XYZ Co. would like to install a new computer system, which must be completed in 15 months. Or else, there would be a penalty cost (i.e. ineffective use of resources, extra manpower, etc.) of $4000 for each month beyond 15 months. The direct costs of the installation involves an overhead cost of $600 for each month until completion. The company has two options, either to set up its own team internally or outsource to another company, ABC Ltd., for the installation. If XYZ Co. uses its own team, there is a 30% chance that the installation can be completed in 14 months, 50% chance to be completed in 15 months, and 20% chance to be completed in 16 months. On the other hand, if the project is outsourced to ABC Ltd., there is a 20% chance that the installation can be completed in 13 months, 40% chance to be completed in 14 months, 30% chance to be completed in 15 months, and 10% chance to be completed in 16 months. However, ABC Ltd. requires a bonus of $1000 per month if the project can be completed in less than 15 months. Draw a decision tree for this problem and calculate the EMV for all courses of action. Hence, determine the optimal choice of XYZ Co. based on the EMV criterion.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Photo attached

XYZ Co. would like to install a new computer system, which must be completed in 15
months. Or else, there would be a penalty cost (i.e. ineffective use of resources, extra
manpower, etc.) of $4000 for each month beyond 15 months. The direct costs of the
installation involves an overhead cost of $600 for each month until completion.
The company has two options, either to set up its own team internally or outsource to
another company, ABC Ltd., for the installation. If XYZ Co. uses its own team, there
is a 30% chance that the installation can be completed in 14 months, 50% chance to be
completed in 15 months, and 20% chance to be completed in 16 months. On the other
hand, if the project is outsourced to ABC Ltd., there is a 20% chance that the installation
can be completed in 13 months, 40% chance to be completed in 14 months, 30% chance
to be completed in 15 months, and 10% chance to be completed in 16 months.
However, ABC Ltd. requires a bonus of $1000 per month if the project can be
completed in less than 15 months.
Draw a decision tree for this problem and calculate the EMV for all courses of action.
Hence, determine the optimal choice of XYZ Co. based on the EMV criterion.
Transcribed Image Text:XYZ Co. would like to install a new computer system, which must be completed in 15 months. Or else, there would be a penalty cost (i.e. ineffective use of resources, extra manpower, etc.) of $4000 for each month beyond 15 months. The direct costs of the installation involves an overhead cost of $600 for each month until completion. The company has two options, either to set up its own team internally or outsource to another company, ABC Ltd., for the installation. If XYZ Co. uses its own team, there is a 30% chance that the installation can be completed in 14 months, 50% chance to be completed in 15 months, and 20% chance to be completed in 16 months. On the other hand, if the project is outsourced to ABC Ltd., there is a 20% chance that the installation can be completed in 13 months, 40% chance to be completed in 14 months, 30% chance to be completed in 15 months, and 10% chance to be completed in 16 months. However, ABC Ltd. requires a bonus of $1000 per month if the project can be completed in less than 15 months. Draw a decision tree for this problem and calculate the EMV for all courses of action. Hence, determine the optimal choice of XYZ Co. based on the EMV criterion.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Forecasting methods
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.