The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Q Normal Time (weeks) 5 7 7 7 1 3 5 4 2 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Time according to schedule (weeks) Time according to schedule (weeks) The cost of shortening of project is $ Activity A B с D E F G H I Activity A B C D E Crash Time (weeks) 4 4 6 6 1 ANNO 3 4 2 2 Cost to Crash ($ per week) (Enter your response as a whole number.) - HG 300 50 300 250 Activity F Н 200 200 Immediate Predecessor(s) 3 2 None None A A B C, D D, E F G
The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Q Normal Time (weeks) 5 7 7 7 1 3 5 4 2 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Time according to schedule (weeks) Time according to schedule (weeks) The cost of shortening of project is $ Activity A B с D E F G H I Activity A B C D E Crash Time (weeks) 4 4 6 6 1 ANNO 3 4 2 2 Cost to Crash ($ per week) (Enter your response as a whole number.) - HG 300 50 300 250 Activity F Н 200 200 Immediate Predecessor(s) 3 2 None None A A B C, D D, E F G
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule.
Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.
Q
Activity
A
B
C
D
E
The cost of shortening of project is $
F
G
H
I
Normal Time
(weeks)
5
7
7
7
1
3
5
4
2
Crash Time
(weeks)
4
4
Activity
A
B
C
D
E
6
4
6
1
3
4
2
2
Cost to Crash
($ per week)
. (Enter your response as a whole number.)
300
50
300
250
200
200
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.)
Time according to
schedule (weeks)
Time according to
schedule (weeks)
Immediate Predecessor(s)
Activity
F
G
H
I
None
None
A
A
B
3~~
C, D
D, E
F
G
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 5 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.