
Concept explainers
A.
Interpretation: A network diagram representing the activities of the project is to be constructed.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
A.

Explanation of Solution
Given information: Theactivities to be taken up for the construction of a gas station and the time duration for each are given in the table.
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The activity times and the precedence relationship are shown in the table:
Activity | Time | Predecessors |
A | 4 | |
B | 2 | A |
C | 3 | B |
D | 1 | C |
E | 1 | D |
F | 2 | B |
G | 3 | F |
H | 1 | G |
I | 5 | B |
J | 3 | I |
K | 4 | C, F, I |
L | 2 | K |
M | 1 | L |
The network diagram showing the work flows is as follows:
B.
Interpretation: The critical path is to be identified by computing the earliest and the latest start and finish times.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
B.

Answer to Problem 26AP
The critical path is A − B − I − K − L − M with completion time as 18 weeks
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The earliest and latest start and finish times are calculated using the formulae:
Earliest Start (EST) = Maximum EFT of the predecessor activity
Latest Start (LST) = LFT - Duration
Earliest Finish (EFT) = EST + Duration
Latest Finish (LFT) = Minimum LST of the immediate successor
Slack = LFT − EFT (or) LST − EST
Activity | Time | EST | EFT | LST | LFT | Slack |
A | 4 | 0 | 4 | 0 | 4 | 0 |
B | 2 | 4 | 6 | 4 | 6 | 0 |
C | 3 | 6 | 9 | 8 | 11 | 2 |
D | 1 | 9 | 10 | 16 | 17 | 7 |
E | 1 | 10 | 11 | 17 | 18 | 7 |
F | 2 | 6 | 8 | 9 | 11 | 3 |
G | 3 | 8 | 11 | 14 | 17 | 6 |
H | 1 | 11 | 12 | 17 | 18 | 6 |
I | 5 | 6 | 11 | 6 | 11 | 0 |
J | 3 | 11 | 14 | 15 | 18 | 4 |
K | 4 | 11 | 15 | 11 | 15 | 0 |
L | 2 | 15 | 17 | 15 | 17 | 0 |
M | 1 | 17 | 18 | 17 | 18 | 0 |
The critical path includes the activities with zero slack. So, here the critical path is A − B− I − K − L − M. The total time taken to complete the project is 18 weeks.
C.
Interpretation: A Gantt chart of the
Concept Introduction: Gantt chart is a project management tool that is a type of bar chart. It depicts the project schedule and is used for resource allocation.
C.

Answer to Problem 26AP
A Gantt chart for the project has been drawn.
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
Activity times and early start times:
Activity | EST | Time |
A | 0 | 4 |
B | 4 | 2 |
C | 6 | 3 |
D | 9 | 1 |
E | 10 | 1 |
F | 6 | 2 |
G | 8 | 3 |
H | 11 | 1 |
I | 6 | 5 |
J | 11 | 3 |
K | 11 | 4 |
L | 15 | 2 |
M | 17 | 1 |
The Gantt chart depicting the project based on the EST:
D.
Interpretation: The impact of replacement of the air compressor which takes two weeks on the completion of the project is to be determined.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
D.

Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
Installing the air compressor is represented by activity G.
Activity | Time | EST | EFT | LST | LFT | Slack |
A | 4 | 0 | 4 | 0 | 4 | 0 |
B | 2 | 4 | 6 | 4 | 6 | 0 |
C | 3 | 6 | 9 | 8 | 11 | 2 |
D | 1 | 9 | 10 | 16 | 17 | 7 |
E | 1 | 10 | 11 | 17 | 18 | 7 |
F | 2 | 6 | 8 | 9 | 11 | 3 |
G | 3 | 8 | 11 | 14 | 17 | 6 |
H | 1 | 11 | 12 | 17 | 18 | 6 |
I | 5 | 6 | 11 | 6 | 11 | 0 |
J | 3 | 11 | 14 | 15 | 18 | 4 |
K | 4 | 11 | 15 | 11 | 15 | 0 |
L | 2 | 15 | 17 | 15 | 17 | 0 |
M | 1 | 17 | 18 | 17 | 18 | 0 |
The latest start time of the activity G is 14th week. If the failure is identified before installation, the project will not be delayed as the replacement time (2 weeks) is less than the slack (6 weeks).
If the failure is found during testing of the air compressor, represented by activity H, still the project would not be delayed, as again there is a slack of 6 weeks.
E.
Interpretation: The activities that can be completed by the end of the 15th week without delaying the project completion are to be determined.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the work flow and is used to compute the total duration of the project.
E.

Answer to Problem 26AP
The activities A, B, C, F and I have to be completed by the end of the 15th week to guarantee project completion without delay.
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The table shows the Earliest and Latest times of the activities
Activity | Time | EST | EFT | LST | LFT | Slack |
A | 4 | 0 | 4 | 0 | 4 | 0 |
B | 2 | 4 | 6 | 4 | 6 | 0 |
C | 3 | 6 | 9 | 8 | 11 | 2 |
D | 1 | 9 | 10 | 16 | 17 | 7 |
E | 1 | 10 | 11 | 17 | 18 | 7 |
F | 2 | 6 | 8 | 9 | 11 | 3 |
G | 3 | 8 | 11 | 14 | 17 | 6 |
H | 1 | 11 | 12 | 17 | 18 | 6 |
I | 5 | 6 | 11 | 6 | 11 | 0 |
J | 3 | 11 | 14 | 15 | 18 | 4 |
K | 4 | 11 | 15 | 11 | 15 | 0 |
L | 2 | 15 | 17 | 15 | 17 | 0 |
M | 1 | 17 | 18 | 17 | 18 | 0 |
The latest finish times of the activities A, B, C, F and Iam less than 15 weeks. Therefore, these activities have to be completed by the end of the 15th weeks to guarantee project completion without any delay.
F.
Interpretation: The optimal solution for the problem is to be determined using linear programming.
Concept Introduction: Linear programming is a mathematical technique used to achieve the best outcome, given a list of parameters usually restrictions on the resources.
F.

Answer to Problem 26AP
The optimal solution for the problem is obtained using linear programming.
Explanation of Solution
Given information:
Activity | Time |
A | 4 |
B | 2 |
C | 3 |
D | 1 |
E | 1 |
F | 2 |
G | 3 |
H | 1 |
I | 5 |
J | 3 |
K | 4 |
L | 2 |
M | 1 |
The various paths of the project and the durations are:
The critical path is A − B − I − K − L − M with the completion time of 18 weeks.
Using linear programming, the EST is calculated.
Objective function = =SUM (B2:M2)
Nodes | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
EST |
The constraints
Activity | Time | ||
A | 0 | > | 4 |
B | 0 | > | 2 |
C | 0 | > | 3 |
D | 0 | > | 1 |
E | 0 | > | 1 |
F | 0 | > | 2 |
G | 0 | > | 3 |
H | 0 | > | 1 |
I | 0 | > | 5 |
J | 0 | > | 3 |
K | 0 | > | 4 |
L | 0 | > | 2 |
M | 0 | > | 1 |
P1 | 0 | > | 0 |
P2 | 0 | > | 0 |
P3 | 0 | > | 0 |
Solver Solution:
Objective Function |
120 |
EST for the nodes:
Nodes | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
EST | 0 | 4 | 6 | 9 | 8 | 11 | 11 | 11 | 10 | 15 | 17 | 18 |
Want to see more full solutions like this?
Chapter 10 Solutions
EBK PRODUCTION AND OPERATIONS ANALYSIS
- a. What order quantity should be used? lures. (Enter your response rounded to the nearest whole number.) b. What reorder point should be used? (Enter your response rounded to the nearest whole number.) c. What is the total annual cost for this inventory system? (Enter your response rounded to two decimal places)arrow_forwardOakwood Hospital is considering using ABC analysis to classify laboratory SKUS into three categories: those that will be delivered daily from their supplier (Class A items), those that will be controlled using a continuous review system (B items), and those that will be held in a two bin system (C items). The following table shows the annual dollar usage for a sample of eight SKUS. Fill in the blanks for annual dollar usage below. (Enter your responses rounded to the nearest whole number.) SKU Unit Value Demand (units) Annual Dollar Usage 1 $1.10 30,000 $ 2 $0.02 125,000 $ 3 $0.20 65,000 S 4 $0.02 1,100 SA 5 $1.40 150 SA 678 $4.10 900 $ $0.80 350 $ $0.55 80 EA $arrow_forwardDyson, a high-tech home appliance maker, has cut ties with Malaysian supplier ATA IMS Bhd following an audit of the company's labour practices and allegations by a whistleblower. ATA is already under US investigation over forced labour allegations. Dyson has terminated its contracts and is in talks with its customer over the audit findings. ATA, which produces parts for Dyson's vacuum cleaners and air purifiers, tumbled 30% to its lowest since April 2020. The termination is a significant blow for Malaysia, a major electronics manufacturing hub, which has faced scrutiny this year over claims of abusive working and living conditions. Dyson terminated the relationship with six months' contractual notice, hoping it would give ATA the impetus to improve and enable an orderly withdrawal in the interests of the workers they employ. Former ATA worker Dhan Kumar Limbu was beaten by police in Malaysia after sharing information about conditions at the factory with activists. ATA denied all…arrow_forward
- Question 4 (25 Marks) Discuss how developing internal performance measures to track the performance of supplier development, can create efficiency for Pick n Pay.arrow_forwardLeadership and people Earlier this year, Pick n Pay actioned the first priority of the plan: the introduction of a new, simplified and seasoned leadership team with proven track records. The team has already implemented strengthened structures, including establishing regional trading areas with local decision-making, with clear sight of strong long-term succession Each operating region now has a regional buying team and store management team in place to meet specific customer needs particular to that region, while also increasing staff training and productivity for an overall improved store experience. Reset the store estate To create a more sustainable supermarket business, the Group is resetting its store estate to minimise losses by creating a smaller but more profitable Pick n Pay store estate. The plan is to leverage the strength of its multi-format model with strategic conversions to lift store profitability: selected Pick n Pay stores will be converted to Boxer, where customer…arrow_forwardQuestion 3 (25 Marks) Elaborate on how Pick n Pay could use information technology and ERP systems across the company and their suppliers to improve their operating model? Question 4 (25 Marks)arrow_forward
- Question 2 (25 Marks) Discuss how you would "reset the store estate" to remain competitive and relevant in the market? Question 3 (25 Marks)arrow_forwardWhat should leaders do after conducting an employee survey? take immediate action on results take at least 6 months to review the results to make sure the leader understands them review them immediately, but do not take action right away keep results confidential from employeesarrow_forwardOne of the best ways to encourage teamwork is to: continually promote from outside of the department recognize employees who focus on their personal performance goals only reward employees who complete their own tasks and also assist with problems outside of their department discuss individual performance issues at staff meetingsarrow_forward
- What can happen if a leader doesn't encourage teamwork? team members will support each other more the environment can become overly competitive and hostile turnover will descrease team members become more motivatedarrow_forwardunderstand 4 Classwork LSC Drag the name of the figure of speech to its example. 12 February 2025 personification Onomatopoeia Simile Metaphor Hyperbole Onomatopoeia metaphor 1. He tried to help but his legs were wax. Metaphor 2. The man flights like a lion on the soccer field. Simile 3. The books fell on the table with a loud thump. Onomatopoeia 4. Rita heard the last piece of pie calling her name. Personification 5. The rustling leaves kept me away. Personification 6. Kisses are the flowers of affection. 7. He's running faster than the windarrow_forwardAnswer the question in the attached photo and draw the network that interprets the dataarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning

