The WACC is used as the discount rate to evaluate various capital budgeting projects. However, it is important to realize that the WACC is an appropriate discount rate only for a project of average risk Analyze the cost of capital situations of the following company cases, and answer the specific questions that finance professionals need to address. Consider the case of Turnbull Co. Tumbull Co, has a target capital structure of 58% debt, 6% preferred stock, and 36% common equity. its cost of preferred stock is 12.2. Turnbull can raise all of its equity capital from retained earnings, its cost of common equity will be common equity, it will carry a cost of 16.0% before-tax cost of debt of 11.1%, and 7. However, if it is necessary to raise new its current tax rate is 25%, how much higher will Tumbull's weighted average cost of capital (WACC) be if it has to raise additional common equity capital by issuing new common stock instead of raising the funds through retained earnings? (Note: Round your intermediate calculations

Entrepreneurial Finance
6th Edition
ISBN:9781337635653
Author:Leach
Publisher:Leach
Chapter14: Security Structures And Determining Enterprise Values
Section: Chapter Questions
Problem 1hM
icon
Related questions
icon
Concept explainers
Question
6. Solving for the WACC
The WACC is used as the discount rate to evaluate various capital budgeting projects. However, it is important to realize that the WACC
is an appropriate discount rate only for a project of average risk.
Analyze the cost of capital situations of the following company cases, and answer the specific questions that finance professionals need to address.
Consider the case of Turnbull Co.
Turnbull Co, has a target capital structure of 55% debt, 6% preferred stock, and 36% common equity. It has a before-tax cost of debt of 11.1%, and
its cost of preferred stock is 12.2%
of Turnbull can raise all of its equity capital from retained earnings, its cost of common equity will be 14.7%. However, if it is necessary to raise new
common equity, it will carry a cost of 16.0%
its current tax rate is 25%, how much higher will Turnbull's weighted average cost of capital (WACC) be if it has to raise additional common equity
capital by issuing new common stock instead of raising the funds through retained earnings? (Note: Round your intermediate calculations to two
decimal places)
0 0.04%
O 1.03 %
0 0.65%
Turnbull Co. is considering a project that requires an initial investment of $1,700,000. The firm will raise the $1,700,000 in capital by issuing $750,000
of debt at a before-tax cost of 11.1%, $70,000 of preferred stock at a cost of 12.2%, and $800,000 of equity at a cost of 14.7%. The firm faces a tax
rate of 25%. What will be the WACC for this project?
(Note: Round your intermediate calculations to three decimal places.)
Consider the case of Kuhun Co.
Kuhn Co. is considering a new project that will require an initial investment of $20 million. It has a target capital structure of 35% debt, 2% preferred
stock, and 63% common equity, Kuhn has noncallable bonds outstanding that mature in five years with a face value of $1,000, an annual coupon rate
of 10%, and a market price of $1,050.76. The yield on the company's current bonds is a good approximation of the yield on any new bonds that it
issues. The company can sell shares of preferred stock that pay an annual dividend of $5 at a price of $92.25 per share.
Kuhn does not have any retained earnings evailable to finance this project, so the firm will have to issue new common stack to help fund . Its
common stock is currently selling for $33.35 per share, and it is expected to pay a dividend of $1.35 at the end of next year Flotation costs will
represent 3% of the funds raised by issuing new common stack. The company is projected to grow at a constant rate of 9.2%, and they face a tax
rate of 25% What will be the WACC for this project?
(Note: Round your intermediate calculations to two decimal places)
Transcribed Image Text:6. Solving for the WACC The WACC is used as the discount rate to evaluate various capital budgeting projects. However, it is important to realize that the WACC is an appropriate discount rate only for a project of average risk. Analyze the cost of capital situations of the following company cases, and answer the specific questions that finance professionals need to address. Consider the case of Turnbull Co. Turnbull Co, has a target capital structure of 55% debt, 6% preferred stock, and 36% common equity. It has a before-tax cost of debt of 11.1%, and its cost of preferred stock is 12.2% of Turnbull can raise all of its equity capital from retained earnings, its cost of common equity will be 14.7%. However, if it is necessary to raise new common equity, it will carry a cost of 16.0% its current tax rate is 25%, how much higher will Turnbull's weighted average cost of capital (WACC) be if it has to raise additional common equity capital by issuing new common stock instead of raising the funds through retained earnings? (Note: Round your intermediate calculations to two decimal places) 0 0.04% O 1.03 % 0 0.65% Turnbull Co. is considering a project that requires an initial investment of $1,700,000. The firm will raise the $1,700,000 in capital by issuing $750,000 of debt at a before-tax cost of 11.1%, $70,000 of preferred stock at a cost of 12.2%, and $800,000 of equity at a cost of 14.7%. The firm faces a tax rate of 25%. What will be the WACC for this project? (Note: Round your intermediate calculations to three decimal places.) Consider the case of Kuhun Co. Kuhn Co. is considering a new project that will require an initial investment of $20 million. It has a target capital structure of 35% debt, 2% preferred stock, and 63% common equity, Kuhn has noncallable bonds outstanding that mature in five years with a face value of $1,000, an annual coupon rate of 10%, and a market price of $1,050.76. The yield on the company's current bonds is a good approximation of the yield on any new bonds that it issues. The company can sell shares of preferred stock that pay an annual dividend of $5 at a price of $92.25 per share. Kuhn does not have any retained earnings evailable to finance this project, so the firm will have to issue new common stack to help fund . Its common stock is currently selling for $33.35 per share, and it is expected to pay a dividend of $1.35 at the end of next year Flotation costs will represent 3% of the funds raised by issuing new common stack. The company is projected to grow at a constant rate of 9.2%, and they face a tax rate of 25% What will be the WACC for this project? (Note: Round your intermediate calculations to two decimal places)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Cost of Capital
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Entrepreneurial Finance
Entrepreneurial Finance
Finance
ISBN:
9781337635653
Author:
Leach
Publisher:
Cengage