Question
Chapter 10, Problem 15QP
Summary Introduction
To find: Whether the project is accepted, and the pretax level of the cost savings that would be indifferent in accepting and not accepting the project.
Introduction:
The systematic and objective evaluation of the completed or the ongoing project is the project evaluation.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Pm.3
Find out the profitability index (PI) of the following project assuming the required rate of return is 8%. Will you accept the project? Why?
year 0 1 2 3 4 5 Cash Flow ($) -250,000 50,000 40,000 120,000 80,000 45,000
Group of answer choices
Accept the project because the PI is equal to 1.06, which is larger than 0.
Accept the project because the PI is equal to 0.98, which is larger than 0.
Reject the project because the PI is equal to 1.06, which is larger than 1.
Reject the project because the PI is equal to 0.98, which is lower than 1.
Accept the project because the PI is equal to 1.06, which is larger than 1.
2. Calculating Payback [LO2] An investment project
provides cash inflows of $745 per year for eight years. What
is the project payback period if the initial cost is $1,700?
What if the initial cost is $3,30o? What if it is $6,100?
note : please you dont use excel.
Chapter 10 Solutions
Fundamentals of Corporate Finance
Ch. 10.1 - What are the relevant incremental cash flows for...Ch. 10.1 - What is the stand-alone principle?Ch. 10.2 - Prob. 10.2ACQCh. 10.2 - Prob. 10.2BCQCh. 10.2 - Explain why interest paid is not a relevant cash...Ch. 10.3 - What is the definition of project operating cash...Ch. 10.3 - For the shark attractant project, why did we add...Ch. 10.4 - Prob. 10.4ACQCh. 10.4 - How is depreciation calculated for fixed assets...Ch. 10.5 - Prob. 10.5ACQ
Ch. 10.5 - Prob. 10.5BCQCh. 10.6 - Prob. 10.6ACQCh. 10.6 - Under what circumstances do we have to worry about...Ch. 10 - Prob. 10.1CTFCh. 10 - What should NOT be included as an incremental cash...Ch. 10 - Prob. 10.3CTFCh. 10 - An asset costs 24,000 and is classified as...Ch. 10 - Prob. 10.5CTFCh. 10 - Prob. 10.6CTFCh. 10 - Opportunity Cost [LO1] In the context of capital...Ch. 10 - Depreciation [LO1] Given the choice, would a firm...Ch. 10 - Net Working Capital [LO1] In our capital budgeting...Ch. 10 - Stand-Alone Principle [LO1] Suppose a financial...Ch. 10 - Prob. 5CRCTCh. 10 - Cash Flow and Depreciation [LOI] When evaluating...Ch. 10 - Capital Budgeting Considerations [LOI] A major...Ch. 10 - Prob. 8CRCTCh. 10 - Prob. 9CRCTCh. 10 - Prob. 10CRCTCh. 10 - Relevant Cash Flows [LO1] Parker Slone, Inc., is...Ch. 10 - Prob. 2QPCh. 10 - Calculating Projected Net Income [LO1] A proposed...Ch. 10 - Calculating OCF [LO1] Consider the following...Ch. 10 - OCF from Several Approaches [LO1] A proposed new...Ch. 10 - Calculating Depreciation [LO1] A piece of newly...Ch. 10 - Calculating Salvage Value [LO1] Consider an asset...Ch. 10 - Calculating Salvage Value [LO1] An asset used in a...Ch. 10 - Calculating Project OCF [LO1] Quad Enterprises is...Ch. 10 - Calculating Project NPV [LO1] In the previous...Ch. 10 - Prob. 11QPCh. 10 - NPV and Modified ACRS [LO1] In the previous...Ch. 10 - Project Evaluation [LO1] Dog Up! Franks is looking...Ch. 10 - Project Evaluation [LO1] Your firm is...Ch. 10 - Prob. 15QPCh. 10 - Calculating EAC [LO4] A five-year project has an...Ch. 10 - Calculating EAC [LO4] You are evaluating two...Ch. 10 - Calculating a Bid Price [LO3] Romo Enterprises...Ch. 10 - Cost-Cutting Proposals [LO2] Warmack Machine Shop...Ch. 10 - Comparing Mutually Exclusive Projects [LO1] Lang...Ch. 10 - Prob. 21QPCh. 10 - Prob. 22QPCh. 10 - Prob. 23QPCh. 10 - Comparing Mutually Exclusive Projects [LO4]...Ch. 10 - Equivalent Annual Cost [LO4] Compact fluorescent...Ch. 10 - Break-Even Cost [LO2] The previous problem...Ch. 10 - Break-Even Replacement [LO2] The previous two...Ch. 10 - Issues in Capital Budgeting [LO1] The debate...Ch. 10 - Replacement Decisions [LO2] Your small remodeling...Ch. 10 - Replacement Decisions [LO2] In the previous...Ch. 10 - Calculating Project NPV [LO1] You have been hired...Ch. 10 - Prob. 32QPCh. 10 - Calculating Required Savings [LO2] A proposed...Ch. 10 - Prob. 34QPCh. 10 - Calculating a Bid Price [LO3] Your company has...Ch. 10 - Replacement Decisions [LO2] Suppose we are...Ch. 10 - Conch Republic Electronics, Part 1 Conch Republic...Ch. 10 - Conch Republic Electronics, Part 1 Conch Republic...Ch. 10 - Conch Republic Electronics, Part 1 Conch Republic...Ch. 10 - Conch Republic Electronics, Part 1 Conch Republic...
Knowledge Booster
Similar questions
- 7. The NPV and payback period What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. Year Year 1 Year 2 Year 3 Year 4 If the project's weighted average cost of capital (WACC) is 10%, the project's NPV (rounded to the nearest dollar) is: O O Cash Flow $325,000 $475,000 $425,000 $475,000 0 0 $351,183 $367,146 Which of the following statements indicate a disadvantage of using the regular payback period (not the discounted payback period) for capital budgeting decisions? Check all that apply. $319,257 $303,294 The payback period is calculated using net income instead of cash flows. The payback period does not take the project's entire life into account. The payback period does not take the…arrow_forwardM4arrow_forwardsolve it correctly. not use excelarrow_forward
- Solve this problemarrow_forward7. The NPV and payback period What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $375,000 Year 2 $475,000 Year 3 $500,000 Year 4 $400,000 If the project’s weighted average cost of capital (WACC) is 8%, the project’s NPV (rounded to the nearest dollar) is: $345,386 $328,117 $414,463 $362,655arrow_forward7. The NPV and payback period What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $300,000 Year 2 $450,000 Year 3 $500,000 Year 4 $500,000 If the project’s weighted average cost of capital (WACC) is 8%, the project’s NPV (rounded to the nearest dollar) is: $470,812 $449,412 $513,613 $428,011 Which of the following statements indicate a disadvantage of using the regular payback period (not the discounted payback period) for capital budgeting decisions? Check all that apply. The payback period does not take the time value of money into account. The payback period is calculated using net…arrow_forward
- Note: PLEASE YOU DONT USE EXCELarrow_forwardMoving to another question will save this response. Question 4 XYZ is evaluating a project that would require an initial investment of $74,900.00 today. The project is expected to produce annual cash flows of $8,900.00 each year forever with the first annual cash flow expected in 1 year. The NPV of the project is $7,100.00. What is the IRR of the project? O 10.85% (plus or minus 0.02 percentage points) O 11.88% (plus or minus 0.02 percentage points) O 9.48% (plus or minus 0.02 percentage points) O 13.13% (plus or minus 0.02 percentage points) O None of the above is within 0.02 percentage points of the correct answer A Moving to another question will save this response.arrow_forward4. Calculating Discounted Payback (LO3) An investment project has annual cash inflows of $4,200, $5.300, $6.100, and $7,400, and a discount rate of 14%. What is the discounted payback period for these cash flows if the initial cost is $7.000? What if the initial cost is $10,000? What if it is $13,000?arrow_forward
- 4. Calculating Discounted Payback [LO3] An investment project has annual cash inflows of $2,800, $3,700, $5,100, and $4,300, for the next four years, respectively. The discount rate is 11 percent. What is the discounted payback period for these cash flows if the initial cost is $5,200? What if the initial cost is $6,40o? What if it is $10,400?arrow_forwardPlease answer the question. The details of the question are attached in the image below.arrow_forwardDon't use chat botarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- EBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT