Which of the following is false? If an activity has a slack value greater than zero, it needs to be a critical activity Lateness in activities, which are not located on the critical path, may or may not result in lateness in overall project completion time, depending on their slack time If there is only one activity in a project, it needs to be a critical activity O If Activity A needs to be completed before Activity B starts, Activity A is the immediate predecessor of activity B O Lateness in any of the activities located on the critical path would result in lateness in overall proiect completion time

Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter8: Cost Analysis
Section: Chapter Questions
Problem 9E
icon
Related questions
Question
Which of the following is false?
If an activity has a slack value
greater than zero, it needs to
be a critical activity
O Lateness in activities, which
are not located on the critical
path, may or may not result in
lateness in overall project
completion time, depending on
their slack time
If there is only one activity in a
project, it needs to be a critical
activity
O If Activity A needs to be
completed before Activity B
starts, Activity A is the
immediate predecessor of
activity B
O Lateness in any of the activities
located on the critical path
would result in lateness in
overall proiect completion timo
Transcribed Image Text:Which of the following is false? If an activity has a slack value greater than zero, it needs to be a critical activity O Lateness in activities, which are not located on the critical path, may or may not result in lateness in overall project completion time, depending on their slack time If there is only one activity in a project, it needs to be a critical activity O If Activity A needs to be completed before Activity B starts, Activity A is the immediate predecessor of activity B O Lateness in any of the activities located on the critical path would result in lateness in overall proiect completion timo
If an activity nas a slack value
greater than zero, it needs to
be a critical activity
O Lateness in activities, which
are not located on the critical
path, may or may not result in
lateness in overall project
completion time, depending on
their slack time
O If there is only one activity in a
project, it needs to be a critical
activity
O If Activity A needs to be
completed before Activity B
starts, Activity A is the
immediate predecessor of
activity B
O Lateness in any of the activities
located on the critical path
would result in lateness in
overall project completion time
Transcribed Image Text:If an activity nas a slack value greater than zero, it needs to be a critical activity O Lateness in activities, which are not located on the critical path, may or may not result in lateness in overall project completion time, depending on their slack time O If there is only one activity in a project, it needs to be a critical activity O If Activity A needs to be completed before Activity B starts, Activity A is the immediate predecessor of activity B O Lateness in any of the activities located on the critical path would result in lateness in overall project completion time
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Multiplicative Exponential demand Model
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning
Micro Economics For Today
Micro Economics For Today
Economics
ISBN:
9781337613064
Author:
Tucker, Irvin B.
Publisher:
Cengage,
Survey Of Economics
Survey Of Economics
Economics
ISBN:
9781337111522
Author:
Tucker, Irvin B.
Publisher:
Cengage,
Principles of Economics 2e
Principles of Economics 2e
Economics
ISBN:
9781947172364
Author:
Steven A. Greenlaw; David Shapiro
Publisher:
OpenStax