Question
Book Icon
Chapter 10, Problem 25P

a)

Summary Introduction

To determine: The normal time for the operation

Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.

a)

Expert Solution
Check Mark

Answer to Problem 25P

Thenormal time calculated as 3.23 minutes.

Explanation of Solution

Given information:

The allowance for tasks is given as 7% for personal, 10% for fatigue, and 3% for delay. The observed time and performance rating for each element is given as follows:

Element Performance rating Observation (minutes per cycle)
1 2 3 4 5
1 110% 0.5 0.4 0.6 0.4 0.4
2 95% 0.6 0.8 0.7 0.6 0.7
3 90% 0.6 0.4 0.7 0.5 0.5
4 85% 1.5 1.8 2 1.7 1.5

Formulae to calculate normal time:

Average time=Observationsn

Normal time=Average time×Performance rating

Calculate the normal time:

Element Performance rating Observation (minutes) Average time Normal time
1 2 3 4 5
1 110% 0.5 0.4 0.6 0.4 0.4 0.46 0.51
2 95% 0.6 0.8 0.7 0.6 0.7 0.68 0.65
3 90% 0.6 0.4 0.7 0.5 0.5 0.54 0.49
4 85% 1.5 1.8 2 1.7 1.5 1.7 1.45

Excel worksheet:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 10, Problem 25P

Calculate the average time for the first element:

Average time=Observationn=0.5+0.4+0.6+0.4+0.45=2.35=0.46 minutes

The average time is calculated by taking an average of the observation given, which is summation of 0.5, 0.4, 0.6, 0.4, and 0.4 and dividing the result by 5. Hence, the average is 0.46 minutes.

Calculate the average time for the second element:

Average time=Observationn=0.6+0.8+0.7+0.6+0.75=3.45=0.68 minutes

The average time is calculated by taking an average of the observation given, which is summation of 0.6, 0.8, 0.7, 0.6, and 0.7 and dividing the result by 5. Hence, the average is 0.68 minutes.

Calculate the average time for the third element:

The average time is calculated by taking an average of the observation given, which is summation of 0.6, 0.4, 0.7 0.5, and 0.5 and dividing the result by 5. Hence, the average is 0.54 minutes.

Average time=Observationn=0.6+0.4+0.7+0.5+0.55=2.75=0.54 minutes

Calculate the average time for the fourth element:

The average time is calculated by taking an average of the observation given, which is summation of 1.5, 1.8, 2.0, 1.7, and 1.5 and dividing the result by 5. Hence, the average is 1.7 minutes.

Average time=Observationn=1.5+1.8+2.0+1.7+1.55=8.55=1.7 minutes

Calculate the normal time for the first element:

The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.46 minutes, and performance rating is given as 110%. Hence, the normal time is 0.51 minutes.

Normal time=Average time×Performance rating=0.46×110%=0.46×1.1=0.51 minutes

Calculate the normal time for the second element:

The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.68 minutes, and performance rating is given as 95%. Hence, the normal time is 0.65 minutes.

Normal time=Average time×Performance rating=0.68×95%=0.68×1.05=0.65 minutes

Calculate the normal time for the third element:

The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.54 minutes, and performance rating is given as 90%. Hence, the normal time is 0.49 minutes.

Normal time=Average time×Performance rating=0.54×90%=0.54×0.90=0.49 minutes

Calculate the normal time for the fourth element:

The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 1.7 minutes, and performance rating is given as 85%. Hence, the normal time is 1.45 minutes.

Normal time=Average time×Performance rating=1.7×85%=1.7×0.85=1.45 minutes

Calculate the total normal time:

The normal time is calculated by adding the normal time of all the elements.

Normal time=Sum of normal times=0.51+0.65+0.49+1.45=3.08 minutes

Hence, the total normal time is 3.08 minutes.

b)

Summary Introduction

To determine: The standard time for the operation.

Introduction: Time study is the basis that helps set the standard time, it would time a sample of the performance of the worker.

b)

Expert Solution
Check Mark

Answer to Problem 25P

Thestandard time is calculated as 5.4 minutes.

Explanation of Solution

Given information:

The allowance for tasks is given as 7% for personal, 10% for fatigue, and 3% for delay. The observed time and performance rating for each element are given as follows:

Element Performance rating Observation (minutes per cycle)
1 2 3 4 5
1 110% 0.5 0.4 0.6 0.4 0.4
2 95% 0.6 0.8 0.7 0.6 0.7
3 90% 0.6 0.4 0.7 0.5 0.5
4 85% 1.5 1.8 2 1.7 1.5

Formulae to calculate standard time:

Allowance factor=Personal+Fatigue+Delay

Standard time=Normal time1Allowance factor

Calculate the allowance factor:

The allowance factor is calculated by adding personal allowance, fatigue, and delay allowance. Personal allowance is given as 7%, fatigue is 10%, and delay allowance is 3%. Hence, the allowance factor is 20%.

Allowance factor=Personal+Fatigue+Delay=7%+10%+3%=20%

Calculate the standard time:

The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. The normal time is calculated as 3.08 minutes and the allowance factor is calculated as 20%

Standard time=Normal time1Allowance factor=3.08 minutes10.20=3.08 minutes0.80=3.85 minutes

Hence, the standard time is 3.85 minutes.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
When does it work?
Durban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and photographs of the bread.Mkumla said she was later contacted by a man from Sasko who apologised for the incident.According to…
PepsiCo South Africa says the incident where a woman discovered part of a rodent in her loaf of bread, is anisolated occurrence.Durban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and…
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Foundations of Business - Standalone book (MindTa...
Marketing
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,