is $6,000.

Calculate the subcontract cost for the month of January:

Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.

Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0

Calculate the subcontract cost for the month of February:

Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.

Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0

Calculate the subcontract cost for the month of March:

Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.

Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0

Note: The calculation repeats for all the months.

Calculate the total subcontract cost:

It is calculated by adding the subcontract cost of all the months.

Total subcontract cost=Subcontract of all the months=$0+$0+$0+$0+$0+$0=$0

Hence, the total subcontract cost is $0.

Calculate the inventory cost for the month of January:

It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $100.

Inventory cost=Inventory cost per unit×Average inventory=$10×10=$100

Calculate the inventory cost for the month of February:

It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $200.

Inventory cost=Inventory cost per unit×Average inventory=$10×20=$200

Calculate the inventory cost for the month of March:

It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $200.

Inventory cost=Inventory cost per unit×Average inventory=$10×20=$200

Note: The calculation repeats for all the months.

Calculate the total inventory cost:

It is calculated by adding the inventory cost of all the months.

Total inventory cost=Inventory cost of all the months=$100+$200+$200+$100+$0+$0=$600

Hence, the total inventory cost is $600.

Calculate the total cost of the plan:

It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.

Total cost of the plan=(Total regular time cost+Total overtime cost+Total subcontract cost+Total inventory cost)=$72,000+$6,000+$0+$600=$78,600

Hence, the total cost of the plan is $78,600.

b)

Expert Solution
Check Mark
Summary Introduction

To compute: The total cost for each aggregate plan.

Introduction:The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

Answer to Problem 1P

The total cost for the aggregate plan is $95,500.

Explanation of Solution

Given information:

Regular output is $40, overtime is $50, subcontract is $60, and average balance inventory is $10.

In addition to this, the following information is given:

Month July August September October November December
Forecast 320 340 360 380 400 400
Regular 300 300 300 300 300 300
Overtime 20 20 20 20 30 30
Subcontract 20 30 40 40 60 70

Determine the aggregate plan to compute total cost:

Month July August September October November December Total
Forecast 320 340 360 380 400 400 2,200
Output
Regular 300 300 300 300 300 300 1,800
Part-time
Overtime 20 20 20 20 30 30 140
Subcontract 20 30 40 40 60 70 260
Difference 20 10 0 -20 -10 0 0
Inventory
Beginning 0 20 30 30 10 0 90
Ending 20 30 30 10 0 0 90
Average 10 25 30 20 5 0 90
Backlog 0 0 0 0 0 0 0
Costs
Regular 40 $12,000 $12,000 $12,000 $12,000 $12,000 $12,000 $72,000
Part-time
Overtime 50 $1,000 $1,000 $1,000 $1,000 $1,500 $1,500 $7,000
Subcontract 60 $1,200 $1,800 $2,400 $2,400 $3,600 $4,200 $15,600
Hire/Layoff
Inventory 10 $100 $250 $300 $200 $50 $0 $900
Backorders
$14,300 $15,050 $15,700 $15,600 $17,150 $17,700 $95,500

Supporting calculation:

Forecast, regular time units, overtime, and subcontract units were given.

Calculate the difference of month July:

It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 20 units.

Difference=OutputForecast=(Regular+Overtime+Subcontract)Forecast=(300+20+20)320=20

Calculate the difference of month August:

It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 10 units.

Difference=OutputForecast=(Regular+Overtime+Subcontract)Forecast=(300+20+30)340=10

Calculate the difference of month September:

It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.

Difference=OutputForecast=(Regular+Overtime+Subcontract)Forecast=(300+20+40)360=0

Note: The calculation repeats for all the months.

Beginning inventory:

The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.

Ending inventory for the month of July:

Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.

Ending inventory=Beginning inventory of July+Difference between output and forecast=0+20=20

Ending inventory for the month of August:

Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.

Ending inventory=Beginning inventory of August+Difference between output and forecast=20+10=30

Ending inventory for the month of September:

Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.

Ending inventory=Beginning inventory of September+Difference between output and forecast=30+0=30

Note: The calculation repeats for all the months.

Average inventory for the month of July:

It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 10 units.

Average inventory=Beginning inventory+Ending inventory2=0+202=10

Average inventory for the month of August:

It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 25 units.

Average inventory=Beginning inventory+Ending inventory2=20+302=25

Average inventory for the month of September:

It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 30 units.

Average inventory=Beginning inventory+Ending inventory2=30+302=30

Note: The calculation repeats for all the months.

Calculate the regular time cost for the month of July:

Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.

Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000

Calculate the regular time cost for the month of August:

Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.

Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000

Calculate the regular time cost for the month of September:

Regular time cost per unit is given as $40 and regular time unit is given as 300. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $12,000.

Regular time cost=Regular time cost per unit×Regular time units=$40×300=$12,000

Note: The calculation repeats for all the months.

Calculate the total regular time cost:

It is calculated by adding the regular time cost of all the months.

Total regular time cost=Regular time of all the months=$12,000+$12,000+$12,000+$12,000+$12,000+$12,000=$72,000

Hence, the total regular time cost is $72,000.

Calculate the overtime cost for the month of July:

Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.

Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000

Calculate the overtime cost for the month of August:

Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.

Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000

Calculate the overtime cost for the month of September:

Overtime cost per unit is given as $50 and overtime unit is given as 20. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $1,000.

Overtime cost=Overtime cost per unit×Overtime units=$50×20=$1,000

Note: The calculation repeats for all the months.

Calculate the total overtime cost:

It is calculated by adding the overtime cost of all the months.

Total overtime cost=Overtime of all the months=$1,000+$1,000+$1,000+$1,000+$1,000+$1,000=$6,000

Hence, the total overtime cost is $6,000.

Calculate the subcontract cost for the month of July:

Subcontract cost per unit is given as $60 and subcontract unit is given as 20. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $1,200.

Subcontract cost=Subcontract cost per unit×Subcontract units=$60×20=$1,200

Calculate the subcontract cost for the month of August:

Subcontract cost per unit is given as $60 and subcontract unit is given as 30. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $1,800.

Subcontract cost=Subcontract cost per unit×Subcontract units=$60×30=$1,800

Calculate the subcontract cost for the month of September:

Subcontract cost per unit is given as $60 and subcontract unit is given as 40. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $2,400.

Subcontract cost=Subcontract cost per unit×Subcontract units=$60×40=$2,400

Note: The calculation repeats for all the months.

Calculate the total subcontract cost:

It is calculated by adding the subcontract cost of all the months.

Total subcontract cost=Subcontract of all the months=$1,200+$1,800+$2,400+$2,400+$3,600+$4,200=$15,600

Hence, the total subcontract cost is $15,600.

Calculate the inventory cost for the month of July:

It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $100.

Inventory cost=Inventory cost per unit×Average inventory=$10×10=$100

Calculate the inventory cost for the month of August:

It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $250.

Inventory cost=Inventory cost per unit×Average inventory=$10×25=$250

Calculate the inventory cost for the month of September:

It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $300.

Inventory cost=Inventory cost per unit×Average inventory=$10×30=$300

Note: The calculation repeats for all the months.

Calculate the total inventory cost:

It is calculated by adding the inventory cost of all the months.

Total inventory cost=Inventory cost of all the months=$100+$250+$300+$200+$50+$0=$900

Hence, the total inventory cost is $900.

Calculate the total cost of the plan:

It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.

Total cost of the plan=(Total regular time cost+Total overtime cost+Total subcontract cost+Total inventory cost)=$72,000+$6,000+$15,600+$900=$95,500

Hence, the total cost of the plan is $95,500.

c)

Expert Solution
Check Mark
Summary Introduction

To compute: The total cost for each aggregate plan.

Introduction:The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

Answer to Problem 1P

The total cost for the aggregate plan is $91,000.

Explanation of Solution

Given information:

Regular output is $40, overtime is $50, subcontract is $60, and average balance inventory is $10.

In addition to this, the following information is given:

Month July August September October November December
Forecast 320 340 360 380 400 400
Regular 350 350 350 350 350 350
Overtime 0 0 0 0 0 0

It is given that subcontract can be used whenever necessary.

Determine the aggregate plan to compute total cost:

Month July August September October November December Total
Forecast 320 340 360 380 400 400 2,200
Output
Regular 350 350 350 350 350 350 2,100
Part-time
Overtime
Subcontract 50 50
Difference 30 10 -10 -30 0 0 0
Inventory
Beginning 0 30 40 30 0 0 100
Ending 30 40 30 0 0 0 100
Average 15 35 35 15 0 0 100
Backlog 0 0 0 0 0 0 0
Costs
Regular 40 $14,000 $14,000 $14,000 $14,000 $14,000 $14,000 $84,000
Part-time
Overtime 50 $0 $0 $0 $0 $0 $0 $0
Subcontract 60 $0 $0 $0 $0 $3,000 $3,000 $6,000
Hire/Layoff
Inventory 10 $150 $350 $350 $150 $0 $0 $1,000
Backorders 0 0 0 0 0 0 0
$14,150 $14,350 $14,350 $14,150 $17,000 $17,000 $91,000

Supporting calculation:

Forecast, regular time units, overtime, and subcontract units were given.

Calculate the difference of month July:

It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 30 units.

Difference=OutputForecast=(Regular+Overtime+Subcontract)Forecast=(350+0+0)320=30

Calculate the difference of month August:

It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 10 units.

Difference=OutputForecast=(Regular+Overtime+Subcontract)Forecast=(350+0+0)340=10

Calculate the difference of month September:

It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -10 units.

Difference=OutputForecast=(Regular+Overtime+Subcontract)Forecast=(350+0+0)360=10

Note: The calculation repeats for all the months.

Beginning inventory:

The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.

Ending inventory for the month of July:

Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 30 units.

Ending inventory=Beginning inventory of July+Difference between output and forecast=0+30=30

Ending inventory for the month of August:

Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 40 units.

Ending inventory=Beginning inventory of August+Difference between output and forecast=30+10=40

Ending inventory for the month of September:

Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 20 units.

Ending inventory=Beginning inventory of September+Difference between output and forecast=40+(10)=30

Note: The calculation repeats for all the months.

Average inventory for the month of July:

It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 15 units.

Average inventory=Beginning inventory+Ending inventory2=0+302=15

Average inventory for the month of August:

It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 35 units.

Average inventory=Beginning inventory+Ending inventory2=30+402=35

Average inventory for the month of September:

It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 35 units.

Average inventory=Beginning inventory+Ending inventory2=40+302=35

Note: The calculation repeats for all the months.

Calculate the regular time cost for the month of July:

Regular time cost per unit is given as $40 and regular time unit is given as 350. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $14,000.

Regular time cost=Regular time cost per unit×Regular time units=$40×350=$14,000

Calculate the regular time cost for the month of August:

Regular time cost per unit is given as $40 and regular time unit is given as 350. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $14,000.

Regular time cost=Regular time cost per unit×Regular time units=$40×350=$14,000

Calculate the regular time cost for the month of September:

Regular time cost per unit is given as $40 and regular time unit is given as 350. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $14,000.

Regular time cost=Regular time cost per unit×Regular time units=$40×350=$14,000

Note: The calculation repeats for all the months.

Calculate the total regular time cost:

It is calculated by adding the regular time cost of all the months.

Total regular time cost=Regular time of all the months=$14,000+$14,000+$14,000+$14,000+$14,000+$14,000=$84,000

Hence, the total regular time cost is $84,000.

Calculate the overtime cost for the month of July:

Overtime cost per unit is given as $50 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.

Overtime cost=Overtime cost per unit×Overtime units=$50×20=$0

Calculate the overtime cost for the month of August:

Overtime cost per unit is given as $50 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.

Overtime cost=Overtime cost per unit×Overtime units=$50×20=$0

Calculate the overtime cost for the month of September:

Overtime cost per unit is given as $50 and overtime unit is given as 0. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $0.

Overtime cost=Overtime cost per unit×Overtime units=$50×20=$0

Note: The calculation repeats for all the months.

Calculate the total overtime cost:

It is calculated by adding the overtime cost of all the months.

Total overtime cost=Overtime of all the months=$0+$0+$0+$0+$0+$0=$0

Hence, the total overtime cost is $0.

Calculate the subcontract cost for the month of July:

Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.

Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0

Calculate the subcontract cost for the month of August:

Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.

Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0

Calculate the subcontract cost for the month of September:

Subcontract cost per unit is given as $60 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.

Subcontract cost=Subcontract cost per unit×Subcontract units=$60×0=$0

Note: The calculation repeats for all the months. As there are backlogs in the month of November and December, there would be 50 units of subcontracting in those months.

Calculate the total subcontract cost:

It is calculated by adding the subcontract cost of all the months.

Total subcontract cost=Subcontract of all the months=$0+$0+$0+$0+$3,000+$3,000=$6,000

Hence, the total subcontract cost is $15,600.

Calculate the inventory cost for the month of July:

It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $150.

Inventory cost=Inventory cost per unit×Average inventory=$10×15=$150

Calculate the inventory cost for the month of August:

It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $350.

Inventory cost=Inventory cost per unit×Average inventory=$10×35=$350

Calculate the inventory cost for the month of September:

It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $350.

Inventory cost=Inventory cost per unit×Average inventory=$10×35=$350

Note: The calculation repeats for all the months.

Calculate the total inventory cost:

It is calculated by adding the inventory cost of all the months.

Total inventory cost=Inventory cost of all the months=$150+$350+$350+$150+$50+$0=$1,000

Hence, the total inventory cost is $1,000.

Calculate the total cost of the plan:

It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.

Total cost of the plan=(Total regular time cost+Total overtime cost+Total subcontract cost+Total inventory cost)=$84,000+$0+$6,000+$1,000=$91,000

Hence, the total cost of the plan is $91,000.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
“Implementing a Performance Management Communication Plan at Accounting, Inc.” Evaluate Accounting Inc.’s communication plan.  Specifically, does it answer all of the questions that a good communication plan should answer? Which questions are left unanswered?  How would you provide answers to the unanswered questions? “Implementing an Appeals Process at Accounting, Inc.”   If you were to design an appeals process to handle these complaints well, what would be the appeal process?  Describe the recommended process and why.
The annual demand for water bottles at Mega Stores is 500 units, with an ordering cost of Rs. 200 per order. If the annual inventory holding cost is estimated to be 20%. of unit cost, how frequently should he replenish his stocks? Further, suppose the supplier offers him a discount on bulk ordering as given below. Can the manager reduce his costs by taking advantage of either of these discounts? Recommend the best ordering policy for the store. Order size Unit cost (Rs.) 1 – 49 pcs. 20.00 50 – 149 pcs. 19.50 150 – 299 pcs. 19.00 300 pcs. or more 18.00
Help answer showing level work and formulas

Chapter 11 Solutions

EBK OPERATIONS MANAGEMENT

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY