Winston's assembly unit has decided to use a p-Chart with an a risk of 1% to monitor the proportion of defective metal shafts produced by their production process. The production manager randomly samples 200 metal shafts at 16 successively selected time periods and counts the number of defective metal shafts in the sample. Table Step 1 of 8: What is the Center Line of the control chart? Round your answer to three decimal places. Answer How to enter your Sample Defects 1 2 9 8 3 4 5 6 7 8 9 10 11 12 13 10 14 13 15 7 16 10 Control Chart 12 12 11 13 7 12 11 11 8 7 The average of the selected cell(s) is8.000. Copy Value Copy Table ypad ortcuts

MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
100%
Winston's assembly unit has decided to use a p-Chart with an a risk of 1 % to monitor the proportion of defective metal shafts produced by their production process.
The production manager randomly samples 200 metal shafts at 16 successively selected time periods and counts the number of defective metal shafts in the sample.
Table
Step 1 of 8: What is the Center Line of the control chart? Round your answer to three decimal places.
Answer
How to enter your
Sample Defects
1
2
9
8
3
4
5
6
7 7
600
12
12
11
13
8 12
9 11
10 11
11
12
13
14
15
16
Control Chart
8
7
10
13
7
10
The average of the selected cell(s) is8.000.
Copy Value
Copy Table
x
ypad
ortcuts
Transcribed Image Text:Winston's assembly unit has decided to use a p-Chart with an a risk of 1 % to monitor the proportion of defective metal shafts produced by their production process. The production manager randomly samples 200 metal shafts at 16 successively selected time periods and counts the number of defective metal shafts in the sample. Table Step 1 of 8: What is the Center Line of the control chart? Round your answer to three decimal places. Answer How to enter your Sample Defects 1 2 9 8 3 4 5 6 7 7 600 12 12 11 13 8 12 9 11 10 11 11 12 13 14 15 16 Control Chart 8 7 10 13 7 10 The average of the selected cell(s) is8.000. Copy Value Copy Table x ypad ortcuts
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
Recommended textbooks for you
MATLAB: An Introduction with Applications
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman