
Practical Management Science
6th Edition
ISBN: 9781337406659
Author: WINSTON, Wayne L.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 10, Problem 56P
When you use a RISKSIMTABLE function for a decision variable, such as the order quantity in the Walton model, explain how this provides a “fair” comparison across the different values tested.
Expert Solution & Answer

Trending nowThis is a popular solution!

Students have asked these similar questions
The S&OP team at Kansas Furniture, led by David Angelow, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sales of $125
per unit, inventory carrying costs of $30 per unit per month, and zero beginning and ending inventory, evaluate the following plan on an incremental cost basis:
Plan B: Vary the workforce to produce the prior month's demand. Demand was 1,300 units in June. The cost of hiring additional workers is $35 per unit produced. The cost of layoffs is $60 per unit
cut back. (Enter all responses as whole numbers.)
Note: Both hiring and layoff costs are incurred in the month of the change (i.e., going from production of 1,300 in July to 1300 in August requires a layoff (and related costs) of 0 units in August).
Hire
Month
1 July
Demand
1300
Production
(Units)
Layoff
(Units)
Ending
Inventory
Stockouts
(Units)
2 August
1150
3 September
1100
4 October
1600
5 November
1900
6 December
1900
The S&OP team at Kansas Furniture, led by David Angelow, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sales of $100
per unit, inventory carrying costs of $20 per unit per month, and zero beginning and ending inventory, evaluate the following plan on an incremental cost basis:
Plan A: Produce at a steady rate (equal to minimum requirements) of 1,100 units per month and subcontract additional
units at a $65 per unit premium cost. Subcontracting capacity is limited to 800 units per month. (Enter all responses as whole numbers).
Ending
Month
Demand
Production Inventory
Subcontract
(Units)
1
July
1300
1,100
0
2
August
1150
1,100
0
3
September
1100
1,100
0
4 October
1600
1,100
0
5 November
1900
1,100
0
6 December
1200
1,100
0
Please help me expand upon my research even more in detail please. Need help added more to mine from the photos please. Not sure what more I can add.
Chapter 10 Solutions
Practical Management Science
Ch. 10.2 - Use the RAND function and the Copy command to...Ch. 10.2 - Use Excels functions (not @RISK) to generate 1000...Ch. 10.2 - Use @RISK to draw a uniform distribution from 400...Ch. 10.2 - Use @RISK to draw a normal distribution with mean...Ch. 10.2 - Use @RISK to draw a triangular distribution with...Ch. 10.2 - Use @RISK to draw a binomial distribution that...Ch. 10.2 - Use @RISK to draw a triangular distribution with...Ch. 10.2 - We all hate to keep track of small change. By...Ch. 10.4 - Prob. 11PCh. 10.4 - In August of the current year, a car dealer is...
Ch. 10.4 - Prob. 13PCh. 10.4 - Prob. 14PCh. 10.4 - Prob. 15PCh. 10.5 - If you add several normally distributed random...Ch. 10.5 - In Problem 11 from the previous section, we stated...Ch. 10.5 - Continuing the previous problem, assume, as in...Ch. 10.5 - In Problem 12 of the previous section, suppose...Ch. 10.5 - Use @RISK to analyze the sweatshirt situation in...Ch. 10.5 - Although the normal distribution is a reasonable...Ch. 10.6 - When you use @RISKs correlation feature to...Ch. 10.6 - Prob. 24PCh. 10.6 - Prob. 25PCh. 10.6 - Prob. 28PCh. 10 - Six months before its annual convention, the...Ch. 10 - Prob. 30PCh. 10 - A new edition of a very popular textbook will be...Ch. 10 - Prob. 32PCh. 10 - W. L. Brown, a direct marketer of womens clothing,...Ch. 10 - Assume that all of a companys job applicants must...Ch. 10 - Lemingtons is trying to determine how many Jean...Ch. 10 - Dilberts Department Store is trying to determine...Ch. 10 - It is surprising (but true) that if 23 people are...Ch. 10 - Prob. 40PCh. 10 - At the beginning of each week, a machine is in one...Ch. 10 - Simulation can be used to illustrate a number of...Ch. 10 - Prob. 43PCh. 10 - Prob. 46PCh. 10 - If you want to replicate the results of a...Ch. 10 - Suppose you simulate a gambling situation where...Ch. 10 - Prob. 49PCh. 10 - Big Hit Video must determine how many copies of a...Ch. 10 - Prob. 51PCh. 10 - Prob. 52PCh. 10 - Why is the RISKCORRMAT function necessary? How...Ch. 10 - Consider the claim that normally distributed...Ch. 10 - Prob. 55PCh. 10 - When you use a RISKSIMTABLE function for a...Ch. 10 - Consider a situation where there is a cost that is...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- How can HR proactively help ensure that other departments are operating in a legally acceptable manner? Answers Deliver interdepartmental training on legal compliance and requirements. Discuss potential sources of risk with an attorney and create a plan to respond to lawsuits. Ensure that all HR members are watching the conduct of other departments and report infractions to the head of HR. Record improper conduct from various employees throughout the organization and pursue disciplinary measures.arrow_forwardCan you guys help me with this? Thank you! Project is Terminal 1 at JFK International Airport Question: Risk management content: Discuss a major risk management event that affected the project (Keep this content about 2 minute talking and please provide actual sources that you have the information to go over this)arrow_forwarduse the screenshot to find the anwser to this If the project finishes within 27 weeks of its start, the project manager receives a $500 bonus. What is the probability of a $500 bonus? Note: Round z-value to 2 decimal places, and probability to 4 decimal places.arrow_forward
- Scan To Pay Log into your own Lightning UPI account of supporting app and scan QR code below to pay! ✰ BINANCEarrow_forwardTo help with preparations, a couple has devised a project network to describe the activities that must be completed by their wedding date. Start A Ꭰ F B E The following table lists the activity time estimates (in weeks) for each activity. Optimistic Most Probable Activity Pessimistic A 4 5 6 B 2.5 3 3.5 C 5 6 7 D 5 5.5 9 E 5 7 9 F 2 3 4 G 7 9 11 H 5 6 13 H Finish Based only on the critical path, what is the estimated probability that the project will be completed within the given time frame? (Round your answers to four decimal places.) (a) Within 19 weeks? (b) Within 21 weeks? (c) Within 25 weeks?arrow_forwardYou may need to use the appropriate technology to answer this question. Mueller Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 46-week completion date requested by the owner. The Mueller project manager prepared the following project network. B H Start A C G Finish E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. Activity Optimistic Most Probable Pessimistic A 4 12 B 6 7 8 C 6 18 D 3 5 7 E 6 9 18 F 5 8 17 G 10 15 20 H 5 13 (a) Find the critical path. (Enter your answers as a comma-separated list.) (b) What is the expected project completion time (in weeks)? weeks i (c) Based only on the critical path, what is the estimated probability the project can be completed in 46 weeks as requested by the owner? (Round your answer to four decimal places.) (d) Based only on the critical path, what is…arrow_forward
- Bridge City Developers is coordinating the construction of an office complex. As part of the planning process, the company generated the following activity list. Draw a project network that can be used to assist in the scheduling of the project activities. Activity Immediate Predecessor ABC E FGH ] A, B A, B D E с с F, G, H, I A E Start B D A E Start B D H H E A E Finish Start D F J Finish Start B D F Finish Finish C H I Harrow_forwardHow can mindfulness be combined with cognitive reframing to build emotional regulation and mental flexibility? What is the strategy for maintaining mental well-being to improve through deliberate practice? How to engage in practices that help regulate emotions and build resilience?arrow_forward• We Are HIRING Salesforce Developer (2 - 4 Years) @ Cloudodyssey It Solutions Requirement : Appropriate knowledge on Salesforce standard objects Leads, Account, Contacts, Opportunity, Products, Lead process, Sales process, is required. • Hands-on experience in Salesforce Experience Cloud, Sales Cloud and Lightning. • • Hands experience with Salesforce development, administration, system integrations, Lightning Design System, and bug fixes. Experience in configuration, integration, APIs creation, testing and deployment of Salesforce.com functionality. Eloquent verbal and written communication skills. • Familiar with Agile framework. Work Location: Bangalore SUBMIT YOUR CV hello@cloudodyssey.coarrow_forward
- Agree or disagree with post On the surface, the numbers in financial statements do present a snapshot of a company's financial position and performance. However, just looking at the raw numbers often doesn't tell the whole story or reveal underlying trends and relationships that are crucial for making informed decisions. Think of it like looking at individual pieces of a puzzle. Each number is a piece, providing some information. But to see the complete picture – the company's overall financial health, its performance over time, how it compares to its peers, and its potential future – you need to assemble those pieces using different analytical tools. For example: Horizontal analysis helps us understand how specific financial statement items have changed over multiple periods. Is revenue growing? Are expenses increasing at a faster rate than sales? This reveals trends that a single year's numbers wouldn't show. Vertical analysis allows us to see the relative size of each item within…arrow_forwardWhat can you do in response to an insulting offer?arrow_forwardAgree or disagree with post If someone hits you with an insulting offer, the first thing to do is not take it personally. It’s normal to feel a little offended, but blowing up or shutting down won’t help your case. Better move is to stay calm and treat it like a misunderstanding or just the first step in the conversation. That way, you keep things respectful but still let them know the offer doesn’t sit right with you. It also helps to back up your response with facts. Bring in things like your experience, numbers, or any specific results you delivered. That can shift the conversation away from feelings and toward the value you bring. Agree or disagree with postarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY