Fundamentals of Corporate Finance
11th Edition
ISBN: 9780077861704
Author: Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Bradford D Jordan Professor
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Question
Chapter 10, Problem 21QP
Summary Introduction
To find: The project that must be selected by the firm
Introduction:
When the projects accept the one investment, it means that they reject the others that are the mutually exclusive projects. Even though the projects stand alone, they have good investments such as the positive
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Which of the following is TRUE about NPV? LO3
NPV is the ratio of a project's present value to the amount of resources consumed in generating it.
O NPV is the rate at which IRR equals $0.
O NPV and IRR are equally reliable investment decision rules when evaluating mutually exclusive projects.
O NPV is the difference between the present value of the benefits and the present value of the costs of a project.
Question 4 (4 points)
◄ Listen
The IRR of normal Project X is greater than the IRR of normal Project Y, and both IRRs are greater than zero. Also,
the NPV of X is greater than the NPV of Y at the cost of capital. If the two projects are mutually exclusive, Project X
should definitely be selected, and the investment made, provided we have confidence in the data. Put another way, it is
impossible to draw NPV profiles that would suggest not accepting Project X.
True
False
QUESTION 7
Which of the following statements is correct?
a. When there are two mutually exclusive projects, the project with the highest NPV should be chosen.
D. The payback period criterion properly considers the time value of money.
OC. The IRR method correctly ranks mutually exclusive projects.
d. Since investors prefer more return and less risk, one will never hold a dominated asset in the risk-return sense. In other words, if asset A has a higher
expected return and lower standard-deviation than asset B, then investors would only hold asset A in their optimal portfolio.
e. When an investment project is evaluated today, the spending that occurred in the last year has to be included in the NPV analysis.
Chapter 10 Solutions
Fundamentals of Corporate Finance
Ch. 10.1 - What are the relevant incremental cash flows for...Ch. 10.1 - What is the stand-alone principle?Ch. 10.2 - Prob. 10.2ACQCh. 10.2 - Prob. 10.2BCQCh. 10.2 - Explain why interest paid is not a relevant cash...Ch. 10.3 - What is the definition of project operating cash...Ch. 10.3 - For the shark attractant project, why did we add...Ch. 10.4 - Prob. 10.4ACQCh. 10.4 - How is depreciation calculated for fixed assets...Ch. 10.5 - Prob. 10.5ACQ
Ch. 10.5 - Prob. 10.5BCQCh. 10.6 - Prob. 10.6ACQCh. 10.6 - Under what circumstances do we have to worry about...Ch. 10 - Prob. 10.1CTFCh. 10 - What should NOT be included as an incremental cash...Ch. 10 - Prob. 10.3CTFCh. 10 - An asset costs 24,000 and is classified as...Ch. 10 - Prob. 10.5CTFCh. 10 - Prob. 10.6CTFCh. 10 - Opportunity Cost [LO1] In the context of capital...Ch. 10 - Depreciation [LO1] Given the choice, would a firm...Ch. 10 - Net Working Capital [LO1] In our capital budgeting...Ch. 10 - Stand-Alone Principle [LO1] Suppose a financial...Ch. 10 - Prob. 5CRCTCh. 10 - Cash Flow and Depreciation [LOI] When evaluating...Ch. 10 - Capital Budgeting Considerations [LOI] A major...Ch. 10 - Prob. 8CRCTCh. 10 - Prob. 9CRCTCh. 10 - Prob. 10CRCTCh. 10 - Relevant Cash Flows [LO1] Parker Slone, Inc., is...Ch. 10 - Prob. 2QPCh. 10 - Calculating Projected Net Income [LO1] A proposed...Ch. 10 - Calculating OCF [LO1] Consider the following...Ch. 10 - OCF from Several Approaches [LO1] A proposed new...Ch. 10 - Calculating Depreciation [LO1] A piece of newly...Ch. 10 - Calculating Salvage Value [LO1] Consider an asset...Ch. 10 - Calculating Salvage Value [LO1] An asset used in a...Ch. 10 - Calculating Project OCF [LO1] Quad Enterprises is...Ch. 10 - Calculating Project NPV [LO1] In the previous...Ch. 10 - Prob. 11QPCh. 10 - NPV and Modified ACRS [LO1] In the previous...Ch. 10 - Project Evaluation [LO1] Dog Up! Franks is looking...Ch. 10 - Project Evaluation [LO1] Your firm is...Ch. 10 - Prob. 15QPCh. 10 - Calculating EAC [LO4] A five-year project has an...Ch. 10 - Calculating EAC [LO4] You are evaluating two...Ch. 10 - Calculating a Bid Price [LO3] Romo Enterprises...Ch. 10 - Cost-Cutting Proposals [LO2] Warmack Machine Shop...Ch. 10 - Comparing Mutually Exclusive Projects [LO1] Lang...Ch. 10 - Prob. 21QPCh. 10 - Prob. 22QPCh. 10 - Prob. 23QPCh. 10 - Comparing Mutually Exclusive Projects [LO4]...Ch. 10 - Equivalent Annual Cost [LO4] Compact fluorescent...Ch. 10 - Break-Even Cost [LO2] The previous problem...Ch. 10 - Break-Even Replacement [LO2] The previous two...Ch. 10 - Issues in Capital Budgeting [LO1] The debate...Ch. 10 - Replacement Decisions [LO2] Your small remodeling...Ch. 10 - Replacement Decisions [LO2] In the previous...Ch. 10 - Calculating Project NPV [LO1] You have been hired...Ch. 10 - Prob. 32QPCh. 10 - Calculating Required Savings [LO2] A proposed...Ch. 10 - Prob. 34QPCh. 10 - Calculating a Bid Price [LO3] Your company has...Ch. 10 - Replacement Decisions [LO2] Suppose we are...Ch. 10 - Conch Republic Electronics, Part 1 Conch Republic...Ch. 10 - Conch Republic Electronics, Part 1 Conch Republic...Ch. 10 - Conch Republic Electronics, Part 1 Conch Republic...Ch. 10 - Conch Republic Electronics, Part 1 Conch Republic...
Knowledge Booster
Similar questions
- F3arrow_forwardLO3 Explain how to set a bid price for a project. LO4 Evaluate the equivalent annual cost of a project.arrow_forwardDivisional Cost of Capital [LO5] Under what circumstances would it be appropriate for a firm to use different costs of capital for its different operating divisions? If the overall firm WACC were used as the hurdle rate for all divisions, would the riskier divisions or the more conservative divisions tend to get most of the investment projects? Why? If you were to try to estimate the appropriate cost of capital for different divisions, what problems might you encounter? What are two techniques you could use to develop a rough estimate for each division’s cost of capital?arrow_forward
- 12.arrow_forwardGive detail explanationarrow_forwardCompute the Profitability Index (PI) for each project? Project A Project B Profitability Index (PI) 5- In light of your answers above, suppose that these two projects might be mutually exclusive or independent. According to these two assumptions, fill in the blanks in the table below with the suitable answer: Points Investment Criteria If A and B are mutually exclusive, then I would select If A and B are independent, then I would select PBP NPV IRR PIarrow_forward
- Making the accept or reject decision Hungry Whale Electronics's decision to accept or reject project Alpha is independent of its decisions on other projects. If the firm follows the NPV method, it should project Alpha. Which of the following statements best explains what it means when a project has an NPV of $0? O When a project has an NPV of $0, the project is earning a rate of return less than the project's weighted average cost of capital. It's OK to accept the project, as long as the project's profit is positive. O When a project has an NPV of $0, the project is earning a rate of return equal to the project's weighted average cost of capital. It's OK to accept a project with an NPV of $0, because the project is earning the required minimum rate of return. O When a project has an NPV of $0, the project is earning a profit of $0. A firm should reject any project with an NPV of $0, because the project is not profitable.arrow_forwardsolve this parctie problemarrow_forwardWorldTrans is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter payback will not cause value to be lost. WACC: 14.25% 0 1 2 3 4 CFS -$950 $500 $800 $0 $0 CFL -$2,100 $400 $800 $800 $1,000 Group of answer choices $127.87 $95.90 $93.62 $116.46 $0.00arrow_forward
- Are there conditions under which a firm might be better off if it were to choose a machine with a rapid traditional payback period, PB, rather than one with a larger NPV? Explain.arrow_forwardQuestion 10 2 pts Which of the following statements is (or are) true? [Select all correct responses.] O For a borrowing (or "delayed investment" project), the internal rate of return (IRR) decision rule states that if the IRR exceeds the benchmark rate, accept the project. O For an investment, the IRR decision rule states that if the IRR exceeds the benchmark rate, accept the project. O NPV should never be used if the project under consideration has nonconventional cash flows. D A decision maker who is considering several mutually exclusive investment opportunities should use IRR to choose the best one among them. O The payback investment rule might not use all possible cash flows in its calculation. O In some instances, for example for mutually exclusive investments, the NPV rule is not as conceptually legitimate as is the payback rule. Practitioners generally prefer the payback decision criterion to the IRR because payback considers the time value of money while IRR does not. The…arrow_forward1) What is the company's WACC? 2) Should the company take the projects? Assume that the projects have the same risk as an average project for your firm. 3) If one project is depended on the other in a way that the company can only take both projects, should it take it?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningAccounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,