You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you determined the following cost formulas and gathered the following actual cost data for March: Utilities Maintenance Supplies Indirect labor Depreciation Cost Formula $16,600+ $0.14 per machine-hour $38,300+ $1.20 per machine-hour $0.80 per machine-hour $94,700+ $1.70 per machine-hour $67,600 Actual Cost in March $ 21,340 $ 57,300 $ 16,600 $ 131,300 $ 69,300 During March, the company worked 19,000 machine-hours and produced 13,000 units. The company had originally planned to work 21,000 machine-hours during March. Required: 1. Calculate the activity variances for March. 2. Calculate the spending variances for March.
You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you determined the following cost formulas and gathered the following actual cost data for March: Utilities Maintenance Supplies Indirect labor Depreciation Cost Formula $16,600+ $0.14 per machine-hour $38,300+ $1.20 per machine-hour $0.80 per machine-hour $94,700+ $1.70 per machine-hour $67,600 Actual Cost in March $ 21,340 $ 57,300 $ 16,600 $ 131,300 $ 69,300 During March, the company worked 19,000 machine-hours and produced 13,000 units. The company had originally planned to work 21,000 machine-hours during March. Required: 1. Calculate the activity variances for March. 2. Calculate the spending variances for March.
Essentials of Business Analytics (MindTap Course List)
2nd Edition
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Chapter11: Linear Optimization Models
Section: Chapter Questions
Problem 10P: The management of Hartman Company is trying to determine the amount of each of two products to...
Related questions
Concept explainers
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Topic Video
Question
Please do not give solution in image format thanku
![ices
Complete this question by entering your answers in the tabs below.
Required 1 Required 2
Calculate the activity variances for March. (Indicate the effect of each variance by selecting "F" for favorable, "U" for
unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
Utilities
Maintenance
Supplies
Indirect labor
Depreciation
Total
FAB Corporation
Activity Variances
For the Month Ended March 31
Required 1 Required 2
Utilities
Maintenance
Supplies
Indirect labor
Depreciation
Total
< Required 1
Complete this question by entering your answers in the tabs below.
FAB Corporation
Spending Variances
For the Month Ended March 31
< Prev
Required 2 >
Calculate the spending variances for March. (Indicate the effect of each variance by selecting "F" for favorable, "U" for
unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
< Required 1
1 of 3
Next >
Required 2 >](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F24de9d49-6070-4d88-ab58-a37c20172dbc%2F1875dc5f-9e71-4248-b8c2-f2fad3474089%2F7g4ezyv_processed.jpeg&w=3840&q=75)
Transcribed Image Text:ices
Complete this question by entering your answers in the tabs below.
Required 1 Required 2
Calculate the activity variances for March. (Indicate the effect of each variance by selecting "F" for favorable, "U" for
unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
Utilities
Maintenance
Supplies
Indirect labor
Depreciation
Total
FAB Corporation
Activity Variances
For the Month Ended March 31
Required 1 Required 2
Utilities
Maintenance
Supplies
Indirect labor
Depreciation
Total
< Required 1
Complete this question by entering your answers in the tabs below.
FAB Corporation
Spending Variances
For the Month Ended March 31
< Prev
Required 2 >
Calculate the spending variances for March. (Indicate the effect of each variance by selecting "F" for favorable, "U" for
unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
< Required 1
1 of 3
Next >
Required 2 >
![You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has
asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing
overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be
an excellent first step in overhead planning and control.
After much effort and analysis, you determined the following cost formulas and gathered the following actual cost data for March:
Utilities
Maintenance
Supplies
Indirect labor
Depreciation
Cost Formula.
$16,600+ $0.14 per machine-hour
$38,300+ $1.20 per machine-hour
$0.80 per machine-hour
$94,700+ $1.70 per machine-hour
$67,600
Required:
1. Calculate the activity variances for March.
2. Calculate the spending variances for March.
During March, the company worked 19,000 machine-hours and produced 13,000 units. The company had originally planned to work
21,000 machine-hours during March.
Actual Cost
in March 1
$ 21,340
$ 57,300
$ 16,600
$ 131,300
$ 69,300
Complete this question by entering your answers in the tabs below.
FAB Corporation
Activity Variances
Far the Manth Endad Merak 10
Required 1 Required 2
Calculate the activity variances for March. (Indicate the effect of each variance by selecting "F" for favorable, "U" for
unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
< Prev
1 of 3
Next >](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F24de9d49-6070-4d88-ab58-a37c20172dbc%2F1875dc5f-9e71-4248-b8c2-f2fad3474089%2F5uor4b6_processed.jpeg&w=3840&q=75)
Transcribed Image Text:You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has
asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing
overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be
an excellent first step in overhead planning and control.
After much effort and analysis, you determined the following cost formulas and gathered the following actual cost data for March:
Utilities
Maintenance
Supplies
Indirect labor
Depreciation
Cost Formula.
$16,600+ $0.14 per machine-hour
$38,300+ $1.20 per machine-hour
$0.80 per machine-hour
$94,700+ $1.70 per machine-hour
$67,600
Required:
1. Calculate the activity variances for March.
2. Calculate the spending variances for March.
During March, the company worked 19,000 machine-hours and produced 13,000 units. The company had originally planned to work
21,000 machine-hours during March.
Actual Cost
in March 1
$ 21,340
$ 57,300
$ 16,600
$ 131,300
$ 69,300
Complete this question by entering your answers in the tabs below.
FAB Corporation
Activity Variances
Far the Manth Endad Merak 10
Required 1 Required 2
Calculate the activity variances for March. (Indicate the effect of each variance by selecting "F" for favorable, "U" for
unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
< Prev
1 of 3
Next >
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 5 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Essentials of Business Analytics (MindTap Course …](https://www.bartleby.com/isbn_cover_images/9781305627734/9781305627734_smallCoverImage.gif)
Essentials of Business Analytics (MindTap Course …
Statistics
ISBN:
9781305627734
Author:
Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:
Cengage Learning
![Cornerstones of Cost Management (Cornerstones Ser…](https://www.bartleby.com/isbn_cover_images/9781305970663/9781305970663_smallCoverImage.gif)
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
![Essentials of Business Analytics (MindTap Course …](https://www.bartleby.com/isbn_cover_images/9781305627734/9781305627734_smallCoverImage.gif)
Essentials of Business Analytics (MindTap Course …
Statistics
ISBN:
9781305627734
Author:
Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:
Cengage Learning
![Cornerstones of Cost Management (Cornerstones Ser…](https://www.bartleby.com/isbn_cover_images/9781305970663/9781305970663_smallCoverImage.gif)
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning