You are working on a construction project. You, your team, and your senior manager all feel that the work is complete. Your stakeholders have communicated their final acceptance of the project. You are now meeting with your team to update the organizational process assets with a record of knowledge gained about the project to help future project managers with their projects. This is BEST described as _____. A. Project records B. Lessons learned C. Project management information system (PMIS) D. Work performance information Which of the following tools is used to document the lessons that were learned when the contract was administered? A. Procurement audit B. Quality audit C. Buyer-conducted performance review D. Contract review
You are working on a construction project. You, your team, and your
senior manager all feel that the work is complete. Your stakeholders have
communicated their final acceptance of the project. You are now meeting
with your team to update the organizational process assets with a record of
knowledge gained about the project to help future project managers with
their projects. This is BEST described as _____.
A. Project records
B. Lessons learned
C. Project management information system (PMIS)
D. Work performance information
Which of the following tools is used to document the lessons that were
learned when the contract was administered?
A. Procurement audit
B. Quality audit
C. Buyer-conducted performance review
D. Contract review