Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into three activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that, even though we should have 83 percent (25/30) of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far, $175,000 has actually been brought in on the project. Calculate the Schedule Variance, Schedule Performance Index, and Cost (actually value in this case) Performance Index. How is the project going? (Hint: Note that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.)
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into three activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that, even though we should have 83 percent (25/30) of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far, $175,000 has actually been brought in on the project. Calculate the
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 4 images