What is the probability that the project will take between 28 and 32 months? If required, round your answer to four decimal places. (c) To submit a competitive bid, the company believes that if the project takes more than 36 months, then the company will lose money on the project. Management does not want to bid on the project if there is greater than a 25% chance that they will lose money on this project. Should the company bid on this project?
Contingency Table
A contingency table can be defined as the visual representation of the relationship between two or more categorical variables that can be evaluated and registered. It is a categorical version of the scatterplot, which is used to investigate the linear relationship between two variables. A contingency table is indeed a type of frequency distribution table that displays two variables at the same time.
Binomial Distribution
Binomial is an algebraic expression of the sum or the difference of two terms. Before knowing about binomial distribution, we must know about the binomial theorem.
The Siler Construction Company is about to bid on a new industrial construction project. To formulate their bid, the company needs to estimate the time required for the project. Based on past experience, management expects that the project will require at least 24 months, and could take as long as 48 months if there are complications. The most likely scenario is that the project will require 30 months.
(a) | Assume that the actual time for the project can be approximated using a triangular probability distribution. What is the probability that the project will take less than 30 months? If required, round your answer to two decimal places. |
(b) | What is the probability that the project will take between 28 and 32 months? If required, round your answer to four decimal places. |
(c) | To submit a competitive bid, the company believes that if the project takes more than 36 months, then the company will lose money on the project. Management does not want to bid on the project if there is greater than a 25% chance that they will lose money on this project. Should the company bid on this project? |
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 4 images