The traffic on the design lane of a proposed four-lane rural interstate highway consists of 25% trucks. If classification studies have shown that the truck factor be taken as 0.45, design a suitable flexible pavement using the 1993 AASHTO procedure if the AADT on the design lane during the first year of operation is 1885, pi = 4.2. Growth rate = 6.5% Design life = 20 yrs Reliability level = 95% Standard deviation = 0.45 SN, Surface course SN, SN Base course D Subbase course D3 Roadbed course drainage of water

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter19: Design Of Flexible Highway Pavements
Section: Chapter Questions
Problem 16P
icon
Related questions
Question
The traffic on the design lane of a proposed four-lane rural interstate highway consists of 25% trucks. If classification studies have shown that the truck factor can
be taken as 0.45, design a suitable flexible pavement using the 1993 AASHTO procedure if the AADT on the design lane during the first year of operation is
1885, pi = 4.2.
Growth rate = 6.5%
%3D
SN,
Design life = 20 yrs
Reliability level = 95%
Standard deviation = 0.45
Surface course
DI
%3D
SN2
%3D
D2
%3D
SN3
Base course
Subbase course
D3
Roadbed course
The pavement structure will be exposed to moisture levels approaching saturation 20% of the time, and it will take about one week for drainage of water.
Effective CBR of the subgrade material is 7. CBR of the base and subbase courses are 70 and 22, respectively, and Mr for the asphalt mixture, 3102 MPa
(450,000 lb/in?).
Transcribed Image Text:The traffic on the design lane of a proposed four-lane rural interstate highway consists of 25% trucks. If classification studies have shown that the truck factor can be taken as 0.45, design a suitable flexible pavement using the 1993 AASHTO procedure if the AADT on the design lane during the first year of operation is 1885, pi = 4.2. Growth rate = 6.5% %3D SN, Design life = 20 yrs Reliability level = 95% Standard deviation = 0.45 Surface course DI %3D SN2 %3D D2 %3D SN3 Base course Subbase course D3 Roadbed course The pavement structure will be exposed to moisture levels approaching saturation 20% of the time, and it will take about one week for drainage of water. Effective CBR of the subgrade material is 7. CBR of the base and subbase courses are 70 and 22, respectively, and Mr for the asphalt mixture, 3102 MPa (450,000 lb/in?).
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Geometric design of highway facilities
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning