Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN: 9781337788281
Author: James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher: Cengage Learning
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 10, Problem 7P

Self-Construction Olson Machine Company manufactures small and large milling machines. Selling prices of these machines range from $35,000 to $200,000. During the 5-month period from August 1, 2019, through December 31, 2019, Olson manufactured a milling machine for its own use. This machine was built as part of the regular production activities. The project required a large amount of time front planning and supervisory personnel, as well as that of some of the company’s officers, because it was a more sophisticated type of machine than the regular production models.

  Throughout the 5-month period, Olson charged all costs directly associated with the construction of the machine to a special account entitled “Asset Construction Account.” An analysis of the charges to this account as of December 31, 2019, follows:

Chapter 10, Problem 7P, Self-Construction Olson Machine Company manufactures small and large milling machines. Selling , example  1

Olson allocates factory overhead to normal production as a percent of direct labor dollars as follows:

Chapter 10, Problem 7P, Self-Construction Olson Machine Company manufactures small and large milling machines. Selling , example  2

Olson uses a flat rate of 40% of direct labor dollars to allocate general and administrative overhead.

  During the machine testing period, a cutter head malfunctioned and did extensive damage to the machine table and one cutter housing. This damage was not anticipated and was the result of an error in the assembly operation. Although no additional raw materials were needed to make the machine operational after the accident, the following labor for rework was required:

Chapter 10, Problem 7P, Self-Construction Olson Machine Company manufactures small and large milling machines. Selling , example  3

Olson has included all these labor charges in the asset construction account. In addition, it included in the account the repairs and maintenance charges of $1,340 that it incurred as a result of the malfunction.

Required:

  1. 1. Compute, consistent with GAAP and common practice, the amount that Olson should capitalize for the milling machine as of December 31, 2019, when it declares the machine operational.
  2. 2. Next Level Identify the costs you included in Requirement 1 for which there are acceptable alternative procedures. Describe the alternative procedure(s) in each case.

1.

Expert Solution
Check Mark
To determine

Calculate the amount that Company O must capitalize for the milling machine as of December 31, 2019.

Explanation of Solution

Cost of self-constructed assets:

Company sometimes constructs an item of “property, plant and equipment” which is used in the business operations and these are known as self-constructed assets. The cost of self-constructed assets comprises of expenses that are required to build an asset and put it in operating condition.

ParticularsAmount ($)Amount ($)
Raw materials:  
Iron castings61,040  
Other raw materials.50,200$111,240
Direct labor:  
Layout (1)$450  
Electricians  (2)2,700 
Machinery (3)7,200 
Heat treatment (4)750 
Assembly  (5)2,450 
Testing (6)1,280 
Additional testing labor (7)80015,630
Factory overhead:  
Layout and electricians (8)$2,205  
Machining, heat treatment, assembly, testing (9)  
 12,48014,685
Interest paid 4,260
Total amount to be capitalized  145,815

Table (1)

Working notes:

(1)Calculate the amount of direct labor costs for layout:

Directlaborcostsforlayout=Numberofhours×Costperunit=90hours×$5=$450

(2)Calculate the amount of direct labor costs for electricians:

Directlaborcostsforelectricians}=[(NumberofhoursNumberofdirectlaborhours)×Costperunit]=[(380hours80hours)×$9]=$2,700

(3)Calculate the amount of direct labor costs for machinery:

DirectlaborcostsforMachinery}=[(NumberofhoursNumberofdirectlaborhours)×Costperunit]=[(1,100hours200hours)×$8]=$7,200

(4)Calculate the amount of direct labor costs for Heat treatment:

DirectlaborcostsforHeattreatment}=Numberofhours×Costperunit=100hours×$7.50=$750

(5)Calculate the amount of direct labor costs for assembly:

Intermediate Accounting: Reporting And Analysis, Chapter 10, Problem 7P , additional homework tip  1

Directlaborcostsforassembly}=[(NumberofhoursNumberofdirectlaborhours)×Costperunit]=[(450hours100hours)×$7]=$2,450

(6)Calculate the amount of direct labor costs for testing:

Intermediate Accounting: Reporting And Analysis, Chapter 10, Problem 7P , additional homework tip  2

Directlaborcostsfortesting}=[(NumberofhoursNumberofdirectlaborhours)×Costperunit]=[(180hours20hours)×$8]=$1,280

(7)Calculate the amount of direct labor costs for additional testing labor:

Directlaborcostsforadditionaltestinglabor}=[(NumberofhoursNumberofdirectlaborhours)×Costperunit]=[(180hours20hours)×$5]=$800

(8)Calculate the factory overhead for layout and electricians:

Factoryoverheadforlayoutandelectricians}=Numberofhours×Costperunit=3,150hours×$0.70=$750

(9)Calculate the factory overhead for machinery, heat treatment, assembly and testing:

Factoryoverheadformachining,heattreatment,assemblyandtesting}=Numberofhours×Costperunit=12,480hours×$1=$12,480

2.

Expert Solution
Check Mark
To determine

Ascertain the costs included in requirement 1 for which there are acceptable alternative procedures and explain the alternative procedures for each case.

Explanation of Solution

“Alternate procedures are probable for two costs— factory overhead and rework costs (affects direct labor, repairs and maintenance, and factory overhead)”

  • Rework costs must be taken as cost for the period in which they are nonstandard. Rework costs rising from errors that must not have incurred should be considered as losses of the period. Seemingly, this was the case in this condition since the impairment resulted from a type of error that is not expected. Accordingly, related repairs, maintenance expenses and rework costs are not capitalized in requirement 1.
  • Two alternative ways are there to allocate overhead costs to self-constructed assets. The method followed in “requirement 1” is to allot a portion of all overhead costs to the self-constructed asset. The reason which justifies this particular treatment is that all productive output must absorb its proportionate share of all factory overhead costs. Additionally, this method result in a cost of the constructed asset that approximates the cost of the equivalent asset acquired.
  • Capitalizing the incremental overhead, that is traceable fixed and variable overhead is the second method that increases as a result of construction. Additional costs occurred in production of the fixed asset (part of the assets’ cost) are included in this method. Traceable fixed overhead and variable overhead are occurred to build the asset and it will be advantageous in the upcoming periods therefore, these costs must be capitalized.
  • If there is no relationship between the self-constructed asset and fixed overhead costs, non-traceable fixed overhead costs will be incurred so, these costs must not be capitalized.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Chilton Peripherals manufactures printers, scanners, and other computer peripheral equipment. In the past, thecompany purchased equipment used in manufacturing from an outside vendor. In March 2018, Chilton decidedto design and build equipment to replace some obsolete equipment. A section of the manufacturing plant was setaside to develop and produce the equipment. Additional personnel were hired for the project. The equipment wascompleted and ready for use in September.Required:1. In general, what costs should be capitalized for a self-constructed asset?2. Discuss two alternatives for the inclusion of overhead costs in the cost of the equipment constructed by Chilton. Which alternative is generally accepted for financial reporting purposes?3. Under what circumstance(s) would interest be included in the cost of the equipment?
Teal Mountain Company has been a retailer of audio systems for the past 3 years. However, after a thorough survey of audio system markets, Teal Mountain decided to turn its retail store into an audio equipment factory. Production began October 1, 2022. Direct materials costs for an audio system total $77 per unit. Workers on the production lines are paid $13 per hour. An audio system takes 6 labor hours to complete. In addition, the rent on the equipment used to assemble audio systems amounts to $5,070 per month. Indirect materials cost $5 per system. A supervisor was hired to oversee production; her monthly salary is $3,700. Factory janitorial costs are $2,030 monthly. Advertising costs for the audio system will be $9,030 per month. The factory building depreciation is $6,360 per year. Property taxes on the factory building will be $8,520 per year. Assuming that Teal Mountain manufactures, on average, 1,400 audio systems per month, enter each cost item on your answer sheet, placing…
Hammer Company produces a variety of electronic equipment. One of its plants produces two laser printers: The Deluxe and the Regular. At the beginning of the year 2019, the following data were prepared for this plant:     Deluxe Regular Quantity 20 000 80 000 Selling price $90 $75 Unit direct cost $53 $48   In addition, the following information was provided so that overhead costs could be assigned to each product:   Activity name Activity Cost Activity driver Deluxe Regular Set-up $200,000 Number of set-up 3 000 5 000 Machining 800,000 Machine hours 10 000 30 000 Engineering 600,000 Engineering hours 100 000 50 000 Packing 100,000 Packing orders 1 000 4 000 Total overhead costs $1,700,000         Required: Calculate the production overhead cost allocated to each product in 2019 using machine-hours as the cost driver (traditional costing system).     Calculate the…

Chapter 10 Solutions

Intermediate Accounting: Reporting And Analysis

Ch. 10 - At what amount does a company record the cost of a...Ch. 10 - Prob. 12GICh. 10 - Prob. 13GICh. 10 - Prob. 14GICh. 10 - Prob. 15GICh. 10 - Prob. 16GICh. 10 - Prob. 17GICh. 10 - What is the distinction between a capital and an...Ch. 10 - Distinguish between additions and...Ch. 10 - Distinguish between ordinary repairs and...Ch. 10 - Prob. 21GICh. 10 - Hickory Company made a lump-sum purchase of three...Ch. 10 - Prob. 2MCCh. 10 - Electro Corporation bought a new machine and...Ch. 10 - Prob. 4MCCh. 10 - Lyle Inc. purchased certain plant assets under a...Ch. 10 - Ashton Company exchanged a nonmonetary asset with...Ch. 10 - Prob. 7MCCh. 10 - Prob. 8MCCh. 10 - Prob. 9MCCh. 10 - Prob. 10MCCh. 10 - On January 1, Duane Company purchases land at a...Ch. 10 - Prob. 2RECh. 10 - Utica Corporation paid 360,000 to purchase land...Ch. 10 - Prob. 4RECh. 10 - Prob. 5RECh. 10 - Prob. 6RECh. 10 - Nabokov Company exchanges assets with Faulkner...Ch. 10 - Prob. 8RECh. 10 - Dexter Construction Corporation is building a...Ch. 10 - Prob. 10RECh. 10 - Prob. 11RECh. 10 - Ricks Towing Company owns three tow trucks. During...Ch. 10 - Inclusion in Property, Plant, and Equipment...Ch. 10 - Prob. 2ECh. 10 - Acquisition Costs Voiture Company manufactures...Ch. 10 - Determination of Acquisition Cost In January 2019,...Ch. 10 - Asset Retirement Obligation Big Cat Exploration...Ch. 10 - Prob. 6ECh. 10 - Prob. 7ECh. 10 - Prob. 8ECh. 10 - Exchange of Assets Two independent companies,...Ch. 10 - Exchange of Assets Use the same information as in...Ch. 10 - Prob. 11ECh. 10 - Exchange of Assets Goodman Company acquired a...Ch. 10 - Exchange of Assets Use the same information as in...Ch. 10 - Prob. 14ECh. 10 - Self-Construction Harshman Company constructed a...Ch. 10 - Prob. 16ECh. 10 - Prob. 17ECh. 10 - Prob. 18ECh. 10 - Prob. 19ECh. 10 - Expenditures after Acquisition McClain Company...Ch. 10 - Prob. 21ECh. 10 - Prob. 1PCh. 10 - Classification of Costs Associated with Assets The...Ch. 10 - Prob. 3PCh. 10 - Comprehensive At December 31, 2018, certain...Ch. 10 - Assets Acquired by Exchange Bremer Company made...Ch. 10 - Assets Acquired by Exchange Bussell Company...Ch. 10 - Self-Construction Olson Machine Company...Ch. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Events Subsequent to Acquisition The following...Ch. 10 - Prob. 11PCh. 10 - Prob. 1CCh. 10 - Prob. 2CCh. 10 - Cost Issues Deskin Company purchased a new machine...Ch. 10 - Prob. 4CCh. 10 - Prob. 5CCh. 10 - Prob. 6CCh. 10 - Prob. 7CCh. 10 - Prob. 9CCh. 10 - Prob. 10CCh. 10 - Prob. 11C
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Cost Classifications - Managerial Accounting- Fixed Costs Variable Costs Direct & Indirect Costs; Author: Accounting Instruction, Help, & How To;https://www.youtube.com/watch?v=QQd1_gEF1yM;License: Standard Youtube License