Use a forward and a backward pass to determine the critical path, and then fill out the following table. Activity times are in weeks. (For the precedence activities, enter your answers as comma-separated lists. If an activity does not have immediate predecessors, enter NONE Activity Precedence Activities Activity Time (weeks) A B с D E F G H I none none none A,B B, C D A, F E G, H ✓ ✓ 12✔ 10 ] ✔ 2✔ 0 0✔ 0 6 9 10 20 21 ES 23 ✓ 6 4 9 10 21 20 23 LS ✓ 25 x x x x x x x 23 x X 0 EF x 2 x 0x 0 6 x 9 X x 10 x 20 x 21 X 23 X 6 ✔ 6 9 10 21 LF 20 ]✔ 23 ✓ 23✔ 25 ✓ ✓ 0 2✔ 0 0 0 0 Slack 0 ✓ Critical Path? Yes No Yes✔✔✔ Yes Yes Yes Yes 0✔ Yes Yes ✓✓
Use a forward and a backward pass to determine the critical path, and then fill out the following table. Activity times are in weeks. (For the precedence activities, enter your answers as comma-separated lists. If an activity does not have immediate predecessors, enter NONE Activity Precedence Activities Activity Time (weeks) A B с D E F G H I none none none A,B B, C D A, F E G, H ✓ ✓ 12✔ 10 ] ✔ 2✔ 0 0✔ 0 6 9 10 20 21 ES 23 ✓ 6 4 9 10 21 20 23 LS ✓ 25 x x x x x x x 23 x X 0 EF x 2 x 0x 0 6 x 9 X x 10 x 20 x 21 X 23 X 6 ✔ 6 9 10 21 LF 20 ]✔ 23 ✓ 23✔ 25 ✓ ✓ 0 2✔ 0 0 0 0 Slack 0 ✓ Critical Path? Yes No Yes✔✔✔ Yes Yes Yes Yes 0✔ Yes Yes ✓✓
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
100%

Transcribed Image Text:A project network is shown in the figure.
Start
A
B
4
C
9
D
4
E
12
G
3
F
10
HN
H
2
I
2
Finish

Transcribed Image Text:Use a forward and a backward pass to determine the critical path, and then fill out the following table. Activity times are in weeks. (For the precedence activities, enter your answers as comma-separated lists. If an activity does not have immediate predecessors, enter NONE.)
Activity Time (weeks)
Activity Precedence Activities
A
B
с
D
E
F
G
H
I
none
none
none
A, B
B, C
D
A, F
E
G, H
6
lò
4
9
12
10
3
2
2
0
lò
0
0
6
9
10
20
21
ES
23
✓
6
✓
4
9
10
21
20
✓ 23
23
25
LS
X
x
X
X
X
X
Xx
0
X
2
10
6
9
|X 20
10
21
23
EF
x
x
x
X
X
X
X
X
X
6
6
9
10
21
20
23
LF
25
✓
✓
✓
✓
23✔✔
✓
0✔
2
10
10
10
0
0
Slack
0
✓
✓
✓
0✔
Critical Path?
Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
✓✓
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 1 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.