Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 Job 2 3 4 The total flow time for the sequence developed using the FCFS rule = days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the FCFS rule = | jobs (round your response to two decimal places). The average tardiness (job lateness) for the sequence developed using the FCFS rule = (round your response to two decimal places). days The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 use the order in which the jobs were received): Sequence Job 1 2 3 Job Date Job Received Due Date Duration (days) BR-02 231 310 30 CX-01 228 300 15 DE-06 225 270 25 RG-05 230 320 35 SY-11 235 360 40 The total flow time for the sequence developed using the EDD rule= to two decimal places). days (round your response The percentage utilization for the sequence developed using the EDD rule = % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the EDD rule = jobs (round your response to two decimal places). The average tardiness (job lateness) for the sequence developed using the EDD rule = days (round your response to two decimal places). Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence 1 2 3 4 5 Job The total flow time for the sequence developed using the SPT rule = [ to two decimal places). days (round your response The percentage utilization for the sequence developed using the SPT rule = % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the SPT rule = jobs (round your response to two decimal places). The average tardiness (job lateness) for the sequence developed using the SPT rule = | (round your response to two decimal places). days Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence 1 Job 2 3 4 The total flow time for the sequence developed using the LPT rule = days (round your response to two decimal places). The percentage utilization for the sequence developed using the LPT rule = % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the LPT rule = jobs (round your response to two decimal places). The average tardiness (job lateness) for the sequence developed using the LPT rule = days (round your response to two decimal places).

Algebra: Structure And Method, Book 1
(REV)00th Edition
ISBN:9780395977224
Author:Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Publisher:Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Chapter2: Working With Real Numbers
Section2.3: Rules For Addition
Problem 8P
icon
Related questions
Question
Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is:
Sequence
1
Job
2
3
4
The total flow time for the sequence developed using the FCFS rule = days (round your
response to two decimal places).
The percentage utilization for the sequence developed using the FCFS rule = % (enter your
response as a percentage rounded to two decimal places).
The average number of jobs in the system for the sequence developed using the FCFS rule = |
jobs (round your response to two decimal places).
The average tardiness (job lateness) for the sequence developed using the FCFS rule =
(round your response to two decimal places).
days
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's
machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which
(day 241 is a work day). Job names refer to names of clients and contract numbers. Compute
all times based on initiating work on day 241.
Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241
use the order in which the jobs were received):
Sequence
Job
1
2
3
Job
Date Job
Received
Due Date Duration (days)
BR-02
231
310
30
CX-01
228
300
15
DE-06
225
270
25
RG-05
230
320
35
SY-11
235
360
40
The total flow time for the sequence developed using the EDD rule=
to two decimal places).
days (round your response
The percentage utilization for the sequence developed using the EDD rule = % (enter your
response as a percentage rounded to two decimal places).
The average number of jobs in the system for the sequence developed using the EDD rule =
jobs (round your response to two decimal places).
The average tardiness (job lateness) for the sequence developed using the EDD rule = days
(round your response to two decimal places).
Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to
resolve a tie, use the order in which the jobs were received):
Sequence
1
2
3
4
5
Job
The total flow time for the sequence developed using the SPT rule = [
to two decimal places).
days (round your response
The percentage utilization for the sequence developed using the SPT rule = % (enter your
response as a percentage rounded to two decimal places).
The average number of jobs in the system for the sequence developed using the SPT rule =
jobs (round your response to two decimal places).
The average tardiness (job lateness) for the sequence developed using the SPT rule = |
(round your response to two decimal places).
days
Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to
resolve a tie, use the order in which the jobs were received):
Sequence
1
Job
2
3
4
The total flow time for the sequence developed using the LPT rule = days (round your response
to two decimal places).
The percentage utilization for the sequence developed using the LPT rule = % (enter your
response as a percentage rounded to two decimal places).
The average number of jobs in the system for the sequence developed using the LPT rule = jobs
(round your response to two decimal places).
The average tardiness (job lateness) for the sequence developed using the LPT rule = days
(round your response to two decimal places).
Transcribed Image Text:Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 Job 2 3 4 The total flow time for the sequence developed using the FCFS rule = days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the FCFS rule = | jobs (round your response to two decimal places). The average tardiness (job lateness) for the sequence developed using the FCFS rule = (round your response to two decimal places). days The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 use the order in which the jobs were received): Sequence Job 1 2 3 Job Date Job Received Due Date Duration (days) BR-02 231 310 30 CX-01 228 300 15 DE-06 225 270 25 RG-05 230 320 35 SY-11 235 360 40 The total flow time for the sequence developed using the EDD rule= to two decimal places). days (round your response The percentage utilization for the sequence developed using the EDD rule = % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the EDD rule = jobs (round your response to two decimal places). The average tardiness (job lateness) for the sequence developed using the EDD rule = days (round your response to two decimal places). Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence 1 2 3 4 5 Job The total flow time for the sequence developed using the SPT rule = [ to two decimal places). days (round your response The percentage utilization for the sequence developed using the SPT rule = % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the SPT rule = jobs (round your response to two decimal places). The average tardiness (job lateness) for the sequence developed using the SPT rule = | (round your response to two decimal places). days Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence 1 Job 2 3 4 The total flow time for the sequence developed using the LPT rule = days (round your response to two decimal places). The percentage utilization for the sequence developed using the LPT rule = % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the LPT rule = jobs (round your response to two decimal places). The average tardiness (job lateness) for the sequence developed using the LPT rule = days (round your response to two decimal places).
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Algebra: Structure And Method, Book 1
Algebra: Structure And Method, Book 1
Algebra
ISBN:
9780395977224
Author:
Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Publisher:
McDougal Littell
Glencoe Algebra 1, Student Edition, 9780079039897…
Glencoe Algebra 1, Student Edition, 9780079039897…
Algebra
ISBN:
9780079039897
Author:
Carter
Publisher:
McGraw Hill
Trigonometry (MindTap Course List)
Trigonometry (MindTap Course List)
Trigonometry
ISBN:
9781305652224
Author:
Charles P. McKeague, Mark D. Turner
Publisher:
Cengage Learning
College Algebra (MindTap Course List)
College Algebra (MindTap Course List)
Algebra
ISBN:
9781305652231
Author:
R. David Gustafson, Jeff Hughes
Publisher:
Cengage Learning
Holt Mcdougal Larson Pre-algebra: Student Edition…
Holt Mcdougal Larson Pre-algebra: Student Edition…
Algebra
ISBN:
9780547587776
Author:
HOLT MCDOUGAL
Publisher:
HOLT MCDOUGAL