Under an ISO 9000 program, which one of the following employees is responsible for checking completed work to make sure it has been performed to company specifications? A. The maintenance general manager B. The PM program administrator C. A shop foreman D. A maintenance technician
c.a. Under an ISO 9000 program, which one of the following employees is responsible for checking
completed work to make sure it has been performed to company specifications?
A. The maintenance general manager
B. The PM program administrator
C. A shop foreman
D. A maintenance technician
c.b. Which one of the following isn’t a goal of a PM program?
A. Limit downtime
B. Save a company money on maintenance so that the cost of its products stays competitive
C. Keep a machine running within its specifications
D. Use fewer repair parts and less time to install those parts
c.c. Which of the following tasks is an uptime PM task that can be performed while the machine is running
during production?
A. Checking the motor starter contacts for burned and pitted areas
B. Checking for excess noise or vibration on the machine
C. Checking the condition of the coupling
D. Tightening electrical connections