a)
To determine: The normal time for the operation.
Introduction: The time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
a)

Answer to Problem 28P
The normal time is calculated as 77.8 minutes.
Explanation of Solution
Given information:
The observed time and performance rating for each element is given as follows:
Element | Performance rating | Observation (minutes) | ||||
1 | 2 | 3 | 4 | 5 | ||
Prepare daily reports | 120 | 35 | 40 | 33 | 42 | 39 |
Photocopy results | 110 | 12 | 10 | 36a | 15 | 13 |
Label and package reports | 90 | 3 | 3 | 5 | 5 | 4 |
Distribute reports | 85 | 15 | 18 | 21 | 17 | 45b |
a refers to the photocopying machine being broken
b refers to the delay in allowance factor
Formulae to calculate normal time:
Calculate normal time:
Element | Performance rating | Observation (minutes) | Average time | Normal time | ||||
1 | 2 | 3 | 4 | 5 | ||||
Prepare daily reports | 120% | 35 | 40 | 33 | 42 | 39 | 37.8 | 45.36 |
Photocopy results | 110% | 12 | 10 | 36a | 15 | 13 | 12.5 | 13.75 |
Label and package reports | 90% | 3 | 3 | 5 | 5 | 4 | 4 | 3.6 |
Distribute reports | 85% | 15 | 18 | 21 | 17 | 45b | 17.75 | 15.09 |
Calculate the average time to prepare daily reports:
The average time is calculated by taking an average of the observation given, which is a summation of 35, 40, 33, 42, and 39 and dividing the result by 5. Hence, the average is 37.8 minutes.
Calculate the average time to photocopy results:
The average time is calculated by taking an average of the observation given, which is a summation of 12, 10, 15, and 13 and dividing the result by 4. Hence, the average is 12.5 minutes.
Note: The observation with (Xa) should not be considered while calculating the average time.
Calculate the average time to label and package reports:
The average time is calculated by taking an average of the observation given, which is a summation of 3, 3, 5, 5, and 4 and dividing the result by 5. Hence, the average is 4 minutes.
Calculate the average time to distribute reports:
The average time is calculated by taking an average of the observation given, which is a summation of 15, 18, 21, and 17 and dividing the result by 4. Hence, the average is 17.75 minutes.
Note: The observation with (Xb) should not be considered while calculating the average time.
Calculate the normal time to prepare daily reports:
The normal time is calculated by multiplying average time and performance rating. The average time is calculated as 37.8 minutes, and performance rating is given as 120%. Hence, the normal time is 45.36 minutes.
Calculate the normal time to photocopy results:
The normal time is calculated by multiplying average time and performance rating. The average time is calculated as 12.50 minutes, and performance rating is given as 110%. Hence, the normal time is 13.75 minutes.
Calculate the normal time to label and package reports:
The normal time is calculated by multiplying average time and performance rating. The average time is calculated as 4.0 minutes, and performance rating is given as 90%. Hence, the normal time is 3.6 minutes.
Calculate the normal time to distribute reports:
The normal time is calculated by multiplying average time and performance rating. The average time is calculated as 17.75 minutes, and performance rating is given as 85%. Hence, the normal time is 15.09 minutes.
Calculate the total normal time:
The normal time is calculated by adding the normal time to prepare daily reports, photocopy results, label and package reports, and distribute reports.
Hence, the total normal time is 77.8 minutes.
b)
To determine: The standard time for the operation.
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
b)

Answer to Problem 28P
Thestandard time is calculated as 91.53 minutes.
Explanation of Solution
Given information:
The allowance is given as 15%. The observed time and performance rating for each element is given as follows:
Element | Performance rating | Observation (minutes) | ||||
1 | 2 | 3 | 4 | 5 | ||
Prepare daily reports | 120 | 35 | 40 | 33 | 42 | 39 |
Photocopy results | 110 | 12 | 10 | 36a | 15 | 13 |
Label and package reports | 90 | 3 | 3 | 5 | 5 | 4 |
Distribute reports | 85 | 15 | 18 | 21 | 17 | 45b |
a refers to the photocopying machine being broken
b refers to the delay in allowance factor
Formula to calculate standard time:
Calculate standard time:
The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. Normal time is calculated as 77.8 minutes and allowance factor is calculated as 15%
Hence, standard time is 91.53 minutes.
c)
To determine: The number of the
Introduction: The sample size is required to determine the number of observations that are necessary to find the true cycle time.
c)

Answer to Problem 28P
The sample size to prepare reports is 15, to photocopy results is 44, label, and package reports is 96, and to distribute reports is 31 samples.
Explanation of Solution
Given information:
The confidence level is 95% and accuracy is ±5%.
Element | Performance rating | Observation (minutes) | ||||
1 | 2 | 3 | 4 | 5 | ||
Prepare daily reports | 120 | 35 | 40 | 33 | 42 | 39 |
Photocopy results | 110 | 12 | 10 | 36a | 15 | 13 |
Label and package reports | 90 | 3 | 3 | 5 | 5 | 4 |
Distribute reports | 85 | 15 | 18 | 21 | 17 | 45b |
Formula to determine the required number of observation:
n refers to the number of observations required
z refers to the table value for the confidence level
s refers to the standard deviation
h refers to an accuracy level
x(bar) refers to the average observed time
Determine a proper number of observation required:
Element | Mean observed time | s | Sample |
Prepare daily reports | 37.8 | 3.7 | 15 |
Photocopy results | 12.5 | 2.1 | 44 |
Label and package reports | 4 | 1 | 96 |
Distribute reports | 17.75 | 2.5 | 31 |
Calculate the standard deviation to prepare daily reports:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the results should be square rooted. The standard deviation to prepare the daily report is 3.7.
Calculate the standard deviation to photocopy results:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the results should be square rooted. The standard deviation to photocopy results is 2.1.
Calculate the standard deviation to label and package reports:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the results should be square rooted. The standard deviation to label and package reports is 1.
Calculate the standard deviation to distribute reports:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the results should be square rooted. The standard deviation to distribute reports is 2.5.
Calculate the sample size to prepare daily reports:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 3.7, and dividing the result with the multiple of the accuracy level and average observed time that is given as 0.05 and 37.8, respectively. Hence, the required number of observations is 15 samples.
Calculate the sample size to photocopy results:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 2.1, and dividing the result with the multiple of the accuracy level and average observed time that is given as 0.05 and 12.5, respectively. Hence, the required number of observations is 44 samples.
Calculate the sample size to label and package reports:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 1, and dividing the result with the multiple of the accuracy level and average observed time that is given as 0.05 and 4, respectively. Hence, the required number of observations is 96 samples.
Calculate the sample size to distribute reports:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 2.5, and dividing the result with the multiple of the accuracy level and average observed time that is given as 0.05 and 17.75, respectively. Hence, the required number of observations is 31 samples.
Hence, the normal time for the process is 77.8 minutes and standard time for the process is 91.53 minutes. The sample size to prepare reports is 15, to photocopy results is 44, label and package reports are 96, and to distribute reports is 31 samples.
Want to see more full solutions like this?
Chapter 10 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
- The deaths are included in the discharges; this includes deaths occurring in less than 48 hours and postoperative deaths. Rehabilitation had 362 discharges, 22 deaths, 1<48 hours, 0 Postoperative. what is the gross death rate for the rehabilitation service?arrow_forwardA copy machine is available 24 hours a day. On a typical day, the machine produces 100 jobs. Each job takes about 3 minutes on the machine, 2 minutes of which is processing time and 1 minute is setup time (logging in, defining the job). About 20 percent of the jobs need to be reworked, in which case the setup time and the processing time have to be repeated. The remainder of the time, the equipment is idle. What is the OEE of the equipment?arrow_forwardHow do you think we can keep updating Toyota's ideas as new technologies come out and what customers want keeps changing?arrow_forward
- Given how TPS has helped change things in so many fields, do you think there are parts of it that might be hard to use in areas that aren’t about making things, like in healthcare or services? If so, why do you think that might be?arrow_forwardDo you feel there is anything positive about rework?arrow_forwardDo you think technology can achieve faster setup times? How would it be implemented in the hospital workforce?arrow_forward
- In your experience or opinion, do you think process changes like organizing workspaces make a bigger difference, or is investing in technology usually the better solution for faster setups?arrow_forwardHave you seen rework done in your business, and what was done to prevent that from occurring again?arrow_forwardResearch a company different than case studies examined and search the internet and find an example of a business that had to rework a process. How was the organization affected to rework a process in order to restore a good flow unit? Did rework hurt a process or improve the organization's operational efficiency? • Note: Include a reference with supportive citations in the discussion reply in your post.arrow_forward
- Setup time is very important in affecting a process and the capacity of a process. How do you reduce setup time? Give examples of reducing setup time. Please Provide a referenecearrow_forwardDo you think TPS was successful? If so, how? Are there other companies that have used TPS? If so, give examples. Please provide a referencearrow_forwardGiven the significant impact on finances, production timelines, and even equipment functionality, as you pointed out, what do you believe is the most effective single strategy a company can implement to significantly reduce the occurrence of rework within their operations?arrow_forward
- Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning
- Understanding Management (MindTap Course List)ManagementISBN:9781305502215Author:Richard L. Daft, Dorothy MarcicPublisher:Cengage Learning