You are the engineer responsible for the design and installation of plumbing in a new public elementary school under construction. The project is running behind schedule ad above budget. The latest catch is that the supplier has not delivered the specified backflow preventers. Although a strike at the manufacturer's plant has been settled, the back order list is moving slowly. The engineer serving as coordinator of the project orders you to obtain less expensive backflow preventers that are readily available from another manufacturer. These backflow preventers are of lesser quality than those specified in the plans, have a history of occasional failure, and are likely to need earlier replacement. What should you do? O A. Order and install the available backflow preventers, but refuse to sign off on this portion of the job. O B. Order and install the available backflow preventers, informing the school board that this equipment may not last as long, but will help the project stay on schedule and closer to budget. O C. Wait for the specified backflow preventers and explain your action to the school board. O D. Order and install the available backflow preventers, and say nothing to the school board.
You are the engineer responsible for the design and installation of plumbing in a new public elementary school under construction. The project is running behind schedule ad above budget. The latest catch is that the supplier has not delivered the specified backflow preventers. Although a strike at the manufacturer's plant has been settled, the back order list is moving slowly. The engineer serving as coordinator of the project orders you to obtain less expensive backflow preventers that are readily available from another manufacturer. These backflow preventers are of lesser quality than those specified in the plans, have a history of occasional failure, and are likely to need earlier replacement. What should you do? O A. Order and install the available backflow preventers, but refuse to sign off on this portion of the job. O B. Order and install the available backflow preventers, informing the school board that this equipment may not last as long, but will help the project stay on schedule and closer to budget. O C. Wait for the specified backflow preventers and explain your action to the school board. O D. Order and install the available backflow preventers, and say nothing to the school board.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
![QUESTION 5
You are the engineer responsible for the design and installation of plumbing in a new public elementary school under construction. The project is
running behind schedule ad above budget. The latest catch is that the supplier has not delivered the specified backflow preventers. Although a
strike at the manufacturer's plant has been settled, the back order list is moving slowly. The engineer serving as coordinator of the project orders
you to obtain less expensive backflow preventers that are readily available from another manufacturer. These backflow preventers are of lesser
quality than those specified in the plans, have a history of occasional failure, and are likely to need earlier replacement. What should you do?
O A. Order and install the available backflow preventers, but refuse to sign off on this portion of the job.
O B. Order and install the available backflow preventers, informing the school board that this equipment may not last as long, but will help the
project stay on schedule and closer to budget.
O C. Wait for the specified backflow preventers and explain your action to the school board.
O D. Order and install the available backflow preventers, and say nothing to the school board.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fb42f7e8f-7cd5-4598-be82-14b19f18dba8%2Ff6ee91c7-cf77-436e-b955-7c168909618a%2Fgpm2mgf_processed.jpeg&w=3840&q=75)
Transcribed Image Text:QUESTION 5
You are the engineer responsible for the design and installation of plumbing in a new public elementary school under construction. The project is
running behind schedule ad above budget. The latest catch is that the supplier has not delivered the specified backflow preventers. Although a
strike at the manufacturer's plant has been settled, the back order list is moving slowly. The engineer serving as coordinator of the project orders
you to obtain less expensive backflow preventers that are readily available from another manufacturer. These backflow preventers are of lesser
quality than those specified in the plans, have a history of occasional failure, and are likely to need earlier replacement. What should you do?
O A. Order and install the available backflow preventers, but refuse to sign off on this portion of the job.
O B. Order and install the available backflow preventers, informing the school board that this equipment may not last as long, but will help the
project stay on schedule and closer to budget.
O C. Wait for the specified backflow preventers and explain your action to the school board.
O D. Order and install the available backflow preventers, and say nothing to the school board.
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning