ނ Using the figure below, write in the appropriate word for a. and b. from these four: (over, under, behind, ahead) Project cost (dollars) ACWP Report date BCWS Schedule variance Cost varlance b. BCWP (earned value) H H + Project duration (typically in months) FIGURE 10.4 General Concepts of Earned Value Analysis. 0 50 50 100 % Budget

Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Saeed Moaveni
Chapter20: Engineering Economics
Section: Chapter Questions
Problem 19P
icon
Related questions
Question

Fill in the blank

ނ
Using the figure below, write in the appropriate word for a. and b. from
these four: (over, under, behind, ahead)
Project cost (dollars)
ACWP
Report date
BCWS
Schedule variance
Cost varlance
b.
BCWP (earned value)
H
H
+
Project duration (typically in months)
FIGURE 10.4 General Concepts of Earned Value Analysis.
0
50
50
100
% Budget
Transcribed Image Text:ނ Using the figure below, write in the appropriate word for a. and b. from these four: (over, under, behind, ahead) Project cost (dollars) ACWP Report date BCWS Schedule variance Cost varlance b. BCWP (earned value) H H + Project duration (typically in months) FIGURE 10.4 General Concepts of Earned Value Analysis. 0 50 50 100 % Budget
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning