Table 1: Survey Data for site of a Dyke BS IS FS RL Remark 1.655 100.000 TBM THU 5 1.512 Baseline AO 1.480 20 1.495 40 1.580 60 1.830 80 1.740 100 1.950 1.950 120 2.400 140 1.880 160 1.890 180 1.550 200 1.530 220 1.275 240 1.170 260 1.975 1.950 1.165 -20 0.900 -40 1.680 c/s THU5 Table 2: Swelling and Shrinkage factors for the proposed fill material Initial Converted to: Soil Type Soil Condition Bank Loose Compacted Clay Bank 1.00 1.27 0.90 Loose 0.79 1.00 0.71 Compacted 1.11 1.41 1.00 Common earth Bank 1.00 1.25 0.90 Loose 0.80 1.00 0.72 Compacted 1.11 1.39 1.00 Rock (blasted) Bank 1.00 1.50 1.30 Loose 0.67 1.00 0.87 Compacted 0.77 1.15 1.00 Sand Bank 1.00 1.12 0.95 Loose 0.89 1.00 0.85 Compacted 1.05 1.18 1.00 Thumbi Irrigation Scheme in Mzimba district is under threat of flooding. In order to mitigate against the problem, authorities have decided to construct a flood protection bund (Dyke). Figure 1 is a cross section of a 300m long proposed dyke; together with its foundation (key). Survey data for the proposed site of the dyke are presented in Table 1. Table 2 provides swelling and shrinkage factors for the fill material that has been proposed. The dyke dimensions that are given are for a compacted fill. (1) Assume you are in the design office, use both the Simpson Rule and Trapezoidal Rule to compute the total volume of earthworks required. (Assume both the dyke and the key will use the same material). (2) If you are a Contractor, how many days will it take to finish hauling the computed earthworks using 3 tippers of 12m³ each? Make appropriate assumptions. DIKE CROSS SECTION OGL KEY (FOUNDATION) 2m 1m 2m 8m Figure 1: Cross section of Dyke and its foundation 1.5m from highest OGL 0.5m from OGL OGL
Table 1: Survey Data for site of a Dyke BS IS FS RL Remark 1.655 100.000 TBM THU 5 1.512 Baseline AO 1.480 20 1.495 40 1.580 60 1.830 80 1.740 100 1.950 1.950 120 2.400 140 1.880 160 1.890 180 1.550 200 1.530 220 1.275 240 1.170 260 1.975 1.950 1.165 -20 0.900 -40 1.680 c/s THU5 Table 2: Swelling and Shrinkage factors for the proposed fill material Initial Converted to: Soil Type Soil Condition Bank Loose Compacted Clay Bank 1.00 1.27 0.90 Loose 0.79 1.00 0.71 Compacted 1.11 1.41 1.00 Common earth Bank 1.00 1.25 0.90 Loose 0.80 1.00 0.72 Compacted 1.11 1.39 1.00 Rock (blasted) Bank 1.00 1.50 1.30 Loose 0.67 1.00 0.87 Compacted 0.77 1.15 1.00 Sand Bank 1.00 1.12 0.95 Loose 0.89 1.00 0.85 Compacted 1.05 1.18 1.00 Thumbi Irrigation Scheme in Mzimba district is under threat of flooding. In order to mitigate against the problem, authorities have decided to construct a flood protection bund (Dyke). Figure 1 is a cross section of a 300m long proposed dyke; together with its foundation (key). Survey data for the proposed site of the dyke are presented in Table 1. Table 2 provides swelling and shrinkage factors for the fill material that has been proposed. The dyke dimensions that are given are for a compacted fill. (1) Assume you are in the design office, use both the Simpson Rule and Trapezoidal Rule to compute the total volume of earthworks required. (Assume both the dyke and the key will use the same material). (2) If you are a Contractor, how many days will it take to finish hauling the computed earthworks using 3 tippers of 12m³ each? Make appropriate assumptions. DIKE CROSS SECTION OGL KEY (FOUNDATION) 2m 1m 2m 8m Figure 1: Cross section of Dyke and its foundation 1.5m from highest OGL 0.5m from OGL OGL
Fundamentals of Geotechnical Engineering (MindTap Course List)
5th Edition
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter7: Seepage
Section: Chapter Questions
Problem 7.7CTP
Related questions
Question

Transcribed Image Text:Table 1: Survey Data for site of a Dyke
BS
IS
FS
RL
Remark
1.655
100.000
TBM THU 5
1.512
Baseline AO
1.480
20
1.495
40
1.580
60
1.830
80
1.740
100
1.950
1.950
120
2.400
140
1.880
160
1.890
180
1.550
200
1.530
220
1.275
240
1.170
260
1.975
1.950
1.165
-20
0.900
-40
1.680
c/s THU5
Table 2: Swelling and Shrinkage factors for the proposed fill material
Initial
Converted to:
Soil Type Soil Condition Bank
Loose Compacted
Clay
Bank
1.00
1.27
0.90
Loose
0.79
1.00
0.71
Compacted
1.11
1.41
1.00
Common earth Bank
1.00
1.25
0.90
Loose
0.80
1.00
0.72
Compacted
1.11
1.39
1.00
Rock (blasted) Bank
1.00
1.50
1.30
Loose
0.67
1.00
0.87
Compacted
0.77
1.15
1.00
Sand
Bank
1.00
1.12
0.95
Loose
0.89
1.00
0.85
Compacted
1.05
1.18
1.00

Transcribed Image Text:Thumbi Irrigation Scheme in Mzimba district is under threat of flooding. In order to
mitigate against the problem, authorities have decided to construct a flood protection
bund (Dyke). Figure 1 is a cross section of a 300m long proposed dyke; together with its
foundation (key). Survey data for the proposed site of the dyke are presented in Table 1.
Table 2 provides swelling and shrinkage factors for the fill material that has been
proposed. The dyke dimensions that are given are for a compacted fill.
(1) Assume you are in the design office, use both the Simpson Rule and Trapezoidal
Rule to compute the total volume of earthworks required. (Assume both the dyke
and the key will use the same material).
(2) If you are a Contractor, how many days will it take to finish hauling the computed
earthworks using 3 tippers of 12m³ each? Make appropriate assumptions.
DIKE CROSS SECTION
OGL
KEY (FOUNDATION)
2m
1m
2m
8m
Figure 1: Cross section of Dyke and its foundation
1.5m from highest OGL
0.5m from OGL
OGL
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images

Recommended textbooks for you

Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning

Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning

Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning

Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning