The trim line at PW is a small subassembly line that, alongwith other such lines, feeds int1, o the final chassis line.The entire assembly line, which consists of more than 900workstations, is to make PW’s new E cars. The trim line itselfinvolves only 13 work elements and must handle 20 cars perhour. Work-element data are as follows:Work Element Time (Sec) Immediate Predecessor(s)A 2.4 NoneB 0.5 NoneC 2.1 NoneD 1.8 CE 1.1 BF 0.9 A G 2 AH 0.7 FI 0.7 DJ 1.8 H, EK 1.3 JL 1.9 GM 1.1 L, I, Ka. Draw a precedence diagram.b. What cycle time (in minutes) results in the desired outputrate?c. What is the theoretical minimum number of stations?d. Use the longest work element decision rule to balance theline and calculate the efficiency of your solution.e. Use the most followers work element decision rule tobalance the line and calculate the efficiency of yoursolution.
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
The trim line at PW is a small subassembly line that, along
with other such lines, feeds int1, o the final chassis line.
The entire assembly line, which consists of more than 900
workstations, is to make PW’s new E cars. The trim line itself
involves only 13 work elements and must handle 20 cars per
hour. Work-element data are as follows:
Work Element Time (Sec) Immediate Predecessor(s)
A 2.4 None
B 0.5 None
C 2.1 None
D 1.8 C
E 1.1 B
F 0.9 A
G 2 A
H 0.7 F
I 0.7 D
J 1.8 H, E
K 1.3 J
L 1.9 G
M 1.1 L, I, K
a. Draw a precedence diagram.
b. What cycle time (in minutes) results in the desired output
rate?
c. What is the theoretical minimum number of stations?
d. Use the longest work element decision rule to balance the
line and calculate the efficiency of your solution.
e. Use the most followers work element decision rule to
balance the line and calculate the efficiency of your
solution.